HKIA/ARB PA Paper 1 study materials
HKIA/ARB PA Paper 1 study resources

HKIA/ARB PA Paper 1 cheat sheet

HKIA/ARB PA Paper 1 · Keep the key ideas within reach.

Quick reference

Professional Practice and Legislation (Cap. 408, Code of Conduct, Title, Registration)

  • Architects Registration Ordinance (Cap. 408) is administered by the Architects Registration Board (ARB); the Board registers architects, maintains the register, and handles disciplinary matters.

  • The title "Architect" (and "Registered Architect") is protected: under Cap. 408 only a registered person may use it or hold out as an architect in Hong Kong; unregistered use is an offence.

  • Registration requires the Board's prescribed qualifications plus experience; corporate practice of architecture must be carried on by a registered architect or an approved firm/corporation recognised under the Ordinance.

  • The Code of Professional Conduct is issued by ARB; breaches can trigger disciplinary inquiry, and sanctions include reprimand, conditions, suspension, or removal from the register.

  • Core conduct duties: competence and due care, honesty and integrity, confidentiality, avoidance of conflicts of interest, and disclosure of any interest in a project or supplier.

  • Advertising and publicity must not be misleading or self-laudatory; touting, fee-cutting inducements, and improper solicitation of work are prohibited.

  • Fees: the profession operates on agreed fees; an architect must not accept remuneration from both client and contractor for the same service, nor secret commissions.

  • Continuing professional development (CPD) is a registration/practice expectation; keep records of CPD hours for audit by the Board.

  • Professional indemnity insurance is a practical requirement for practice; the architect's liability may be contractual and in tort for negligence.

Quick reference

Contract and Project Administration (procurement, tendering, contract administration, security of payment adjudication)

  • Procurement routes: traditional (design-bid-build), design-and-build, management contracting, and construction management - each allocates design responsibility and risk differently.

  • Typical tender sequence: prequalification, invitation, issue of tender documents, tender queries and addenda, submission, opening, evaluation, clarification/negotiation, recommendation, award.

  • Tender evaluation criteria must be stated in advance; assess price, programme, method, resources, and qualifications; avoid post-tender changes that undermine fair competition.

  • Contract sum types: lump sum, remeasurement, cost-plus, and guaranteed maximum price (GMP); choose based on design completeness and risk allocation.

  • Standard forms used in Hong Kong include HKIA/HKIS/HKCE joint standard forms of building contract; the contract documents order of precedence governs conflicts.

  • Security of payment: the Construction Industry Security of Payment Ordinance (Cap. 652) provides statutory adjudication for payment disputes, with tight timelines - adjudication must be commenced and decided within statutory periods.

  • Payment claim and payment response mechanism: unpaid party may refer to adjudication; an adjudicator's determination is binding pending final resolution by arbitration/litigation.

  • Contract administration duties: issue instructions, certify payments and extensions of time, value variations, monitor progress, and issue completion/non-completion certificates per the contract.

  • Record keeping is critical: site diaries, minutes, instructions in writing, variation orders, and notices within contractual time limits preserve the architect's position.

Quick reference

Building Technology, Design and Construction (technical design, detailing, materials, construction and site practice)

  • Structural systems: reinforced concrete frames, steel frames, and load-bearing walls; selection depends on span, height, loading, programme, and cost.

  • Concrete: grade denotes characteristic cube strength (e.g., C30); cover to reinforcement protects against corrosion and fire; curing affects strength and durability.

  • Foundations: shallow (pad, strip, raft) versus deep (piles, caissons); choice depends on soil bearing capacity, settlement limits, and groundwater.

  • Fire safety: Buildings Ordinance and Codes of Practice on Fire Safety in Buildings govern means of escape, fire-resisting construction, compartmentation, and access for firefighting.

  • Means of escape: travel distance, exit width, and protected routes; staircases and exit doors must satisfy prescribed requirements.

  • Barrier-free access: Design Manual - Barrier Free Access 2008 sets requirements for ramps, lifts, door widths, and accessible toilets.

  • Building envelope: control of water penetration via damp-proof courses, flashings, cavity drainage, and correct lap detailing; thermal and condensation control by insulation and vapour barriers.

  • Site practice: method statements, temporary works design, scaffolding safety, hoarding, and site supervision; the Authorized Person/Registered Structural Engineer/Registered Geotechnical Engineer supervise under the Buildings Ordinance.

  • Buildings Ordinance: submission of plans for approval, supervision by AP/RSE/RGE, occupation permits, and the Building Authority's power to order rectification of unauthorized building works.

Quick reference

Professional Knowledge and Case Study (case study analysis, examiners' report themes, professional judgement and ethics)

  • Case study approach: identify the parties, contractual relationships, obligations, timeline of events, and the specific issue in dispute before proposing a resolution.

  • Common examiners' themes: failure to issue instructions in writing, inadequate site supervision, late certification, unclear scope, and poor communication with clients and contractors.

  • Conflict of interest: declare any personal or financial interest; where a conflict exists, decline the appointment or obtain informed written consent.

  • Certification duty: the architect must certify honestly and independently, not favouring the client who pays the fee; bias or pressure to under/over-certify is misconduct.

  • Confidentiality: client information must not be disclosed without consent except where required by law or to prevent serious harm.

  • Negligence and liability: duty of care to the client; liability may extend to third parties in limited circumstances; keep records to defend claims.

  • Professional judgement: when facing an ethical dilemma, document the facts, consider the Code of Conduct and Ordinance, seek advice from the Board or professional body, and act transparently.

  • Communication: confirm verbal instructions in writing promptly; keep minutes of meetings and distribute them; ensure decisions and approvals are recorded.

  • Accepting gifts or hospitality: modest hospitality may be acceptable, but gifts that could influence decisions must be declined or disclosed.