IPMA Level C flashcards
IPMA Level C · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Power/interest grid
- A stakeholder classification tool plotting influence (power) against concern (interest). It sets engagement strategy: manage closely, keep satisfied, keep informed, or monitor.
- Stakeholder salience model
- Classifies stakeholders by power, legitimacy and urgency. One attribute gives a latent stakeholder, two an expectant one, all three a definitive stakeholder owed immediate attention.
- Project governance
- The framework of decision rights, accountability, policies and escalation paths that aligns a project with organisational strategy and defines who decides what, when and how.
- Compliance in projects
- Conformance to mandatory external requirements such as law, regulation and standards, plus internal requirements such as policies, procedures and contractual obligations, throughout the project life cycle.
- Cultural layers
- Culture shows as visible artefacts, espoused values and underlying assumptions. Assumptions are invisible, hardest to change, and most strongly drive behaviour in projects and organisations.
- PESTLE analysis
- A context-scanning technique covering political, economic, social, technological, legal and environmental factors. It identifies external influences that may affect project objectives and risk exposure.
- Strategy alignment
- The traceability of project objectives and deliverables to organisational goals. A project lacking a clear strategic justification should be challenged at the governance level.
- Tuckman team stages
- Forming, storming, norming, performing, adjourning. Conflict typically peaks in storming; the project manager's style should shift from directing to delegating as the team matures.
- Thomas-Kilmann conflict modes
- Five conflict-handling styles: competing, collaborating, compromising, avoiding and accommodating. Collaborating suits high-stakes issues where both task outcome and relationship matter.
- BATNA
- Best Alternative To a Negotiated Agreement: the fallback if no deal is reached. A proposed agreement is acceptable only if it is better than the BATNA.
- ZOPA
- Zone Of Possible Agreement: the overlap between each party's reservation point. If the zones do not overlap, no mutually acceptable deal exists without changing the scope.
- Situational leadership
- Adapting style to follower maturity: directing, coaching, supporting, delegating. Low-competence, low-commitment followers need direction; high-maturity followers need delegation.
- Emotional intelligence
- The set of self-awareness, self-regulation, motivation, empathy and social skill. Self-awareness is the foundation, enabling a project manager to manage reactions and read others accurately.
- Communication feedback loop
- Effective communication requires sender, encoding, medium, decoding, receiver and feedback. Without feedback and attention to noise, the sender cannot confirm the message was understood.
- Personal integrity
- Consistency between stated values and actual behaviour. Decisions that could not withstand public scrutiny indicate an integrity gap that damages stakeholder trust.
- Critical path
- The longest path through the project network. It determines minimum project duration and has zero total float, so any delay on it delays the project completion date.
- Cost variance (CV)
- CV = EV − AC. A negative value means the project has spent more than the value earned to date; a positive value means it is under budget.
- Schedule performance index
- SPI = EV / PV. A value below 1.0 indicates work is progressing slower than planned; above 1.0 indicates it is ahead of the plan.
- Estimate at completion
- EAC = BAC / CPI when current cost performance is expected to continue. ETC = EAC − AC gives the remaining cost; VAC = BAC − EAC gives expected over/underspend.
- Scope baseline
- The approved scope statement, work breakdown structure and WBS dictionary. Changes to any of these components must pass through integrated change control before implementation.
- Threat response strategies
- Avoid, transfer, mitigate, accept or escalate. Choice depends on risk exposure, cost of response and who is best positioned to own the risk.
- Quality assurance vs control
- Assurance is preventive and process-focused, confirming the right processes are used. Control is detective and product-focused, verifying deliverables meet acceptance criteria.
- Requirements traceability
- Each requirement links to a business need and to verification evidence. A requirement that cannot be tested or traced to a need should be rejected or clarified.
- Fixed-price vs reimbursable
- Under fixed-price contracts the seller bears cost risk; under cost-reimbursable contracts the buyer does. Select based on requirement clarity and risk appetite.
- Integrated change control
- The process of reviewing change requests for impact on scope, time, cost, quality and risk, then approving, rejecting and recording decisions before any baseline is updated.
- IPMA 4-L-C levels
- Four certification levels: A (portfolio/director), B (senior project or programme manager), C (project manager), D (project management associate). Complexity and responsibility rise from D to A.
- Level C requirements
- Level C certification requires a written knowledge exam plus a competence-based assessment of demonstrated experience, typically interview or assessment centre, not knowledge alone.
- ICB4 competence rating scale
- Competences are rated from 0 (not applied) to 10 (innovates and teaches others). Assessors look for demonstrated behaviour and evidence, not recited definitions.
- Evidence-based competence claim
- A claim supported by a concrete situation, the actions the candidate personally took, and the outcome. Generic statements without specific examples score poorly in assessment.
- Assessment centre exercises
- Simulations such as presentations, role-plays, interviews and case exercises. Each targets different competences and is scored against ICB4 behavioural indicators.
- Self-assessment before certification
- Candidates map their own experience against ICB4 competences and indicators, identifying strengths and gaps, to prepare evidence for the formal competence assessment.
- Assessor feedback
- Post-assessment feedback references specific ICB4 competence indicators, stating which were demonstrated and which need development, rather than giving a single overall pass or fail comment.