GER Licensed Electrical Inspector study materials
GER Licensed Electrical Inspector study resources

GER Licensed Electrical Inspector cheat sheet

GER Licensed Electrical Inspector · Keep the key ideas within reach.

Quick reference

Electrical Theory and Fundamentals

  • Ohm's law: E = I × R; power P = E × I = I²R = E²/R. In AC circuits, use impedance Z in place of R for the full relationship.

  • Series circuit: current is common, resistances add (R_T = R1 + R2 + ...), and voltage divides in proportion to resistance.

  • Parallel circuit: voltage is common, conductances add (1/R_T = 1/R1 + 1/R2 + ...), and current divides inversely with resistance.

  • Effective (RMS) AC voltage of a sine wave = peak ÷ √2; average voltage of a full-wave rectified sine = 0.637 × peak.

  • Three-phase power: P = √3 × E_line × I_line × power factor for a balanced load; single-phase P = E × I × PF.

  • Conductor resistance rises with temperature for copper and aluminum; ampacity tables assume an ambient of 30°C (86°F) for conductors and 40°C for some equipment ratings.

  • Power factor = true power (watts) ÷ apparent power (volt-amperes); a lagging power factor indicates inductive load such as motors.

  • Skin effect and proximity effect increase AC resistance at higher frequencies and in large conductors, which is why large sizes are paralleled.

Quick reference

Wiring Methods and Materials

  • Conductors in parallel must be 1/0 AWG or larger, of the same material, same length, same insulation type, and terminated alike; each raceway may contain only one set unless otherwise permitted.

  • NM-B cable is limited to normally dry locations and must be protected where passing through framing; it cannot be installed in wet locations or embedded in masonry.

  • RMC and IMC require threaded connections or listed fittings; PVC conduit requires expansion fittings where thermal expansion exceeds 1/4 in. per 100 ft of run.

  • Box fill is calculated by counting each conductor, each yoke device, each clamp, and equipment grounding conductors, then comparing to the box's marked volume in cubic inches.

  • Support intervals: NM cable every 4.5 ft and within 12 in. of boxes; RMC/IMC every 10 ft; EMT every 10 ft with a maximum of 5 ft between a coupling and a box.

  • Conductor ampacity is adjusted for ambient temperature and for more than three current-carrying conductors in a raceway or cable, per the adjustment tables.

  • Minimum burial depth for direct-buried cable is typically 24 in.; for rigid metal conduit it is 6 in. under a building or 18 in. elsewhere, per the applicable table.

Quick reference

Branch Circuits, Feeders, and Service Calculations

  • Continuous loads are calculated at 125% of the load for branch-circuit and feeder sizing; noncontinuous loads at 100%.

  • Standard general lighting load for dwellings is 3 VA per square foot; small-appliance branch circuits are 1,500 VA each and laundry is 1,500 VA.

  • Dwelling service demand factors: first 3,000 VA at 100%, then 35% of the remainder from 3,001 to 120,000 VA, then 25% above 120,000 VA.

  • A 20 A small-appliance branch circuit may supply receptacles in kitchen, dining, pantry, and similar areas; at least two such circuits are required in a dwelling.

  • Receptacle spacing in dwelling habitable rooms: no point along the floor line is more than 6 ft from a receptacle, and any wall space 2 ft or wider needs one.

  • Feeder and service neutral load is the maximum unbalanced load; it may be reduced to 70% of the load exceeding 200 A for dwellings, with restrictions on nonlinear loads.

  • Voltage drop is not a code-mandated limit but a recommended practice: keep branch circuits under 3% and the total feeder plus branch under 5%.

Quick reference

Grounding, Bonding, and Overcurrent Protection

  • The service neutral (grounded conductor) is bonded to the equipment grounding system only at the service disconnecting means; downstream panels use separate neutral and ground bars.

  • Standard overcurrent device ratings: 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100 A, then in 50 A increments above 100 A.

  • The next-higher standard rating may be used where the conductor ampacity does not correspond to a standard rating, provided the load does not exceed the conductor ampacity.

  • Equipment grounding conductor sizing follows the table keyed to the rating of the overcurrent device protecting the circuit, not to the phase conductor size alone.

  • Grounding electrode conductor sizing is based on the largest ungrounded service conductor; bonding jumpers around water meters and at fittings must be sized accordingly.

  • GFCI protection is required for dwelling bathroom receptacles, kitchen countertop receptacles, garages, outdoors, and unfinished basements.

  • AFCI protection is required for most 120 V branch circuits in dwelling living areas, including bedrooms, and must be listed for the circuit.

  • A grounded conductor may not be used as an equipment grounding conductor on the load side of the service disconnecting means.

Quick reference

Electrical Inspection Procedures and Documentation

  • A typical inspection sequence is rough-in (before cover), then final; concealed work cannot be approved after it is covered without verification.

  • The inspection record should identify the permit number, the code edition adopted, the circuits or equipment inspected, and the result as approved, approved with corrections, or rejected.

  • Correction notices should cite the specific code section, the location, and the corrective action required, so the contractor can respond without ambiguity.

  • Continuity and polarity tests verify grounding conductor continuity, correct neutral-to-ground separation, and that the grounded conductor is not switched.

  • Insulation resistance testing with a megohmmeter is a diagnostic tool; results below 1 megohm per 1,000 V of test voltage warrant investigation.

  • Field-testing records should note the instrument, its calibration date, the test method, and the readings, because the record may be needed if a dispute arises.

  • A reinspection should confirm each cited correction was completed; new deficiencies observed during reinspection should be documented as separate items.

Quick reference

Code Enforcement and Plan Review

  • Plan review verifies service and feeder calculations, conductor and overcurrent sizing, grounding, and working clearances before construction begins.

  • The adopted code edition and any local amendments govern; where editions conflict, the locally adopted version controls the permit.

  • Working clearance in front of electrical equipment is at least 36 in. deep, 30 in. wide, and 6 ft 6 in. high, with the depth increased for higher voltages.

  • A dedicated equipment space above and in front of switchboards and panelboards must be kept clear of piping, ducts, and foreign systems.

  • Service disconnecting means must be installed at a readily accessible location nearest the point of entry of the service conductors, with the number of disconnects limited.

  • Plan review should confirm that the available fault current does not exceed the interrupting rating of the overcurrent devices installed.

  • Where a code requirement is ambiguous, a written interpretation should be issued and retained so enforcement is consistent across inspectors.

Quick reference

Special Occupancies, Equipment, and Hazardous Locations

  • Class I locations involve flammable gases or vapors; Class II involves combustible dust; Class III involves ignitable fibers or flyings.

  • Divisions: Division 1 is where the hazard exists under normal conditions; Division 2 is where it exists only under abnormal conditions.

  • Zones 0, 1, and 2 correspond to Class I continuous, intermittent, and abnormal presence of gas; Zones 20, 21, and 22 correspond to dust.

  • Equipment in hazardous locations must be marked with its class, division or zone, and group; the marking must match the area classification.

  • Seals are required in conduit systems entering hazardous locations to prevent the passage of gases or vapors, and at specified distances from the enclosure.

  • Bathroom and wet-location receptacles require GFCI protection; swimming pool equipment requires equipotential bonding of metal parts and the water.

  • Health care facility critical branch circuits must be kept separate from other circuits and must not be connected to the general care branch.

Quick reference

Safety, Liability, and Professional Ethics

  • The inspector's authority derives from the adopted code and local ordinance; the inspector does not design the installation or direct the contractor's means and methods.

  • Approval of a portion of an installation does not relieve the installer of responsibility for code compliance of the entire installation.

  • An inspector should disclose any financial interest in the work being inspected and should decline the assignment where a conflict exists.

  • Inspection findings should be factual and specific; opinions about the contractor's competence belong in a separate record, not in the correction notice.

  • Personal protective equipment for electrical inspection includes arc-rated clothing and face protection when working near energized equipment.

  • Liability exposure is reduced by documenting the code basis for each decision and by retaining inspection records for the period required by the jurisdiction.