NC Land Surveyor flashcards
NC Land Surveyor ยท Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Statute of Frauds
- A legal rule requiring that conveyances of land be in writing and signed by the grantor, with a description sufficient to identify the property.
- Surveyor's seal
- A licensee's seal on a survey map certifies that the work was prepared by the licensee or under the licensee's direct supervision and meets applicable standards.
- Adverse possession elements
- Actual, open, notorious, exclusive, hostile, and continuous possession of land for the statutory period, generally twenty years in North Carolina, can ripen into title.
- Prescriptive easement
- A right to use another's land acquired by adverse, open, notorious, continuous use under claim of right for the statutory period, commonly twenty years in North Carolina.
- Senior rights rule
- When overlapping conveyances conflict, the earlier senior grant generally prevails to the extent of the overlap, and the later junior grantee takes only the remaining land.
- Boundary evidence hierarchy
- In retracement, natural monuments generally control over artificial monuments, which control over courses and distances; area and quantity are the weakest evidence of boundary location.
- Accretion versus avulsion
- Accretion is gradual, imperceptible addition of land that moves a water boundary; avulsion is sudden change, such as a flood cutoff, that leaves the boundary unchanged.
- Boundary by acquiescence
- A boundary line may be established when adjoining owners recognize and treat a line as the boundary for the statutory period, even if it differs from the deed line.
- Recorded plat incorporation
- When a deed refers to a recorded plat, the plat is incorporated into the deed, and its lot lines, dimensions, and monuments become part of the legal description.
- Original government corner
- A corner established by the original federal survey that is evidence of the original survey; it controls later retracement measurements and later-set corners.
- Metes and bounds description
- A property description that starts at a point of beginning and follows calls of bearing and distance, often with monument references, returning to close the parcel.
- Riparian boundary
- For non-navigable streams, the boundary commonly extends to the thread of the stream; navigable waters are generally held by the state for public use.
- Horizontal distance formula
- From slope distance and vertical angle, horizontal distance equals slope distance times the cosine of the vertical angle measured from horizontal.
- Traverse angle closure
- For a closed polygon traverse with n sides, the sum of interior angles should equal (n โ 2) times 180 degrees; any difference is angular misclosure.
- Compass rule adjustment
- A traverse adjustment that distributes latitude and longitude corrections in proportion to each leg's length, correcting linear misclosure systematically around the traverse.
- Differential leveling equation
- Elevation difference between two points equals backsight rod reading minus foresight rod reading; summing backsights and foresights checks the level run.
- RTK fixed solution
- A real-time kinematic GNSS mode in which integer carrier-phase ambiguities are resolved, giving centimeter-level horizontal coordinates when satellite geometry and signal quality are good.
- Systematic versus random error
- Systematic errors follow a physical or instrumental cause and can be modeled or corrected; random errors are small unpredictable variations that can be reduced by repeated measurements.
- Coordinate computation
- Northing equals starting northing plus horizontal distance times cosine of azimuth; easting equals starting easting plus horizontal distance times sine of azimuth.
- Geoid undulation relation
- Orthometric height equals ellipsoid height minus geoid undulation; GNSS provides ellipsoid height, while leveling provides orthometric height above the geoid.
- Combined factor
- Grid distance equals ground distance multiplied by the combined factor, which is the product of the projection scale factor and the elevation factor.
- Representative fraction
- A unitless map scale ratio such as 1:24,000, meaning one unit on the map represents 24,000 of the same units on the ground.
- Vector versus raster
- Vector GIS stores points, lines, and polygons with attributes; raster GIS stores a grid of cells, each holding a value for a continuous or categorical surface.
- NAD83 versus WGS84
- NAD83 is a North American horizontal datum used for mapping and state plane coordinates; WGS84 is a global GNSS datum that differs from NAD83 by small amounts.
- NAVD88 vertical datum
- A national vertical datum based on geodetic leveling and gravity, used for orthometric elevations in the United States and referenced to a tide station network.
- GIS parcel layer
- A digital polygon layer showing parcel boundaries and attributes for mapping and administration; it is not a legal determination of boundary location unless based on authoritative records.
- Horizontal curve tangent
- For a circular horizontal curve, tangent length equals radius times the tangent of half the central deflection angle; it runs from the point of curvature or tangency to the point of intersection.
- Horizontal curve external
- For a circular horizontal curve, external distance equals radius times the quantity secant of half the deflection angle minus one, measured from the point of intersection to the curve midpoint.
- Vertical curve K value
- In vertical curve design, K equals curve length divided by the algebraic difference in grades in percent; K indicates the rate of elevation change per percent grade.
- Percent grade
- Grade in percent equals rise divided by horizontal run times one hundred; a 2.00 percent grade rises 2.00 feet per 100 feet of horizontal distance.
- Average end area volume
- Volume by average end area equals the distance between cross sections times the average of their end areas; it assumes a linear change between sections.
- Cut and fill sign
- Cut or fill equals existing ground elevation minus design elevation; a positive value indicates cut, and a negative value indicates fill at that point.