Legal Principles and Professional Practice

  • North Carolina regulates land surveying through the Board of Examiners for Engineers and Surveyors; boundary, control, and cadastral surveying for others requires licensure.

  • A conveyance of an interest in land must be in writing, signed by the grantor, and contain a description sufficient to identify the property under the statute of frauds.

  • A licensee's seal certifies that the survey work was prepared by the licensee or under the licensee's direct supervision and complies with applicable standards.

  • In boundary retracement, natural monuments generally control over artificial monuments, artificial monuments control over courses and distances, and area or quantity is the weakest evidence.

  • Under senior rights, when overlapping conveyances conflict, the earlier conveyance generally prevails to the extent of the overlap and the later grantee takes the remainder.

  • Adverse possession in North Carolina commonly requires actual, open, notorious, exclusive, hostile, and continuous possession for the statutory period, generally twenty years.

  • A prescriptive easement requires adverse, open, notorious, continuous use under claim of right for the statutory period, commonly twenty years in North Carolina.

  • Riparian owners on non-navigable streams generally own to the thread of the stream; navigable waters are held by the State in trust for public use.

Quick reference

Boundary and Cadastral Surveying

  • An original government monument is evidence of the original survey and generally controls later retracement measurements and later-set corners.

  • A deed call to an identifiable adjoiner is treated as a monument and can control over courses and distances in resolving a boundary.

  • A boundary by agreement or acquiescence can be established when adjoining owners recognize and treat a line as the boundary for the statutory period, even if it differs from the deed line.

  • Accretion is gradual and imperceptible, moving a water boundary with the water; avulsion is sudden, leaving the boundary at its former location.

  • A recorded plat referenced in a deed is incorporated into the deed, and its lot lines, dimensions, and monuments become part of the legal description.

  • In metes and bounds descriptions, the point of beginning and calls must close; a deed misclosure is resolved from evidence of intent rather than by simply rotating the figure.

  • When a deed states a quantity 'more or less,' the quantity is generally subordinate to monuments and courses and distances.

Quick reference

Field Data Acquisition and Measurement

  • Horizontal distance from slope distance and vertical angle: HD = SD × cos(vertical angle from horizontal), or HD = SD × sin(zenith angle).

  • Coordinate computation: Northing = N0 + HD × cos(azimuth); Easting = E0 + HD × sin(azimuth).

  • For a closed polygon traverse with n sides, the sum of interior angles equals (n − 2) × 180 degrees, and the difference from that sum is angular misclosure.

  • The compass rule adjusts latitude and longitude corrections in proportion to traverse leg length; the transit rule uses the magnitudes of the latitudes and longitudes.

  • Differential leveling elevation difference = backsight − foresight; the sum of backsights minus the sum of foresights should equal final elevation minus initial elevation.

  • RTK GNSS requires a fixed integer ambiguity solution; poor PDOP, multipath, and obstructed sky degrade accuracy, and vertical accuracy is generally weaker than horizontal accuracy.

  • Systematic errors follow an instrumental or physical cause and can be modeled or corrected; random errors are statistical, and blunders are mistakes to be rejected.

  • A backsight establishes instrument orientation; the operator occupies the station, sets zero on the backsight, and turns to the foresight to measure the angle.

Quick reference

Mapping, Geodesy, and Geographic Information Systems

  • Orthometric height H = ellipsoid height h − geoid undulation N; GNSS provides ellipsoid heights while leveling provides orthometric heights.

  • Grid distance = ground distance × combined factor, where combined factor = projection scale factor × elevation factor.

  • A large-scale map shows a small area in more detail, such as 1:1,000; a small-scale map shows a large area with less detail, such as 1:100,000.

  • NAD83 is the horizontal datum for most current U.S. mapping, NAVD88 is the vertical datum, and WGS84 is a global GNSS datum that differs slightly from NAD83.

  • Vector GIS represents discrete features as points, lines, and polygons with attributes; raster GIS represents surfaces as a grid of cells, each holding a value.

  • A parcel layer in a GIS is a graphical and administrative representation and does not by itself establish legal boundary location.

  • A representative fraction such as 1:24,000 is unitless and means one map unit represents 24,000 of the same units on the ground.

  • Projection scale factor equals 1.0 only along standard lines, so ground-to-grid corrections are required for precise surveys away from those lines.

Quick reference

Engineering and Construction Surveying

  • Horizontal curve tangent: T = R tan(Δ/2), where R is radius and Δ is the central deflection angle.

  • Horizontal curve length: L = RΔ in radians; long chord: LC = 2R sin(Δ/2).

  • Horizontal curve external: E = R[sec(Δ/2) − 1]; middle ordinate: M = R[1 − cos(Δ/2)].

  • Vertical curve K value: K = L/A, where L is curve length and A is the algebraic grade change in percent; K gives the rate of curvature.

  • Vertical curve elevation: y = y_BVC + g1x + [(g2 − g1)/(2L)]x², with grades as decimals and x measured from the BVC.

  • Percent grade = (rise/run) × 100; a +2.00% grade rises 2.00 feet per 100 feet of horizontal run.

  • Average end area volume = L × (A1 + A2)/2; the prismoidal formula is more exact when cross sections change nonlinearly.

  • Cut or fill = existing ground elevation − design elevation; positive indicates cut and negative indicates fill.

Quick reference

Legal Principles and Professional Practice

  • North Carolina regulates land surveying through the Board of Examiners for Engineers and Surveyors; boundary, control, and cadastral surveying for others requires licensure.

  • A conveyance of an interest in land must be in writing, signed by the grantor, and contain a description sufficient to identify the property under the statute of frauds.

  • A licensee's seal certifies that the survey work was prepared by the licensee or under the licensee's direct supervision and complies with applicable standards.

  • In boundary retracement, natural monuments generally control over artificial monuments, artificial monuments control over courses and distances, and area or quantity is the weakest evidence.

  • Under senior rights, when overlapping conveyances conflict, the earlier conveyance generally prevails to the extent of the overlap and the later grantee takes the remainder.

  • Adverse possession in North Carolina commonly requires actual, open, notorious, exclusive, hostile, and continuous possession for the statutory period, generally twenty years.

  • A prescriptive easement requires adverse, open, notorious, continuous use under claim of right for the statutory period, commonly twenty years in North Carolina.

  • Riparian owners on non-navigable streams generally own to the thread of the stream; navigable waters are held by the State in trust for public use.

Quick reference

Boundary and Cadastral Surveying

  • An original government monument is evidence of the original survey and generally controls later retracement measurements and later-set corners.

  • A deed call to an identifiable adjoiner is treated as a monument and can control over courses and distances in resolving a boundary.

  • A boundary by agreement or acquiescence can be established when adjoining owners recognize and treat a line as the boundary for the statutory period, even if it differs from the deed line.

  • Accretion is gradual and imperceptible, moving a water boundary with the water; avulsion is sudden, leaving the boundary at its former location.

  • A recorded plat referenced in a deed is incorporated into the deed, and its lot lines, dimensions, and monuments become part of the legal description.

  • In metes and bounds descriptions, the point of beginning and calls must close; a deed misclosure is resolved from evidence of intent rather than by simply rotating the figure.

  • When a deed states a quantity 'more or less,' the quantity is generally subordinate to monuments and courses and distances.

Quick reference

Field Data Acquisition and Measurement

  • Horizontal distance from slope distance and vertical angle: HD = SD × cos(vertical angle from horizontal), or HD = SD × sin(zenith angle).

  • Coordinate computation: Northing = N0 + HD × cos(azimuth); Easting = E0 + HD × sin(azimuth).

  • For a closed polygon traverse with n sides, the sum of interior angles equals (n − 2) × 180 degrees, and the difference from that sum is angular misclosure.

  • The compass rule adjusts latitude and longitude corrections in proportion to traverse leg length; the transit rule uses the magnitudes of the latitudes and longitudes.

  • Differential leveling elevation difference = backsight − foresight; the sum of backsights minus the sum of foresights should equal final elevation minus initial elevation.

  • RTK GNSS requires a fixed integer ambiguity solution; poor PDOP, multipath, and obstructed sky degrade accuracy, and vertical accuracy is generally weaker than horizontal accuracy.

  • Systematic errors follow an instrumental or physical cause and can be modeled or corrected; random errors are statistical, and blunders are mistakes to be rejected.

  • A backsight establishes instrument orientation; the operator occupies the station, sets zero on the backsight, and turns to the foresight to measure the angle.

Quick reference

Mapping, Geodesy, and Geographic Information Systems

  • Orthometric height H = ellipsoid height h − geoid undulation N; GNSS provides ellipsoid heights while leveling provides orthometric heights.

  • Grid distance = ground distance × combined factor, where combined factor = projection scale factor × elevation factor.

  • A large-scale map shows a small area in more detail, such as 1:1,000; a small-scale map shows a large area with less detail, such as 1:100,000.

  • NAD83 is the horizontal datum for most current U.S. mapping, NAVD88 is the vertical datum, and WGS84 is a global GNSS datum that differs slightly from NAD83.

  • Vector GIS represents discrete features as points, lines, and polygons with attributes; raster GIS represents surfaces as a grid of cells, each holding a value.

  • A parcel layer in a GIS is a graphical and administrative representation and does not by itself establish legal boundary location.

  • A representative fraction such as 1:24,000 is unitless and means one map unit represents 24,000 of the same units on the ground.

  • Projection scale factor equals 1.0 only along standard lines, so ground-to-grid corrections are required for precise surveys away from those lines.

Quick reference

Engineering and Construction Surveying

  • Horizontal curve tangent: T = R tan(Δ/2), where R is radius and Δ is the central deflection angle.

  • Horizontal curve length: L = RΔ in radians; long chord: LC = 2R sin(Δ/2).

  • Horizontal curve external: E = R[sec(Δ/2) − 1]; middle ordinate: M = R[1 − cos(Δ/2)].

  • Vertical curve K value: K = L/A, where L is curve length and A is the algebraic grade change in percent; K gives the rate of curvature.

  • Vertical curve elevation: y = y_BVC + g1x + [(g2 − g1)/(2L)]x², with grades as decimals and x measured from the BVC.

  • Percent grade = (rise/run) × 100; a +2.00% grade rises 2.00 feet per 100 feet of horizontal run.

  • Average end area volume = L × (A1 + A2)/2; the prismoidal formula is more exact when cross sections change nonlinearly.

  • Cut or fill = existing ground elevation − design elevation; positive indicates cut and negative indicates fill.