NATE Air Distribution Installation · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Duct Installation and Assembly & Duct Materials, Components, and Fabrication

  • Map the full duct assembly sequence (layout, hangers, fittings, branch takeoffs, terminal connections) and write it out as a numbered checklist you can recite from memory

  • Identify the common duct materials and gages used for rectangular, round, and flexible duct in residential and light commercial work, and state where each is and is not acceptable

  • Practice laying out and cutting a rectangular transition and a 90-degree elbow on paper using triangulation, then verify your developed lengths against a scrap-piece mock-up

  • List the hanger and support spacing rules for rectangular and round duct and explain in your own words why spacing changes with duct size and orientation

Your checkpoint

A one-page assembly sequence flowchart plus a materials/gage reference table covering at least six duct types, both checked against your code book

Week 2

Duct Installation and Assembly & Duct Materials, Components, and Fabrication

  • Assemble a small mock-up section (straight run, one elbow, one branch takeoff) using the joining method you expect on the job, and document each step with notes on what went wrong

  • Compare four joining methods (slip-and-drive, drive cleats, transverse flanges, flexible duct ties) for speed, leakage, and appropriate application, and pick the right one for five given scenarios

  • Calculate duct weight per linear foot for two rectangular sizes and select hanger rod and strap sizes accordingly

  • Explain how fittings affect friction loss and identify which fittings in a layout should be avoided or redesigned

Your checkpoint

A written mock-up build log with photos or sketches of each joint plus a five-scenario joining-method selection sheet with justifications

Week 3

Duct System Design Fundamentals and Load Considerations & Duct Installation and Assembly

  • Convert a simple room-by-room load summary into required cfm per room using sensible heat ratios, and show your work for at least four rooms

  • Size a trunk-and-branch layout using the equal-friction method and then check it with the static-regain method, noting where the two diverge

  • Apply the friction-rate and velocity limits you would expect on a residential job and justify each limit you use

  • Identify the top three design mistakes that cause field installation problems (undersized returns, excessive flex, tight elbows) and describe the field symptom of each

Your checkpoint

A complete one-line duct layout for a small house with cfm, size, and velocity annotated at every segment, plus a short memo on where the layout is most sensitive to installation error

Week 4

Duct System Design Fundamentals and Load Considerations & Air Distribution Devices and Airflow Balance

  • Select supply and return grilles and registers for four rooms using face velocity, throw, and pressure-drop data, and record the catalog values you used

  • Explain the difference between face velocity and neck velocity and show how each affects noise and pressure drop

  • Lay out a return air path for a closed-door bedroom and justify the transfer method you choose

  • Describe how supply diffuser selection changes with ceiling height and mounting location (ceiling, high sidewall, floor)

Your checkpoint

A device schedule for a four-room example listing size, cfm, face velocity, throw, and pressure drop for each grille, with a one-paragraph defense of each selection

Week 5

Air Distribution Devices and Airflow Balance & Sealing, Insulation, and Vapor Control

  • Describe the step-by-step balancing procedure for a trunk-and-branch system, including the order in which you adjust dampers and why

  • Explain how to use a manometer, a balometer, and a pitot tube, and state what each measures and its main limitation

  • List the sealing requirements for the major joint types and identify where mastic, tape, or both are required

  • Explain vapor barrier placement, insulation R-value selection, and the consequences of a breached vapor retarder in a cold climate versus a hot-humid climate

Your checkpoint

A balancing procedure sheet with a filled-in example balancing table (design cfm, measured cfm, percent deviation, adjustment made) plus a sealing and insulation checklist for one duct system

Week 6

Sealing, Insulation, and Vapor Control & Testing, Adjusting, and Commissioning

  • Perform a duct leakage test on a mock-up or small section, compute leakage as a percentage of design airflow, and compare it to a target you state up front

  • Describe how to set up and read a duct leakage tester, including what to do about register boots and open ends during the test

  • Write the commissioning sequence for a residential duct system from rough-in inspection through final TAB

  • Explain what a TAB report should contain and how to spot an incomplete or padded report

Your checkpoint

A completed leakage test record for your mock-up with measured values, calculated leakage percentage, pass/fail against your stated target, and a corrective action list

Week 7

Safety and Jobsite Practices & Testing, Adjusting, and Commissioning

  • Identify the personal protective equipment and hazard controls for the main duct-installation tasks: overhead work, sheet metal handling, confined spaces, and power tools

  • Describe lockout/tagout and safe work practices around rooftop units and energized equipment

  • Explain how to safely handle and cut sheet metal, including glove selection, edge treatment, and tool guarding

  • Outline the steps for a pre-task safety briefing and list the hazards specific to duct installation that a generic briefing would miss

Your checkpoint

A job-hazard analysis for a full duct rough-in, covering at least eight hazards with a specific control for each

Week 8

Codes, Standards, and Documentation & Safety and Jobsite Practices & Testing, Adjusting, and Commissioning

  • Locate and summarize the code and standard provisions that govern duct installation, clearance to combustibles, and sealing in the code edition your jurisdiction adopts

  • Explain the difference between a code requirement, a standard, and a manufacturer instruction, and state which governs when they conflict

  • Assemble the documentation package a completed duct installation should leave behind (submittals, TAB report, leakage test, as-builts, inspection sign-offs)

  • Complete a timed 60-question practice set across all eight domains and review every missed item to its source

Your checkpoint

A one-page code citation sheet with at least ten provisions cited by section, plus a scored practice-set log showing your weak domains and a review note for each miss

Milestones

Week 2: You can lay out and assemble a straight run, elbow, and branch takeoff without referring to notes, and you can name the correct joining method for five different field scenarios

Week 4: You can take a room load to a sized duct segment to a selected grille in one continuous pass, showing cfm, velocity, and pressure drop at each step

Week 6: You can run a leakage test end to end, calculate percent leakage, and explain what a passing result does and does not prove about the system

Week 8: You score at least 80 percent on a timed mixed-domain practice set and can cite the governing code section for at least ten common installation requirements