Quick reference

Calibration

  • Percent error = (measured value − true value) ÷ span × 100.

  • For a 4–20 mA transmitter: 4 mA = 0%, 12 mA = 50%, 20 mA = 100% of span.

  • Take test points at 0, 25, 50, 75 and 100% of span in both directions; the downscale pass exposes hysteresis and repeatability.

  • Adjust zero at 0% input first, then span at 100% input, then repeat the full upscale/downscale check.

  • An instrument passes only if its error at every test point lies inside the manufacturer's tolerance; errors are never averaged.

  • Hysteresis = largest difference between upscale and downscale readings taken at the same input value.

  • Reference-standard accuracy should be at least four times better than the device under test (4:1 test uncertainty ratio).

  • A Pt100 changes about 0.385 Ω per °C (100 Ω at 0 °C); thermocouple measurements require cold-junction compensation referenced to 0 °C.

  • Record as-found values before any adjustment and as-left values after; as-found data proves whether the device was in tolerance.

Quick reference

Maintenance and Repair

  • As-found readings are taken before adjustment; they document drift and determine whether the device was within tolerance in service.

  • Apply lockout/tagout, isolate every energy source, and verify zero energy before opening a loop or replacing an instrument.

  • Availability = MTBF ÷ (MTBF + MTTR); MTBF = 1 ÷ failure rate.

  • Preventive maintenance intervals derive from the manufacturer's recommendation, service criticality, and historical failure data.

  • A transmitter output near 3.6 mA indicates a detected internal fault (downscale drive); output near 21 mA often indicates upscale drive.

  • Check the 24 VDC supply at the transmitter terminals under load; open-circuit voltage can look correct while a loaded supply collapses.

  • Replace fuses, gaskets and seals only with the specified rating and material; never upsize a fuse.

  • Impulse lines must slope continuously so gas can return to the process in liquid service and liquid drains back in gas service.

Quick reference

Troubleshooting

  • Isolate the fault by stage: sensor, field wiring, transmitter, I/O card, or control system; inject a known signal to identify the faulty stage.

  • Apply a known mA signal at the transmitter terminals; if the control system reads it correctly, the fault is in the field device or its wiring.

  • HART communication requires at least 250 Ω of loop resistance between the connection point and the power supply.

  • Voltage across a 250 Ω resistor = loop current × 250; 4 mA gives 1 V and 20 mA gives 5 V, so current can be inferred without breaking the loop.

  • A shield grounded at more than one point creates ground loops that appear as noise, offset, or drifting readings.

  • An open RTD or thermocouple produces a burnout indication whose direction (upscale or downscale) is set in the transmitter configuration.

  • A reading that changes when the terminal cover is touched or when ambient temperature shifts points to a cold-junction or connection problem.

  • 0 mA in a 4–20 mA loop means lost power, an open circuit, or a dead transmitter - it is never a valid zero process value.

Quick reference

Project Start-up

  • Verify mechanical completion and close the punch list before energizing power, admitting instrument air, or introducing process fluid.

  • Walk down the P&ID against the installed plant: confirm every tag, location, orientation, and impulse-line connection.

  • Check nameplate data, range, and wetted materials against the instrument index and datasheet before accepting an installation.

  • Confirm the device certificate, gas group and temperature class match the area classification drawing before energizing in a hazardous area.

  • The loop folder contains the instrument index, datasheet, calibration certificate, loop drawing, and completed test records.

  • Instrument air must be dry and oil-free; verify dew point, pressure, and filtration before connecting air to instruments.

  • Bump-test motors to confirm rotation direction before the coupling is installed and the driven equipment is started.

  • FAT is performed at the vendor's works before shipment; SAT verifies installed performance at the plant.

Quick reference

Commissioning

  • Sequence: mechanical completion → loop checks → functional tests → dry commissioning → wet commissioning → performance test.

  • Dry commissioning uses utilities only (power, instrument air, control system) with no process fluid in the lines.

  • A functional test proves the whole loop responds correctly from the sensor input through the control system to the final element.

  • Verify alarm and trip setpoints by driving the input with a calibrated source and recording the exact value at which annunciation occurs.

  • Every deviation between design and as-installed condition is recorded, approved by engineering, and closed before sign-off.

  • Hydrostatic and leak tests are completed and accepted before process fluid is introduced.

  • Initial controller settings are verified and each loop is placed in its designed mode (manual or automatic) before process introduction.

  • Verify DCS/PLC I/O at 0, 50 and 100% for each point and confirm engineering units match the instrument index.

Quick reference

Loop Check

  • A loop check verifies continuity, polarity, and tagging from the field device through the I/O card to the control system and back to the final element.

  • Drive the transmitter with a mA source or HART and confirm the control system indicates the same percentage at 0, 50 and 100%.

  • Drive the controller output from 0 to 100% and confirm the valve or positioner strokes fully with correct position feedback.

  • Record tag number, range, applied input %, indicated output %, and any discrepancy on the loop check sheet.

  • Confirm that failure action on signal or power loss matches the design (fail closed, fail open, or hold last).

  • Maximum loop resistance for a 4–20 mA transmitter ≈ (supply voltage − 12 V) ÷ 0.02 A.

  • Confirm correct polarity and single-point shield grounding at the control-system end of the cable.

  • Alarm and trip annunciation at the operator station is verified during the loop check, before functional testing begins.