KSE Professional Engineer flashcards
KSE Professional Engineer · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Hooke's law
- Within the linear-elastic range, stress is proportional to strain: σ = Eε, where E is Young's modulus. The relationship ceases at the proportional limit and is not valid after yielding.
- Factor of safety
- Ratio of a material's failure strength to the allowable working stress. It accounts for load uncertainty, material variability, and consequences of failure; higher values apply where failure is catastrophic.
- Carnot efficiency
- Maximum theoretical efficiency of a heat engine operating between two reservoirs: η = 1 − T_cold/T_hot, with absolute temperatures. No real cycle can exceed this limit.
- Reynolds number
- Dimensionless ratio Re = ρVD/μ used to predict flow regime. In pipes, laminar flow generally occurs below about 2,000 and turbulent flow above about 4,000.
- Bernoulli equation
- For steady, incompressible, frictionless flow along a streamline, p/γ + V²/2g + z is constant. It expresses conservation of energy between pressure, velocity, and elevation.
- Von Mises criterion
- A yield criterion for ductile materials stating that yielding occurs when the distortion energy reaches a critical value. It is preferred over maximum shear stress for most static ductile design.
- Endurance limit
- The stress amplitude below which a material, typically steel, exhibits effectively infinite fatigue life on an S-N curve. Nonferrous metals often lack a true endurance limit.
- Miner's rule
- Cumulative fatigue damage rule: Σ(n_i/N_i) = 1 at predicted failure, where n_i is applied cycles and N_i is cycles to failure at stress level i. It assumes linear damage accumulation.
- Stress concentration factor
- K_t is the ratio of maximum local stress to nominal stress at a geometric discontinuity such as a hole or fillet. It is applied to nominal stress to estimate peak stress.
- Critical path
- The longest-duration sequence of dependent activities through a project network. It determines the minimum project duration and has zero total float.
- Earned value CPI
- Cost performance index CPI = EV/AC, where EV is earned value and AC is actual cost. A CPI below 1.0 indicates the project is over budget relative to work performed.
- PERT expected duration
- Weighted estimate t_E = (O + 4M + P)/6 using optimistic, most likely, and pessimistic durations. Standard deviation is (P − O)/6 for the activity.
- Total float
- The amount of time an activity can be delayed without delaying the project finish, calculated as LS − ES or LF − EF. Critical activities have zero total float.
- ASME Section IX
- The section of the ASME Boiler and Pressure Vessel Code governing qualification of welding procedures and welders. Procedure qualification is documented by a PQR supporting a WPS.
- ASME B31.3
- The ASME code for process piping, covering design, materials, fabrication, inspection, and testing. It applies to piping in chemical, petroleum, and similar process facilities.
- API 510
- API standard for in-service inspection, repair, alteration, and rerating of pressure vessels. It complements ASME Section VIII, which governs new construction.
- ISO 9001
- International standard specifying requirements for a quality management system. It emphasizes process approach, customer focus, and risk-based thinking, and is certifiable by accredited bodies.
- Hierarchy of controls
- Ranking of hazard controls from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment. PPE is the last line of defense.
- Permit-required confined space
- A space with a hazardous atmosphere, engulfment potential, entrapment configuration, or other serious hazard. Entry requires a permit, atmospheric testing, an attendant, and a rescue plan.
- LEL and UEL
- Lower and upper explosive limits define the concentration range in air within which a flammable gas can ignite. Combustible gas detectors commonly alarm at 10% and 25% LEL.
- Lockout/tagout
- Energy control procedure under 29 CFR 1910.147 requiring isolation, lock and tag application, and verification of zero energy before servicing. Locks are removed only by the applying employee.
- Magnetic particle testing
- A nondestructive method that detects surface and near-surface discontinuities in ferromagnetic materials by magnetic flux leakage. It does not apply to austenitic stainless steel or aluminum.
- Gauge R&R
- Measurement system analysis estimating repeatability and reproducibility as a percentage of tolerance. Below 10% is generally acceptable; above 30% is typically unacceptable.
- Process capability Cpk
- A centered capability index equal to the lesser of (USL − μ)/(3σ) and (μ − LSL)/(3σ). It accounts for process centering, unlike Cp, and higher values indicate fewer defects.
- Hydrostatic test
- Pressure test using water to verify structural integrity of vessels or piping. Test pressure is commonly 1.3 times maximum allowable working pressure adjusted for allowable stress ratios.
- Ultrasonic testing
- Nondestructive method using high-frequency sound waves to detect internal flaws and measure thickness. It requires a coupling medium and skilled interpretation of signal indications.
- Paramountcy of public safety
- The first canon of engineering ethics: engineers shall hold paramount the safety, health, and welfare of the public. It overrides obligations to clients or employers when conflict arises.
- Competence limitation
- Ethical rule that engineers perform services only in areas of their competence. Accepting work outside one's expertise without qualification or supervision is a violation.
- Conflict of interest
- A situation where personal or financial interests could impair professional judgment. It must be disclosed promptly, and compensation from multiple parties for the same service requires disclosure.
- Seal and signature
- The professional engineer's seal certifies that work was prepared by or under the direct supervision of the licensee. Affixing it to work not so prepared is misconduct.
- As-built drawings
- Drawings revised to reflect actual installed conditions after construction. They are distinguished from design drawings and are essential for future maintenance and modification.
- Document control
- System ensuring that only current, approved documents are used. It includes unique identification, revision status, distribution records, and removal of obsolete copies from points of use.