LA Landscape study materials
LA Landscape study resources

LA Landscape cheat sheet

LA Landscape · Keep the key ideas within reach.

Quick reference

Project and Construction Administration

  • Contract types: lump sum (fixed price for defined scope), unit price (paid per measured quantity, used when quantities are uncertain), cost-plus-fee (owner bears cost risk; used for undefined or fast-track work), and time-and-materials.

  • Standard AIA-style roles: owner, architect/landscape architect, contractor, and construction manager. In design-bid-build the LA administers the contract but does not supervise means and methods, which belong to the contractor.

  • Bid package essentials: drawings, specifications, bid form, instructions to bidders, general and supplementary conditions, addenda, and alternates. Addenda issued during bidding become part of the contract.

  • Pay applications are certified by the contractor, reviewed by the LA for percentage of work in place, and typically retain 5-10% retainage until substantial completion.

  • Substantial completion triggers warranty start, owner occupancy, and release of some retainage; final completion follows punch-list closeout and release of final payment.

  • Change order vs. construction change directive: a change order is signed by all parties; a CCD directs work before price agreement is reached and is later converted to a change order.

  • Critical-path schedule logic: float is the slack in a non-critical activity; delaying an activity beyond its total float delays the project and may support a time extension claim.

  • Submittal review stamps: approved, approved as noted, revise and resubmit, rejected, and submit specified item. The LA's review does not relieve the contractor of responsibility for compliance.

Quick reference

Inventory and Analysis

  • Site inventory covers physical (topography, soils, hydrology, vegetation, climate), biological, cultural (land use, circulation, views), and legal/regulatory data; analysis interprets constraints and opportunities from that data.

  • Slope classes: 0-3% generally buildable and accessible; 3-8% buildable with grading; 8-15% requires terracing and careful erosion control; over 15-25% is severely limited and often protected.

  • USDA soil textural triangle: sand, loamy sand, sandy loam, loam, silt loam, clay loam, silty clay, and clay. Loam (roughly 40% sand, 40% silt, 20% clay) is the agronomic ideal.

  • Site carrying capacity and suitability analysis use overlay mapping (McHarg method) to combine factor layers such as slope, soils, floodplain, and vegetation into a composite suitability map.

  • Sun and shadow study: solar altitude and azimuth vary with latitude and season; winter sun angles are low and shadows long; summer angles are high and shadows short.

  • Drainage patterns: dendritic (branching, uniform soils), radial (conical peaks), trellised (folded strata), and deranged (glaciated, poorly integrated).

  • Viewshed analysis maps the area visible from a point or route; it combines elevation data with observer height and screening vegetation or structures.

  • Data sources: USGS topographic quadrangles, NRCS soil surveys and Web Soil Survey, FEMA flood insurance rate maps, LiDAR-derived DEMs, and aerial/satellite imagery.

Quick reference

Design and Construction Documentation

  • Drawing set order: cover and index, general notes and legends, demolition, site layout and grading, utility and drainage plans, planting plans, irrigation, details, and schedules.

  • Scale conventions: site plans 1"=20' to 1"=50'; grading and utility plans 1"=10' to 1"=20'; details 1"=1' or larger; planting plans commonly 1"=10' to 1"=20'.

  • Plan symbols: spot elevations as decimal feet (e.g., 102.50), contour intervals typically 1' or 2' for site work, flow arrows, and benchmark references tied to a known datum.

  • Specification format follows CSI MasterFormat divisions; site work falls in Division 31 (earthwork), 32 (exterior improvements), and 33 (utilities), with landscape planting in Division 32.

  • Plant schedule fields: symbol, botanical name (genus, species, cultivar), common name, size (caliper or height/spread), root condition (B&B, container, bare root), quantity, and remarks.

  • Construction documents must be coordinated across disciplines; conflicts between architectural, civil, and landscape sheets are resolved before bid, with the most stringent requirement governing.

  • Shop drawings and samples are contractor-prepared documents showing fabrication details; they are reviewed for design intent, not for dimensional or field verification.

  • Record drawings (as-builts) document actual installed conditions and are prepared from contractor markups for the owner's facility records.

Quick reference

Grading, Drainage, and Stormwater Management

  • Slope formula: S (%) = (rise/run) x 100. A 2% slope drops 2 feet per 100 feet; 1% = 1/8 inch per foot; 2% = 1/4 inch per foot.

  • Minimum grades: 1-2% for paved walks and plazas for positive drainage; 0.5% minimum for swales and pipes; 4.76% is the maximum ADA ramp slope, with 8.33% maximum cross slope on accessible routes being 2%.

  • Rational method: Q = CiA, where Q is peak flow (cfs), C is runoff coefficient, i is rainfall intensity (in/hr), and A is area (acres).

  • Runoff coefficients: lawn 0.15-0.35, gravel 0.35, asphalt 0.85-0.95, concrete 0.90, roofs 0.90-0.95, undeveloped woodland 0.05-0.25.

  • Manning's equation for open channels and pipes: Q = (1.486/n) A R^(2/3) S^(1/2), where n is roughness, R is hydraulic radius, and S is slope.

  • Stormwater volume control: detention holds runoff temporarily and releases it slowly; retention holds water permanently (ponds, basins); infiltration practices include bioretention, permeable pavement, and dry wells.

  • Grading rules: slope away from buildings at minimum 2% for the first 10 feet; never drain toward foundations; use swales and berms to direct flow to inlets or infiltration areas.

  • Cut and fill balance minimizes haul: average end area method computes volume as V = (A1 + A2)/2 x L for each segment; shrinkage and swell factors adjust for soil compaction.

Quick reference

Soil, Water, and Vegetation Management

  • Soil profile horizons: O (organic), A (topsoil), E (eluviated), B (accumulation), C (parent material), R (bedrock). Topsoil depth of 6 inches is a common minimum for planting beds.

  • Soil pH ranges: most landscape plants tolerate 6.0-7.0; acid-lovers (rhododendron, blueberry, azalea) need 4.5-5.5; alkaline-tolerant species include juniper and lavender.

  • CEC (cation exchange capacity) measures a soil's ability to hold nutrients; high clay and organic matter raise CEC; sandy soils leach nutrients readily.

  • Irrigation: evapotranspiration (ET) drives scheduling; drip irrigation is 90%+ efficient, sprinklers 60-80%, and overhead flooding less. Apply water to the root zone depth, not the surface.

  • Macronutrients N-P-K (nitrogen, phosphorus, potassium); nitrogen drives vegetative growth, phosphorus supports roots and flowers, potassium supports stress tolerance and fruiting.

  • Planting specifications: root ball diameter is roughly 10-12 inches per inch of trunk caliper; planting hole should be 2-3 times the root ball width and no deeper than the root ball.

  • Native and adapted plant selection reduces irrigation and maintenance; invasive species (e.g., kudzu, English ivy, Japanese knotweed) displace natives and are regulated in many jurisdictions.

  • Tree protection: critical root zone (CRZ) is often defined as 1 foot of radius per inch of trunk diameter; fencing is required before demolition and grading begins.

Quick reference

Materials, Methods, and Construction Detailing

  • Concrete: 4-inch minimum for pedestrian walks, 6 inches for vehicular drives, with 4,000 psi typical; control joints at 1-1.5 times slab thickness in feet (e.g., 10-15 feet for a 4-inch slab).

  • Pavers: flexible (sand-set) vs. rigid (mortar-set) systems; base depth of 4-6 inches compacted aggregate for pedestrian, 8-12 inches for vehicular; edge restraint is required.

  • Wood decay resistance: naturally durable species (cedar, black locust, ipe) vs. pressure-treated (ACQ, copper azole); fasteners must be stainless or hot-dip galvanized to avoid corrosion.

  • Retaining walls: gravity walls rely on mass; cantilever walls use a footing and stem; segmental block walls need geogrid reinforcement above certain heights (often 4 feet).

  • Drainage details: weep holes and drainage gravel behind retaining walls, footing drains with filter fabric, and subgrade drains under paving to prevent frost heave and saturation.

  • Pond and water feature details: liner (EPDM, PVC, or bentonite), underlayment, edge treatment (coping, boulder, or shelf), and aeration or circulation to prevent stagnation.

  • Fencing and site furnishings: post embedment depth typically 1/3 of post height plus 6 inches; concrete footings sized to frost depth in cold climates.

  • Erosion control: silt fence, straw wattles, inlet protection, and temporary seeding; BMPs must be installed before grading and maintained until stabilization.

Quick reference

Site Planning and Land Use

  • Zoning regulates use, density, floor area ratio (FAR), lot coverage, setbacks, height, and parking; FAR = gross floor area / lot area.

  • Parking demand: typical ratios are 1 space per 250-350 sf of office, 1 per 100-200 sf of retail, and 1 per dwelling unit; shared parking can reduce total demand.

  • Accessible routes must connect site arrival points to building entrances; maximum running slope 1:20 (5%), maximum cross slope 1:48 (2%), and clear width 36 inches minimum.

  • Accessible parking: 96-inch-wide spaces with 60-inch access aisles; van-accessible spaces are 132 inches wide (or 96 inches plus an access aisle) and must be signed.

  • Transit-oriented and mixed-use planning reduce vehicle trips; walkability measures include intersection density, block length, and sidewalk continuity.

  • Floodplain management: the 100-year floodplain (1% annual chance) is regulated; the base flood elevation (BFE) and freeboard requirements control lowest floor elevation.

  • Watershed and buffer requirements: riparian buffers of 25-100 feet are common; impervious cover limits (e.g., 10-30%) are used to protect stream health.

  • Site circulation: pedestrian and vehicular routes should cross as few times as possible; sight triangles at driveways keep views clear of obstructions.

Quick reference

Codes, Regulations, and Professional Practice

  • ADA Standards: accessible route slope maximum 1:20 running and 1:48 cross; ramps over 1:20 require handrails, landings, and edge protection.

  • OSHA construction standards: excavation slopes and shoring required for trenches 5 feet or deeper; competent person inspections daily and after rain.

  • Professional licensure: LAs are licensed by state boards; practice across state lines requires licensure in that state or a reciprocal agreement; stamping unqualified work is a violation.

  • Standard of care: the LA owes the client the skill and care ordinarily provided by professionals under similar circumstances, not a guarantee of perfection.

  • Contracts: scope, fee, schedule, and limitation of liability clauses; indemnification and insurance (general liability, professional liability) are standard provisions.

  • Environmental review: NEPA applies to federal actions; state-level equivalents (e.g., CEQA in California) apply to state and local projects; Section 106 of the National Historic Preservation Act protects historic properties.

  • Wetlands and waters: Section 404 of the Clean Water Act regulates discharge of dredged or fill material into waters of the US; a Section 404 permit may be required.

  • Permits and approvals: grading, building, stormwater (NPDES), floodplain, and tree removal permits; approval timelines should be built into the schedule.

Quick reference

Communication and Documentation

  • Meeting minutes should record date, attendees, decisions, action items with responsible parties, and deadlines; distribute within a defined period (often 48-72 hours).

  • RFI (request for information) process: contractor submits a question, LA responds in writing, and the response becomes part of the contract documents if it changes the design.

  • Transmittals document the exchange of documents, including date sent, recipient, purpose, and action required; they create a chain of custody.

  • Daily reports record weather, labor, equipment, visitors, and work performed; they are essential evidence for delay and change claims.

  • Punch lists identify incomplete or defective work; the contractor completes items, the LA verifies, and final payment follows.

  • Photo documentation should be dated, located, and captioned; it supports as-built records and dispute resolution.

  • Written notice requirements: most contracts require notice of changed conditions or claims within a specified period (e.g., 14-21 days) or the claim may be waived.

  • Public participation: charrettes, open houses, and comment periods gather input; documentation should record how comments were addressed.

Quick reference

Environmental and Cultural Resources

  • Wetlands are identified by hydric soils, hydrophytic vegetation, and wetland hydrology; delineation follows the US Army Corps of Engineers manual and jurisdictional determination.

  • Endangered species: the federal Endangered Species Act prohibits take; Section 7 consultation applies to federal actions; state lists may add protection.

  • Historic preservation: Section 106 of the NHPA requires review of federal undertakings for effects on historic properties; the National Register of Historic Places lists significant sites.

  • Cultural landscapes include designed landscapes, vernacular landscapes, and ethnographic landscapes; treatment options are preservation, rehabilitation, restoration, and reconstruction.

  • Stormwater and water quality: low-impact development (LID) and green infrastructure (bioretention, green roofs, permeable pavement) manage runoff at the source.

  • Brownfield remediation: Phase I environmental site assessment reviews records; Phase II involves sampling; cleanup standards vary by jurisdiction and intended use.

  • Tree and habitat protection: ordinances may protect heritage trees, require tree surveys, and mandate replacement planting ratios.

  • Climate and microclimate: vegetation shading reduces heat island effect; windbreaks reduce heating loads; urban tree canopy targets of 30-40% are common.