ISA CCST Level I study materials
ISA CCST Level I study resources

ISA CCST Level I flashcards

ISA CCST Level I · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Span
The difference between the upper and lower range values; a transmitter ranged 0–100 psig has a span of 100 psi, and 20 mA corresponds to 100%.
Zero shift
An error in which the output at the lower range value is offset while the span stays correct; it is removed by adjusting zero at 0% input.
Hysteresis
The difference between output readings taken at the same input when approached from increasing and decreasing directions; found by running upscale and downscale passes.
Five-point calibration
A check at 0, 25, 50, 75 and 100 percent of span in both directions; the downscale pass exposes hysteresis and repeatability problems.
Test uncertainty ratio
The ratio of the reference standard's accuracy to the accuracy of the device under test; 4:1 is the commonly required minimum for a valid calibration.
Pt100 resistance change
A Pt100 RTD reads 100 Ω at 0 °C and changes about 0.385 Ω per °C, so roughly 138.5 Ω corresponds to 100 °C.
As-found data
Readings recorded before any adjustment; they document the drift since the last calibration and show whether the device was within tolerance.
MTBF
Mean time between failures, equal to one divided by the failure rate; used to set preventive maintenance intervals and spare-parts holdings.
Availability formula
Availability equals MTBF divided by the sum of MTBF and MTTR; reducing repair time raises availability as effectively as reducing failures.
Lockout tagout
An energy-isolation procedure in which every energy source is isolated, locked, tagged, and then verified at zero energy before work begins.
Downscale drive
A transmitter output forced below 4 mA, typically about 3.6 mA, to signal that the device has detected an internal fault or sensor failure.
Breaking the loop
Measuring loop current directly requires opening the circuit and placing the meter in series; measuring voltage across a known resistor avoids breaking it.
Substitution test
Applying a known mA signal at the transmitter terminals; if the control system indicates correctly, the fault lies in the field device or its wiring.
Ground loop symptom
Noise, offset or drifting readings caused by a shield grounded at more than one point; corrected by single-point grounding of the shield.
HART communicator resistance
A HART communicator needs at least 250 Ω of loop resistance between its connection point and the power supply for reliable digital communication.
Voltage across 250 ohms
At 4–20 mA a 250 Ω resistor drops 1–5 V, so measuring this voltage lets you infer loop current without breaking the circuit.
Live zero
Using 4 mA to represent 0% of range so that a failed loop reading 0 mA can be told apart from a genuine zero process value.
Mechanical completion
The state in which all equipment is installed and documented, with punch-list items closed, before power, air, or process fluid is introduced.
Loop folder
The document set for each loop: instrument index, datasheet, calibration certificate, loop drawing, and completed test records.
FAT and SAT
The factory acceptance test is run at the vendor's works before shipment; the site acceptance test confirms installed performance at the plant.
Hazardous area verification
Confirming the installed device's certificate, gas group and temperature class match the area classification drawing before energizing it in a classified location.
Pump bump test
A brief jog of the motor to confirm rotation matches the pump arrow before the coupling is installed and the unit is started.
Commissioning sequence
Mechanical completion, then loop checks, then functional tests, then dry and wet commissioning, then performance testing of the completed system.
Functional test
An end-to-end test proving the loop responds correctly from the simulated sensor input through the control system to the final control element.
Alarm setpoint verification
Driving the input with a calibrated source to the alarm value and recording the exact value at which the operator station annunciates.
Dry commissioning
Testing with utilities only - power, instrument air and the control system - with no process fluid present in the lines.
Deviation record
A documented difference between design and as-installed condition that requires engineering approval and a closed action before sign-off.
Loop check
Verification that wiring, tagging and signal paths are correct from the field device through the I/O card to the control system and back.
Valve stroke test
Driving the controller output from 0 to 100% and confirming the valve or positioner travels fully with correct position feedback.
Fail-safe action
The designed final-element position on signal or power loss, such as fail closed for a fuel gas shutoff valve, verified during loop checks.
Maximum loop resistance
Approximately supply voltage minus 12 V, divided by 0.02 A, for a 4–20 mA transmitter that needs 12 V to operate.
Shield grounding
Grounding the cable shield at one point only, normally the control-system end, to prevent ground loops and induced electrical noise.