KSE Professional Engineer: Project Planning and Management

KSE Professional Engineer · Work through your exam, one topic at a time.

All guide sections

Project Planning and Management

Planning, scheduling, and control

This domain tests the management systems that keep engineering work within scope, schedule, cost, and risk. Questions often require interpreting earned-value data, network logic, or change control rather than reciting definitions.

Core rules

  • Decompose scope into a WBS; every work package needs an owner, deliverable, duration, and cost account.
  • In a precedence network, the critical path has zero total float; delaying it delays the project. Total float is not the same as free float.
  • Earned value: CV = EV − AC; SV = EV − PV; CPI = EV/AC; SPI = EV/PV. CPI or SPI below 1.0 signals unfavorable performance.
  • Manage changes through formal request, impact assessment, approval, and baseline update; do not let scope creep enter through verbal instructions.
  • Keep a risk register with probability, impact, owner, response, and trigger.

Worked example

A work package has PV = 200 million KRW, EV = 180 million, and AC = 210 million at the status date. CV = 180 − 210 = −30 million; SV = 180 − 200 = −20 million; CPI = 180/210 = 0.857; SPI = 180/200 = 0.90. The project is over budget and behind schedule. Cost performance is worse: each unit of earned value costs about 1.17 units of actual cost. A recovery plan should address cost drivers before schedule compression, because crashing may increase AC further.

Traps

Reversing CV and SV signs; using AC in the SPI numerator; treating total float as available on the critical path; and approving a schedule recovery plan without updating the cost baseline.