- Building Official
- The appointed officer charged with enforcing the code, including issuing permits, conducting inspections, rendering interpretations, approving alternative materials, and issuing notices, orders, and certificates.
- Board of Appeals
- A body established under IBC Section 112 to hear appeals of building official decisions involving code interpretation, application of provisions, or proposed equivalent construction.
- Police Power
- The constitutional authority of the state, delegated to local governments, to adopt and enforce regulations such as building codes to protect public health, safety, and welfare.
- Nonconforming Use
- A lawfully existing building or use that does not comply with current code requirements may continue, but typically cannot be enlarged and may be lost after discontinuance.
- Code Modification Authority
- Under IBC 104.10 the building official may grant case-specific modifications from strict code application where impractical, provided the intent and level of safety are maintained.
- Alternative Materials Approval
- IBC 104.11 allows the building official to approve materials, designs, or methods not prescribed by the code when found equivalent in quality, strength, fire resistance, and safety.
- Right of Entry
- Authority of the code official to enter premises at reasonable times after presenting credentials; refusal is addressed through an inspection warrant or other legal remedy.
- Permit Application Contents
- A complete application identifies the owner and contractor, describes the scope and valuation of work, and includes construction documents and required signatures.
- Construction Documents
- Drawings, specifications, and engineering details submitted with a permit application that must be sufficiently clear to show compliance with all applicable code provisions.
- Permit Expiration Rule
- Under IBC 105.5 a permit becomes invalid if work does not begin within 180 days of issuance or is suspended or abandoned for 180 days after work starts.
- Certificate of Occupancy
- A document issued under IBC Section 111 after final inspection confirming that the building complies with the code for its intended use and occupancy classification.
- Temporary Certificate of Occupancy
- A conditional certificate allowing occupancy of part of a building or before all work is finished, limited by stated conditions and an expiration date.
- Deferred Submittals
- Design elements not included in the original permit application that are submitted and reviewed later under a procedure pre-approved by the building official.
- Valuation-Based Permit Fees
- Permit fees computed from the total construction value or scope of work using a fee schedule adopted by ordinance by the governing jurisdiction.
- Concealed Work Inspection
- Work that will be hidden by subsequent construction must be inspected and approved first; covering it prematurely can require removal for examination by the official.
- Final Inspection
- The last required inspection verifying that all permitted work is complete and compliant, triggering eligibility for a certificate of occupancy.
- Stop Work Order
- A written directive under IBC Section 115 halting work that is unsafe, contrary to code, or proceeding without the required permit, subject to appeal.
- Special Inspection
- Independent inspection under IBC Chapter 17 of critical structural or fire-resistant elements, performed by an approved agency rather than by the jurisdiction's own inspectors.
- Partial Approval
- Approval of a defined portion of inspected work while other items remain incomplete or uncorrected and require follow-up inspection.
- Field Correction Notice
- A document issued at the site listing code deficiencies, the required corrective action, a reinspection deadline, and the consequence of noncompliance.
- Notice of Violation
- A written notice identifying the property, the code section violated, a factual description of the violation, the corrective action required, a deadline, and appeal rights.
- Unsafe Structure
- A structure that is structurally unsafe, unsanitary, or a fire hazard and may be ordered repaired, vacated, or demolished under IPMC Section 108.
- Abatement
- The jurisdiction's correction or removal of a violation when the owner fails to comply, with costs recovered through a lien or special assessment.
- Emergency Measures
- IPMC Section 109 authority to act immediately when a structure poses imminent danger, with notice and an opportunity for hearing provided promptly after the action.
- Civil Penalty
- A monetary sanction imposed through an administrative or judicial process for code violations, often accruing per day until compliance is achieved.
- Condemnation Placard
- A posted notice declaring a structure unsafe for occupancy; removing or defacing it without authorization is itself a violation.
- Performance Measure
- A quantifiable indicator such as plan review cycle time or inspections per inspector, used to evaluate departmental efficiency and service levels.
- Records Retention Schedule
- A legally established timetable specifying how long permit files, inspection records, and enforcement case files must be kept before authorized disposal.
- Continuing Education Units
- Training credits required to renew professional certifications; ICC certifications are maintained on a recurring renewal cycle that mandates documented continuing education.
- Cross-Training
- Preparing staff to perform duties across multiple disciplines so permitting and inspection services continue during absences, vacancies, or peak workloads.
- Interagency Coordination
- Formal procedures or agreements with fire, planning, public works, and health agencies that define referrals, shared reviews, and joint approvals.
- Conflict of Interest