Architects Registration Ordinance
Cap. 408 establishes the Architects Registration Board, provides for registration of architects, and regulates professional conduct and discipline in Hong Kong.
Protected title 'Architect'
Under Cap. 408, only registered architects may use the title 'Architect' or hold out as such; unauthorized use is a criminal offence.
Architects Registration Board
Statutory body under Cap. 408 that maintains the register of architects, sets registration requirements, and handles disciplinary inquiries into misconduct.
Code of Professional Conduct
ARB-issued code setting standards of integrity, competence, confidentiality, and conflict avoidance; breaches may lead to disciplinary sanctions including suspension or removal.
Conflict of interest
A situation where personal or financial interest could influence professional judgement; the architect must declare it and avoid or obtain informed consent.
Continuing professional development
Ongoing learning expected of registered architects to maintain competence; records of CPD hours should be kept for audit by the Board.
Professional indemnity insurance
Insurance covering the architect's liability for negligent design or advice; a practical requirement for practice and often a condition of appointment.
Secret commission prohibition
An architect must not accept undisclosed payments or benefits from contractors or suppliers in connection with a project; such conduct is a disciplinary matter.
Traditional procurement
Design-bid-build route where the architect designs fully, then tenders are invited and a contractor builds; design responsibility rests with the client's consultant team.
Design and build
Procurement route where a single contractor is responsible for both design and construction, shifting design coordination risk to the contractor.
Tender evaluation criteria
Pre-stated factors such as price, programme, method, and resources used to compare tenders fairly; changing criteria after receipt undermines fairness.
Lump sum contract
Contract where the contractor agrees a fixed price for defined scope; suitable when design is complete, with variations valued separately.
Security of payment adjudication
Statutory mechanism under Cap. 652 allowing rapid resolution of payment disputes by an adjudicator, binding pending final arbitration or litigation.
Payment claim and response
Formal claim for payment served by a party, answered by a payment response within the statutory period; failure enables adjudication referral.
Extension of time
Contractual adjustment of the completion date for excusable delay; the architect assesses and certifies it per the contract conditions.
Variation order
Written instruction changing the works; it must be valued and recorded, and oral instructions should be confirmed in writing promptly.
Order of precedence
Contract clause ranking documents (e.g., agreement, conditions, specification, drawings) to resolve conflicts when documents are inconsistent.
Reinforced concrete grade
Concrete grade denotes characteristic cube strength (e.g., C30); adequate cover and curing protect reinforcement from corrosion and fire.
Shallow versus deep foundations
Pad, strip, or raft foundations suit adequate bearing strata; piles and caissons transfer loads to deeper, stronger soil or rock.
Means of escape
Fire safety requirements governing travel distance, exit width, and protected routes, set under the Buildings Ordinance and fire safety codes.
Barrier-free access
Design Manual - Barrier Free Access 2008 requirements for ramps, lifts, door widths, and accessible facilities in buildings.
Damp-proof course
Layer in construction resisting moisture movement; combined with flashings and correct laps it controls water penetration through the building envelope.
Buildings Ordinance supervision
Plans require approval, and works must be supervised by an Authorized Person, Registered Structural Engineer, or Registered Geotechnical Engineer.
Occupation permit
Approval issued by the Building Authority permitting occupation after works comply with approved plans and relevant requirements.
Unauthorized building works
Works carried out without approval or contrary to the Buildings Ordinance; the Building Authority may order removal or rectification.
Case study method
Identify parties, contractual relationships, obligations, timeline, and the precise issue before proposing a reasoned professional resolution.
Independent certification
The architect must certify honestly and independently, not favouring the client who pays the fee; bias is professional misconduct.
Confidentiality duty
Client information must not be disclosed without consent except where required by law or to prevent serious harm.
Negligence liability
The architect owes a duty of care to the client; breach causing loss gives rise to liability, so records and clear advice are essential.
Written confirmation
Verbal instructions and decisions should be confirmed in writing promptly, and meeting minutes circulated, to preserve an accurate record.
Gifts and hospitality
Modest hospitality may be acceptable, but gifts capable of influencing decisions must be declined or disclosed under the Code of Conduct.
Examiners' report themes
Recurring weaknesses include unwritten instructions, poor supervision, late certification, unclear scope, and inadequate communication with parties.