ICC S1 Structural Steel and Bolting study materials
ICC S1 Structural Steel and Bolting study resources

ICC S1 Structural Steel and Bolting study plan

ICC S1 Structural Steel and Bolting · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Bolted Connections: Bolts, Washers, Installation and Tensioning

  • Label the parts of a bolted connection (bolt, nut, hardened washer, hole) and state the function of each in load transfer.

  • Distinguish snug-tight, pretensioned, and slip-critical connections, and state the conditions under which each is permitted.

  • Identify bolt grade markings and state the minimum required bolt tension for common high-strength grades used in structural work.

  • Explain the turn-of-nut, calibrated-wrench, twist-off tension-control, and direct-tension-indicator methods, including required nut rotation by bolt length and diameter.

  • Build a 40-term flashcard deck covering bolt, nut, washer, and hole terminology.

Your checkpoint

Flashcard deck of 40 bolt terms complete plus a self-written 30-question bolt-installation quiz scored at 80% or higher.

Week 2

Bolted Connections: Bolts, Washers, Installation and Tensioning & Structural Steel Materials, Fabrication and Component Verification

  • Sequence the inspection steps for verifying a pretensioned bolt installation, including DTI gap feeler-gauge checks and tension-control bolt tip verification.

  • Compare standard, oversize, short-slotted, and long-slotted holes and state the washer requirements and allowable use for each.

  • Describe proper storage, handling, and field touch-up requirements for high-strength bolts and galvanized fasteners, including conditions that prohibit reuse.

  • Trace a heat of steel from mill certificate to installed member using heat numbers, and list the physical and chemical properties verified on a mill test report.

  • Match common ASTM structural steel and bolt specifications to their intended applications.

Your checkpoint

A one-page bolt installation and inspection sign-off flowchart, plus a 25-question quiz on bolts and material verification scored at 85% or higher.

Week 3

Welded Connections: Welding Processes, Qualification and Weld Inspection

  • Compare shielded metal arc, flux-cored arc, gas metal arc, and submerged arc welding on equipment, electrode handling, position capability, and typical structural applications.

  • Decode an electrode classification number and state the position, coating, current, and strength each designation implies.

  • Explain the relationship among a welding procedure specification, a procedure qualification record, and welder performance qualification, and state who may approve each.

  • List the prequalified joint details and the essential variables that require requalification when changed.

  • Diagram the weld joint types and positions commonly detailed on structural drawings.

Your checkpoint

A written process-comparison matrix for four welding processes plus a completed electrode-classification worksheet, self-scored at 80% or higher on a 20-question quiz.

Week 4

Welded Connections: Welding Processes, Qualification and Weld Inspection

  • Differentiate visual inspection from ultrasonic, radiographic, magnetic particle, and penetrant testing by what each detects and when each is specified.

  • Classify common weld discontinuities (porosity, slag inclusion, incomplete fusion, undercut, cracks) and state the general acceptance disposition of each.

  • Explain the inspector's role in verifying preheat, interpass temperature, heat input, and distortion control before and during welding.

  • Describe the inspection sequence for welded shear studs, including bend testing and ring-gauge checks.

  • Assemble a weld inspection checklist an inspector would carry to a fabrication shop.

Your checkpoint

A 50-question timed exam covering bolting and welding domains, scored at 80% or higher, with every missed item written up as a corrected note.

Week 5

Structural Steel Erection, Framing and Alignment & Structural Steel Materials, Fabrication and Component Verification

  • Outline the contents of an erection plan and identify the stability provisions (temporary bracing, guying, shoring) required before releasing crane loads.

  • Sequence the erection of a multi-story braced frame from anchor-rod survey through final bolting.

  • Explain how anchor rod placement, shimming, grouting, and base plate details affect column alignment.

  • Reproduce the plumbness and alignment tolerance limits for columns and members and state how out-of-tolerance conditions are corrected.

  • Identify when field modification, reaming, or cutting requires engineer approval and documentation.

Your checkpoint

A written erection sequence narrative for a three-story braced frame plus a tolerance table reproduced from memory and checked against the reference standard.

Week 6

Quality Assurance, Inspection and Testing of Steel Construction & Structural Steel Materials, Fabrication and Component Verification

  • Draft an inspection and test plan that assigns hold points, witness points, and surveillance points across fabrication and erection activities.

  • Specify sampling frequencies and verification methods for bolt tensioning, weld inspection, and structural steel material verification.

  • Write a nonconformance report for a simulated failed bolt tension check and route it through disposition and closure.

  • Explain the difference between shop and field quality control responsibilities and the role of third-party inspection.

  • Distinguish destructive from nondestructive verification testing and state when each is warranted.

Your checkpoint

A complete inspection and test plan for a bolted and welded steel frame with at least ten hold points, plus a cumulative mixed-domain exam scored at 80% or higher.

Week 7

Code Administration, Plans and Specification Review for Structural Steel & Special Inspection, Documentation and Reporting

  • Map the responsibilities of the owner, engineer of record, fabricator, erector, and inspector as assigned by the code of standard practice.

  • Assemble a plan-review checklist covering connection details, bolting notes, welding symbols, and inspection requirements, and apply it to a sample drawing set.

  • Trace how the building code chapter on special inspections triggers structural steel special inspection and what the statement of special inspections must contain.

  • Identify the submittals and approvals required before fabrication (shop drawings, erection drawings, procedure specifications, welder qualifications).

  • List the elements of a daily inspection report and a final special inspection report, including documents that must be retained.

Your checkpoint

A completed plan-review checklist against a sample structural drawing set, plus reusable daily and final report templates.

Week 8

Special Inspection, Documentation and Reporting & Bolted Connections: Bolts, Washers, Installation and Tensioning & Welded Connections: Welding Processes, Qualification and Weld Inspection & Structural Steel Erection, Framing and Alignment & Quality Assurance, Inspection and Testing of Steel Construction

  • Write three simulated daily reports that capture location, activity, crew, verification performed, and deficiencies observed.

  • Trace a documentation package from pre-construction submittals through final report and identify gaps that would fail an audit.

  • Re-test the two lowest-scoring domains from earlier weeks and log the specific errors corrected.

  • Complete two full-length timed practice exams under exam conditions.

  • Consolidate all corrected notes into a single pre-exam review sheet of no more than four pages.

Your checkpoint

Two full-length timed practice exams scored at 85% or higher, a four-page review sheet, and a written weak-area remediation log showing closure of every previously missed item.

Milestones

Week 2: Can explain and demonstrate, without notes, the inspection sequence for pretensioned bolts by all four tensioning methods and correctly identify hole type and washer requirements in 9 of 10 drill items.

Week 4: Scores 80% or higher on the 50-question bolting and welding exam and can classify ten weld discontinuities and state their acceptance disposition with 100% accuracy.

Week 6: Produces a defensible inspection and test plan containing at least ten hold points and scores 80% or higher on a cumulative mixed-domain exam covering domains 2 through 6.

Week 8: Scores 85% or higher on two full-length timed practice exams, with no domain below 75% and every missed item closed out in the remediation log.