LA Landscape flashcards
LA Landscape · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Lump sum contract
- A fixed-price contract for a defined scope of work. The contractor bears cost-overrun risk, so drawings and specifications must be complete before bidding.
- Construction change directive
- A written order directing the contractor to proceed with work before price and time are agreed. It is later converted into a change order.
- Substantial completion
- The stage when the work is sufficiently complete for its intended use. It starts warranty periods and typically triggers partial retainage release.
- Total float
- The amount of time an activity can be delayed without delaying the project completion date. Exceeding float on the critical path delays the project.
- Slope percentage formula
- Slope percent equals rise divided by run, multiplied by 100. A 2 percent slope drops 2 feet over 100 feet, or one-quarter inch per foot.
- USDA soil textural triangle
- A chart classifying soil by percentages of sand, silt, and clay. Loam, near 40 percent sand, 40 silt, and 20 clay, is the agronomic ideal.
- Overlay suitability mapping
- A method combining factor layers such as slope, soils, floodplain, and vegetation into a composite map showing where development is most and least suitable.
- Viewshed analysis
- Mapping the area visible from a point or route using elevation data, observer height, and screening by vegetation or structures.
- CSI MasterFormat divisions
- The organizational standard for specifications. Site work falls in Division 31 earthwork, Division 32 exterior improvements, and Division 33 utilities.
- Plant schedule fields
- A table listing symbol, botanical name, common name, size, root condition, quantity, and remarks for each plant species specified.
- Record drawings
- Drawings documenting actual installed conditions, prepared from contractor markups during construction and retained for the owner's facility records.
- Rational method
- A formula estimating peak runoff: Q equals C times i times A, where C is runoff coefficient, i is rainfall intensity, and A is area in acres.
- Detention versus retention
- Detention temporarily stores runoff and releases it slowly. Retention holds water permanently in ponds or basins. Infiltration practices allow water to soak into the ground.
- Manning's equation
- A formula for open-channel flow: Q equals 1.486 divided by n, times area, times hydraulic radius to the two-thirds power, times slope to the one-half power.
- Cut and fill balance
- Designing grading so excavated soil volume roughly equals fill volume, minimizing hauling cost. Average end area method computes volume between cross sections.
- Cation exchange capacity
- A measure of a soil's ability to hold positively charged nutrients. Clay and organic matter raise CEC; sandy soils leach nutrients readily.
- Critical root zone
- The protected soil area around a tree, often one foot of radius per inch of trunk diameter, fenced before demolition and grading begin.
- Evapotranspiration
- The combined water loss from soil evaporation and plant transpiration. It drives irrigation scheduling and is influenced by temperature, wind, and solar radiation.
- Control joints in concrete
- Planned cracks in concrete slabs, spaced about 1 to 1.5 times the slab thickness in feet, to control where cracking occurs.
- Flexible versus rigid pavers
- Flexible pavers are sand-set on compacted aggregate base. Rigid pavers are mortar-set on a concrete base. Both require edge restraint.
- Weep holes
- Small openings in retaining walls that allow water to drain, preventing hydrostatic pressure buildup. They are paired with drainage gravel and filter fabric.
- Silt fence
- A temporary erosion control barrier of filter fabric on posts, installed downslope of disturbed areas to trap sediment before it leaves the site.
- Floor area ratio
- The ratio of gross floor area to lot area. A 0.5 FAR on a 20,000 square foot lot allows 10,000 square feet of building.
- Accessible parking dimensions
- Standard accessible spaces are 96 inches wide with a 60-inch access aisle. Van-accessible spaces are 132 inches wide and must be signed.
- Base flood elevation
- The elevation of the 100-year flood, the flood with a 1 percent annual chance of occurring. It controls lowest floor elevation in regulated floodplains.
- Riparian buffer
- A vegetated strip along a stream, commonly 25 to 100 feet wide, that filters runoff, stabilizes banks, and protects aquatic habitat.
- ADA running slope limit
- Accessible routes may not exceed a 1:20 running slope, which is 5 percent. Steeper ramps require handrails, landings, and edge protection.
- OSHA trench shoring
- Excavations 5 feet or deeper require protective systems such as sloping, shoring, or shielding, inspected daily by a competent person.
- Standard of care
- The skill and care ordinarily provided by professionals under similar circumstances. It is not a guarantee of perfection or of a specific result.
- Request for information
- A written contractor question about the contract documents. The landscape architect's written response clarifies intent and may become part of the contract.
- Punch list
- A list of incomplete or defective work identified near substantial completion. The contractor completes items and the landscape architect verifies before final payment.
- Wetland delineation
- Identifying wetland boundaries using hydric soils, hydrophytic vegetation, and wetland hydrology, following the US Army Corps of Engineers manual.
- Section 106 review
- A requirement of the National Historic Preservation Act that federal undertakings be reviewed for effects on historic properties before approval.