FCICA CIM: Utilizing the Estimate to Establish and Manage Installation Costs

FCICA CIM · Work through your exam, one topic at a time.

All guide sections

Utilizing the Estimate to Establish and Manage Installation Costs

From bid to control baseline

The CIM exam tests whether you can turn a bid estimate into a live cost-control tool, not just a lump sum. The estimate becomes a budget when quantities, production rates, labor burden, material waste, equipment, and indirect costs are assigned cost codes and time-phased to the schedule. Preserve the takeoff assumptions: square footage by product, prep quantities, waste percentage, crew mix, and expected units per installer-day. Labor must carry burden-payroll taxes, workers compensation, liability insurance, and fringe-not just the hourly wage. A schedule of values should follow cost codes and actual progress, not front-load cash.

Managing with production rates

Installer-days equal quantity divided by the production rate. Crew-days equal installer-days divided by crew size. Track actual daily output by cost code; a favorable material variance does not excuse an unfavorable labor variance. Cost-to-complete equals remaining quantity divided by demonstrated daily rate, multiplied by burdened daily cost. Update the budget at buyout because commitments can differ from bid assumptions. Review committed cost, actual cost, and earned value together; otherwise a job can look profitable while losing money.

Worked example

An estimate covers 18,000 sf of VCT at 300 sf per installer-day, four installers, $42 per hour burdened, and eight-hour days. Installer-days = 18,000 ÷ 300 = 60. Crew-days = 60 ÷ 4 = 15. Budgeted labor = 60 × 8 × $42 = $20,160. After three days the crew has installed 4,500 sf. Demonstrated crew rate = 4,500 ÷ 3 = 1,500 sf per day, or 375 sf per installer-day. Remaining 13,500 sf ÷ 1,500 = 9 crew-days. Forecast labor = actual-to-date (3 × 4 × 8 × $42 = $4,032) plus remaining (9 × 4 × 8 × $42 = $12,096) = $16,128. The job trends $4,032 under budget. Check whether the faster rate is sustainable before releasing contingency.

Traps that cost marks

  • Using wage rate instead of burdened rate.
  • Omitting floor prep, mobilization, dumpsters, and temporary protection from cost codes.
  • Treating estimate waste as an installer productivity problem.
  • Pricing changes from stale estimate rates instead of current material and burden.
  • Front-loading the schedule of values or billing percent complete from dollars rather than installed units.