ICDL Project Planning (ICDL) study plan
ICDL Project Planning · Give each week a clear focus.
8 weeks · About 7 hours per week
Project planning fundamentals and the project life cycle & Scheduling, activities, dependencies and resource allocation
Map each of the five process groups to a phase of the project life cycle and name the decision gate that closes each phase
Distinguish project, program and portfolio work by writing three original examples of each and stating the boundary test used
Decompose a small sample project (office relocation) into 15 activities and draw them as a precedence diagram
Label all four dependency types (finish-to-start, start-to-start, finish-to-finish, start-to-finish) on that diagram and justify the two leads or lags you introduce
Your checkpoint
One-page life-cycle map plus a 15-activity precedence diagram with all four dependency types labelled and a 150-word written justification of the leads and lags used
Scheduling, activities, dependencies and resource allocation
Perform forward and backward passes on the 15-activity network to derive early and late start and finish dates for every activity
Identify the critical path and compute both total float and free float for each activity
Compress the schedule by three days using crashing and fast-tracking, recording the cost or risk trade-off for each option considered
Level the resource histogram so two over-allocated roles sit within their stated capacity
Your checkpoint
Solved network schedule showing the critical path, a complete float table for all 15 activities, and a before-and-after resource histogram that keeps both roles within capacity
Cost estimation, budgeting and risk planning
Apply analogous, parametric, bottom-up and three-point estimating to the same work package and tabulate how far the four results diverge
Calculate a PERT weighted estimate and state the conditions under which it beats a simple average
Build a time-phased cost baseline that keeps a 10% contingency reserve separate from management reserve
Plot a cumulative S-curve and mark the funding limit and the point at which the reserve is released
Your checkpoint
Cost estimate workbook containing four estimating methods for one work package, a worked PERT calculation, and a cumulative S-curve budget baseline with contingency shown as its own line
Cost estimation, budgeting and risk planning
Score ten project risks on probability and impact with a 5x5 matrix and rank them by exposure
Compute expected monetary value for each risk and derive the total contingency reserve the scores imply
Select a response strategy (avoid, mitigate, transfer, accept, escalate) for every risk and assign an owner and a trigger condition
Separate risks from issues and describe the escalation path each follows
Your checkpoint
Risk register of ten risks with 5x5 scores, EMV calculations, owners, triggers and response strategies, plus a one-page summary of the total contingency reserve
Scope definition, deliverables and stakeholder analysis
Write a scope statement covering in-scope work, explicit exclusions, assumptions, constraints and acceptance criteria
Build a three-level work breakdown structure that passes the 100% rule and assign an accountable owner to each work package
Analyse twelve stakeholders on a power/interest grid and plan a distinct engagement approach for each quadrant
Define three measurable acceptance criteria and name the verification method for each
Your checkpoint
Scope statement, three-level work breakdown structure with a dictionary entry for each lowest-level package, and a stakeholder register of twelve people with power/interest ratings and engagement actions
Monitoring, progress reporting and project closure
Compute planned value, earned value, actual cost, schedule variance, cost variance, SPI and CPI from a six-period dataset
Interpret each index in plain language and forecast estimate at completion using two different formulas
Set variance thresholds that trigger escalation and draft the matching change request for one breach
Produce a one-page status report with a RAG rating and a forecast-to-complete statement
Your checkpoint
Earned value dashboard covering six periods with all seven metrics, two estimate-at-completion forecasts, RAG status and a 200-word variance analysis memo
Monitoring, progress reporting and project closure & Project planning fundamentals and the project life cycle
Run a stage-gate review and record formal acceptance sign-off against each deliverable
Write a closure checklist covering contract close, resource release, records archive and handover
Facilitate a lessons-learned session and convert three findings into specific process changes with owners
Re-test domain 1 concepts (life cycle, roles, governance) and correct the errors carried over from week 1
Your checkpoint
Closure pack containing a signed acceptance log, a completed closure checklist, a lessons-learned register with three process improvements, and a corrected life-cycle map
Scope definition, deliverables and stakeholder analysis & Scheduling, activities, dependencies and resource allocation & Cost estimation, budgeting and risk planning & Monitoring, progress reporting and project closure
Complete two full-length timed mock exams under exam conditions without notes
Log every incorrect answer with the underlying concept and a one-line correction rule
Re-study the three weakest areas named by the error log, rebuilding one worked example for each
Recite the PERT, EMV, float and earned value formulas from memory and check them against a reference
Your checkpoint
Error log of all missed items with correction rules, plus a one-page formula sheet written from memory and a second mock exam score of at least 80%
Milestones
Week 2: Closed-book: derive the critical path and full float table for a 12-activity network in under 40 minutes with no arithmetic errors, scoring at least 85% on a self-marked check
Week 4: Closed-book: produce a time-phased cost baseline with contingency plus a ten-risk register with EMV totals in a single 60-minute sitting, scoring at least 80% on a self-marked check
Week 6: Closed-book: calculate all seven earned value metrics and both completion forecasts from a raw dataset within 30 minutes, then correctly explain any variance above 10%
Week 8: Second full-length mock exam completed within the time limit at 80% or higher, with every remaining error logged and assigned a correction rule