ICDL Project Planning (ICDL) key terms
ICDL Project Planning · Get comfortable with the vocabulary.
- Project
- Related: Project life cycle, Project charter, Deliverable
A temporary effort with a defined start and end, undertaken to create a unique product, service or result within agreed scope, time and cost limits.
- Project life cycle
- Related: Phase, Phase gate
The sequence of phases a project passes through from initiation to closure, typically initiation, planning, execution, monitoring and control, and closing.
- Phase
- Related: Phase gate, Milestone
A distinct, manageable segment of a project that groups related work and ends with a checkpoint where progress and deliverables are reviewed before the next stage begins.
- Phase gate
- Related: Phase, Milestone
A formal review point at the end of a project phase where decision-makers confirm that exit criteria are met and authorise, delay or cancel the next phase.
- Project charter
- Related: Project, Scope statement, Stakeholder
A document that formally authorises a project, names the project manager, states objectives and high-level scope, and records initial constraints, assumptions and success criteria.
- Baseline
- Related: Change control, Progress report
An approved, frozen version of scope, schedule or cost used as the reference against which actual performance and change requests are measured.
- Triple constraint
- Related: Scope statement, Budget, Critical path
The interdependent limits of scope, time and cost that shape a project, where changing one normally requires adjusting at least one of the others; quality is often added as a fourth.
- Assumption
- Related: Constraint, Risk
A factor taken as true for planning purposes without proof; assumptions are recorded so they can be validated and their impact managed if they prove false.
- Constraint
- Related: Assumption, Triple constraint
A restriction or limitation, such as a fixed budget, deadline, mandated technology or legal rule, that reduces the options available when planning and executing a project.
- Scope statement
- Related: Work breakdown structure, Acceptance criteria, Scope creep
A document that defines what the project will and will not deliver, including objectives, deliverables, acceptance criteria, boundaries and key assumptions or constraints.
- Work breakdown structure
- Related: Work package, Deliverable
A hierarchical decomposition of total project scope into progressively smaller deliverables and work packages, forming the basis for estimating, scheduling and assigning responsibility.
- Work package
- Related: Activity, Work breakdown structure
The lowest level of a work breakdown structure: a defined chunk of work with clear output, cost and duration that can be assigned to an owner and estimated reliably.
- Deliverable
- Related: Acceptance criteria, Milestone
A tangible or measurable output, product or service produced by the project, which is formally reviewed and accepted by the customer or sponsor.
- Stakeholder
- Related: Stakeholder analysis, Project charter
Any individual or group with an interest in, influence over, or exposure to the effects of a project, such as the sponsor, team, users and suppliers.
- Stakeholder analysis
- Related: Stakeholder, Project charter
The process of identifying stakeholders and assessing their interest, influence and attitudes so that engagement strategies can be planned and prioritised.
- Scope creep
- Related: Change control, Scope statement
Uncontrolled incremental expansion of project scope without corresponding approval, time or budget adjustments, usually leading to schedule overruns and extra cost.
- Acceptance criteria
- Related: Deliverable, Scope statement
Pre-agreed, testable conditions that a deliverable must satisfy to be accepted by the customer or sponsor, often recorded with requirements or the scope statement.
- Activity
- Related: Dependency, Work package
A discrete piece of work within a work package that has a defined duration, consumes resources and is scheduled within the project timetable.
- Dependency
- Related: Critical path, Network diagram
A logical relationship in a schedule where one activity's start or finish depends on another's, typically finish-to-start, start-to-start, finish-to-finish or start-to-finish.
- Critical path
- Related: Float, Network diagram, Dependency
The longest chain of dependent activities through a project network, which determines the shortest possible project duration; any delay on it delays the whole project.
- Float
- Related: Critical path, Resource levelling
The amount of time an activity can be delayed without delaying the project finish (total float) or the start of a following activity (free float).
- Gantt chart
- Related: Milestone, Dependency, Critical path
A bar chart showing scheduled activities against a calendar timeline, with bars representing duration and often links, milestones and progress shown alongside.
- Network diagram
- Related: Critical path, Dependency
A graphical representation of activities and their logical dependencies, used to analyse sequences and calculate the critical path, float and overall project duration.
- Resource levelling
- Related: Float, Gantt chart
The process of resolving resource conflicts and overloads by adjusting activity start dates within available float, accepting a possible extension to the schedule.
- Milestone
- Related: Phase, Deliverable, Gantt chart
A significant point or event in the project with zero duration, used to mark completion of a key deliverable, an important decision or a phase boundary.
- Cost estimate
- Related: Budget, Bottom-up estimating
A prediction of the costs of project resources and activities, produced at varying levels of accuracy as scope becomes clearer and more detail is known.
- Budget
- Related: Cost estimate, Contingency reserve, Baseline
The approved total of planned expenditure for the project, distributed across cost categories and time periods, against which actual spending is monitored and controlled.
- Contingency reserve
- Related: Risk, Risk register, Budget
Money set aside within the approved budget to cover identified risks and known uncertainties, released when specific risk events occur and their cost impact is confirmed.
- Risk
- Related: Risk register, Risk response
An uncertain event or condition that, if it occurs, affects one or more project objectives; risks are assessed by their probability of occurrence and potential impact.
- Risk register
- Related: Risk, Risk response, Issue log
A document listing identified risks with their causes, probability, impact, severity, owners and planned responses, kept current throughout the project.
- Risk response
- Related: Risk, Contingency reserve
A planned action for handling a risk, such as avoiding, transferring, mitigating or accepting it, chosen according to its severity and the project's risk tolerance.
- Bottom-up estimating
- Related: Cost estimate, Work package
A technique that estimates the cost or duration of each work package in detail and rolls the figures up to a project total, giving high accuracy at high effort.
- Progress report
- Related: Earned value management, Baseline, Issue log
A periodic summary comparing actual scope, schedule and cost performance against the baseline, highlighting variances, issues and planned actions for the next period.
- Earned value management
- Related: Progress report, Baseline
A technique that combines scope, schedule and cost data to measure performance: planned value, earned value and actual cost reveal schedule and cost variances.
- Change control
- Related: Baseline, Scope creep, Issue log
A formal process for reviewing, approving or rejecting requests to alter scope, schedule or budget, and for updating baselines and documents when a change is approved.
- Issue log
- Related: Risk register, Progress report
A record of current problems affecting the project, with owner, priority, status and resolution actions, used to track each issue until it is closed.
- Lessons learned
- Related: Project closure, Post-implementation review
Knowledge captured during or after a project about what worked, what failed and what should be done differently, used to improve future projects.
- Project closure
- Related: Lessons learned, Post-implementation review, Deliverable
The final stage in which deliverables are handed over and accepted, contracts closed, resources released, records archived and a review of performance completed.
- Post-implementation review
- Related: Project closure, Lessons learned
An evaluation carried out after the project has been running long enough to show results, comparing actual benefits and outcomes with those stated in the business case.