NABCEP SHI flashcards
NABCEP SHI · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- OSHA fall protection threshold
- Construction fall protection is required at 6 feet above a lower level; roof edges, skylights, and open penetrations require guardrails, covers, or personal fall arrest.
- PV DC hazard
- PV source circuits remain energized whenever exposed to light; treat DC conductors as live and verify zero voltage with a CAT III meter after isolation.
- Scald prevention setpoint
- A tempering valve at the hot water outlet should limit domestic delivery to about 120°F (49°C) to reduce scald risk from stratified solar storage.
- Glycol safety data
- Propylene glycol requires access to its safety data sheet, chemical goggles, gloves, and ventilation; do not mix it with chlorine or acids.
- Ladder roof access rule
- A roof-access ladder should extend 3 feet above the landing, be secured, and be set at a 1:4 angle with three-point contact.
- True south azimuth
- In the northern hemisphere, collectors generally face true south; correct a compass reading for local magnetic declination before marking the array orientation.
- Solar window criterion
- A common shading criterion is an unshaded solar window from about 9 a.m. to 3 p.m. year-round, checked at winter solstice when shadows are longest.
- Latitude tilt rule
- Year-round domestic hot water collectors typically tilt near the site latitude; winter-biased designs add 10–15°, and summer pool heating may subtract 10–15°.
- Roof dead load review
- The structural review compares collector, rack, fluid, and snow dead loads with roof capacity; decking alone is not evidence of rafter or truss strength.
- Magnetic declination
- Magnetic declination is the angle between magnetic north and true north; it must be applied to compass readings so collector azimuth is set correctly.
- Rafter attachment rule
- Collector standoffs must fasten into rafters or trusses at the manufacturer's specified embedment; roof decking or sheathing alone is not a structural attachment.
- Flashing primary barrier
- Every roof penetration needs flashed and counter-flashed detailing; sealant is only a secondary barrier and will not replace proper flashing.
- Wind uplift zones
- Wind uplift is greatest at roof corners and edges; rack attachment spacing there must follow ASCE 7 or local code and manufacturer engineering.
- Row spacing formula
- To avoid winter shading, row spacing D equals collector height H divided by the tangent of the minimum solar altitude: D = H / tan(alpha).
- Galvanic corrosion isolation
- Copper and aluminum contact causes galvanic corrosion; use dielectric bushings, washers, or isolating clamps wherever dissimilar metals meet in the rack.
- Ground mount frost depth
- Ground-mount piers must extend below local frost depth and resist wind overturning; concrete must cure to the specified strength before collectors are loaded.
- Collector design flow
- Typical flat-plate collector flow is about 0.05 gallons per minute per square foot; always confirm the exact rate in the collector manufacturer's manual.
- Pipe velocity limit
- Keep copper pipe velocity generally below 5 feet per second and plastic pipe below 4 feet per second to limit erosion, noise, and pressure drop.
- Drainback slope
- Drainback piping must slope continuously to the drainback tank, typically at least 1/4 inch per foot, with no traps or high points that hold water.
- Pressure relief setting
- A solar loop pressure relief valve is commonly set at 150 psi, and a tank temperature relief valve near 210°F; final settings must follow code and equipment ratings.
- Glycol concentration limit
- Propylene glycol freeze protection commonly uses 30–50% concentration; above about 60%, heat transfer drops and pump energy rises, so avoid over-concentration.
- Backflow protection
- Potable water connections to a solar loop need backflow prevention and a thermal expansion tank; a simple check valve does not protect the public supply.
- Differential control setpoints
- A differential controller typically turns the pump on when collector temperature exceeds tank temperature by 8–12°F and off near a 4°F difference.
- Collector sensor location
- The collector temperature sensor is mounted at the collector hot outlet and must be thermally coupled, shielded from sun, and wired away from line voltage.
- Freeze recirculation setpoint
- Freeze protection recirculation commonly starts at 38–40°F; drainback systems instead drain when the pump stops and depend on continuous slope.
- Pump curve selection
- Pump selection matches the system head-flow curve to the collector manufacturer's required flow; a balancing valve trims flow and isolation flanges permit service.
- Pool pump GFCI
- Pool circulating pumps require GFCI protection and a disconnecting means per electrical code; solar controls should run only when filtration flow is proven.
- Loop pressure test
- Pressure-test the solar loop at 1.5 times maximum operating pressure or as code requires, hold the test, and record results before installing insulation.
- Commissioning record
- Commissioning records include fill pressure, pump current, flow rate, collector and tank temperatures, delta-T, glycol concentration, and controller setpoints.
- No-heat troubleshooting order
- For no heat, check pump operation, controller sensor readings, flow, air locks, freeze protection, and isolation valves before replacing components.
- Glycol service interval
- Test glycol annually for pH and inhibitor strength; many propylene glycol solar systems need fluid replacement every three to five years or per test results.
- Handover package
- Handover includes manuals, warranties, freeze protection instructions, controller settings, shutoff locations, maintenance schedule, and emergency shutdown procedures.