ICDL Project Planning study materials
ICDL Project Planning study resources

ICDL Project Planning (ICDL) cheat sheet

ICDL Project Planning · Keep the key ideas within reach.

Quick reference

Project planning fundamentals and the project life cycle

  • A project is temporary, creates a unique output and has a defined start and finish; operations are ongoing and repetitive.

  • The triple constraint links scope, time and cost, with quality at the centre: a change to one normally forces adjustment of at least one other.

  • Generic life cycle phases are initiation, planning, execution and closure; monitoring and control runs across all of them.

  • Process groups (initiating, planning, executing, monitoring/controlling, closing) are not the same as phases; they overlap in time.

  • The project charter authorizes the project, names the project manager, and states objectives, high-level scope, budget, milestones and constraints.

  • SMART objectives are specific, measurable, achievable, relevant and time-bound; each objective needs an acceptance criterion.

  • Progressive elaboration (rolling wave planning) means detail and estimate accuracy increase as the project moves forward.

  • A phase gate or stage gate is a formal review where governance decides to continue, revise or terminate; money already spent is irrelevant to that decision.

  • The sponsor funds and authorizes the project and owns the benefits; the project manager delivers the agreed scope within the approved constraints.

Quick reference

Scope definition, deliverables and stakeholder analysis

  • The scope statement records product scope, deliverables, acceptance criteria, exclusions, assumptions and constraints.

  • The WBS is deliverable-oriented and hierarchical; decomposition stops at work packages that can be estimated, scheduled and assigned.

  • 100% rule: the children of every WBS node must sum exactly to the parent, covering all scope and nothing beyond it.

  • A work package is the lowest WBS level, commonly sized at roughly 8 to 80 hours of effort; the WBS dictionary defines its content in detail.

  • A deliverable is a tangible output requiring formal acceptance; a milestone is a zero-duration marker of a significant point or event.

  • Stakeholder analysis maps power and interest: high power/high interest stakeholders are managed closely, low power/low interest are simply monitored.

  • RACI assigns one Accountable per activity, a Responsible doer, two-way Consulted parties and one-way Informed parties.

  • Scope creep is uncontrolled scope growth without change control; gold plating is unrequested extra features added by the team.

  • Every scope change follows: request, impact analysis on scope, time, cost and risk, approval, then baseline update and communication.

Quick reference

Scheduling, activities, dependencies and resource allocation

  • Scheduling sequence: WBS, activity list, sequencing with dependencies, duration estimates, then the schedule baseline.

  • PDM dependency types are finish-to-start (most common), start-to-start, finish-to-finish and start-to-finish (rare); dependencies can also be mandatory, discretionary or external.

  • Lead overlaps a successor with its predecessor; lag inserts waiting time between them.

  • The critical path is the longest path through the network, gives the shortest possible project duration, and has zero total float.

  • Total float = LS minus ES = LF minus EF; free float = early start of the successor minus early finish of the activity.

  • The forward pass sets early start and early finish; the backward pass sets late start and late finish; float is the difference between them.

  • PERT expected duration = (O + 4M + P) / 6; standard deviation = (P minus O) / 6.

  • Crashing adds resources or cost to critical activities; fast tracking runs sequential activities in parallel and raises risk and rework.

  • Resource leveling resolves over-allocation and may extend duration; resource smoothing uses float to flatten peaks without moving the finish date.

Quick reference

Cost estimation, budgeting and risk planning

  • Estimate accuracy improves over the life cycle: rough order of magnitude (minus 25% to plus 75%), budgetary (minus 10% to plus 25%), definitive (minus 5% to plus 10%).

  • Analogous estimating uses a similar past project (fast, low accuracy); parametric uses unit rate times quantity; bottom-up sums work-package estimates (most accurate, most costly).

  • Three-point or PERT estimate = (O + 4M + P) / 6, weighting the most likely value and expressing uncertainty through the range.

  • The cost baseline is the approved, time-phased budget excluding management reserve; it is the reference for measuring cost performance.

  • Contingency reserve covers identified risks (known unknowns), sits inside the baseline and is controlled by the project manager.

  • Management reserve covers unidentified risks (unknown unknowns), sits above the baseline and is released by senior management.

  • Risk process: identify, analyse by probability times impact, plan responses, implement, then monitor and review.

  • Threat responses are avoid, mitigate, transfer and accept; opportunity responses are exploit, enhance, share and accept.

  • EMV = probability times monetary impact; the sum of EMVs of identified risks approximates the contingency reserve needed.

Quick reference

Monitoring, progress reporting and project closure

  • EVM inputs: PV (planned value), EV (earned value), AC (actual cost) and BAC (budget at completion).

  • SV = EV minus PV and CV = EV minus AC; negative values mean behind schedule or over budget.

  • SPI = EV divided by PV and CPI = EV divided by AC; above 1 is favourable, below 1 is unfavourable.

  • EAC = BAC divided by CPI when current cost performance continues; ETC = EAC minus AC; VAC = BAC minus EAC.

  • TCPI = (BAC minus EV) divided by (BAC minus AC): the cost efficiency needed to finish within the remaining budget.

  • Percent complete = EV divided by BAC; S-curves compare planned, earned and actual values over time.

  • Variance thresholds defined in the plan trigger exception reports and escalation to the sponsor or steering committee.

  • Change control: request, impact analysis, CCB decision, baseline and plan update, then communication to stakeholders.

  • Closure: confirm deliverable acceptance, close contracts, release resources, archive records, record lessons learned and issue the final report.