Site, Work Area, and Environmental Hazards

  • Treat every power line as energized; OSHA crane minimum approach distance is 10 ft at 50 kV or less and increases 0.4 in per kV above 50 kV.

  • Outdoor lifting stops when wind exceeds the manufacturer's limit or when the load cannot be controlled with tag lines; capacity charts assume still air unless stated otherwise.

  • Lightning response: land the load, lower the hook, and secure or move the crane per the site plan; do not resume until the storm has passed.

  • Verify the floor, runway, or support surface can carry the crane plus load; check for trenches, voids, soft fill, and uncompacted areas.

  • Adequate illumination must reach the load, rigging, hook, and signal person; if these cannot be seen clearly, the lift does not proceed.

  • Ice, snow, mud, and grease reduce traction and brake friction; remove accumulations from walkways, rails, and crane surfaces before operation.

  • Barricade the swing radius and keep pedestrians out from under or near the load; a load must not pass over personnel.

  • Check clearance to roof trusses, piping, doors, and other cranes through the full travel path before moving.

Quick reference

Pre-Operational Inspection and Crane Setup

  • Before first use each shift, inspect hook, wire rope, chains, brakes, limit switches, controls, warning devices, rails, bumpers, and record defects.

  • Remove a hook from service if throat opening increased more than 15 percent, twist exceeds 10 degrees, cracks are present, or the latch is missing or inoperative.

  • Inspect wire rope for broken wires, kinks, birdcaging, corrosion, crushed areas, and diameter loss; reject rope exceeding ASME B30.2 criteria.

  • Test the hoist brake by lifting a load slightly, stopping, and confirming the brake holds without drift.

  • Test upper and lower hoist limits and bridge and trolley travel limits without a load at safe speed.

  • Check runway rail alignment, end stops, rail sweeps, and clearance; remove obstructions from the travel path.

  • Verify control function and labeling, and test the emergency stop before placing the crane into service.

  • Do not operate a crane with a safety defect; document the defect and keep the crane out of service until repaired.

Quick reference

Rigging, Load Attachment, and Load Weight Determination

  • Gross load equals the load weight plus all rigging, slings, shackles, spreader beams, and attachments; capacity ratings apply to this total.

  • Determine weight from shipping papers, drawings, manufacturer markings, or a scale; do not rely only on appearance or volume.

  • For a known material, weight equals volume multiplied by material density, with consistent units.

  • Position the hook over the load's center of gravity; off-center lifts require multiple pick points or a plan to prevent tilt and load shift.

  • For a symmetric two-leg lift, tension per leg equals load divided by two times the sine of the sling angle from horizontal: T = W/(2 sin theta).

  • As sling legs approach horizontal, tension increases; at 30 degrees from horizontal each leg carries the load divided by two times 0.5.

  • Never exceed a sling's working load limit; the WLL changes with hitch type, angle, wear, and configuration.

  • Attach to designated lifting points, protect slings from sharp edges, and inspect shackles and slings before use.

Quick reference

Crane Operation and Load Handling

  • Hoist vertically over the load's center of gravity; side pulls, dragging, and swinging loads create forces the crane was not designed to resist.

  • Raise the load a few inches, stop, and check load stability, rigging security, brake holding, and crane response before continuing.

  • Never leave a suspended load unattended and never allow personnel under or on a load; land the load before leaving the controls.

  • Use smooth acceleration and deceleration; shock loading from rapid starts or stops can exceed structural and rigging limits.

  • Travel with the load as low as practical and controlled; use tag lines to prevent rotation and drift.

  • Multiple-crane lifts require a written plan and a qualified person to determine load distribution and coordinate signals.

  • If the load becomes uncontrollable, stop motion, lower the load if possible, and keep personnel clear.

  • On power failure, set brakes, keep the area clear, and lower the load using the crane's controlled lowering procedure; do not allow free fall.

Quick reference

Load Charts, Capacity, and Structural/Limit Considerations

  • Rated capacity is the maximum gross load allowed for a specific crane configuration and includes load, rigging, and attachments.

  • Match the load chart to the crane model, serial number, reeving, trolley position, hook height, and site-specific restrictions.

  • On cranes with variable ratings, capacity can change with trolley position, hoist reeving, hook height, and bridge or runway configuration.

  • Two-blocking occurs when the hook block contacts the hoist drum or upper block; the upper limit switch and operator control prevent rope damage.

  • Limit switches are safety devices; they are tested without a load and are not used as normal stopping controls.

  • Structural warning signs include cracks, deformation, unusual noise, vibration, and loose fasteners; stop operation and report them.

  • Do not use the crane as an anchor, tow point, or drag line; such forces are outside the load chart rating.

  • If load weight is unknown, the chart is missing or illegible, or gross load exceeds rated capacity, do not lift until verified.

Quick reference

Communication and Standard Hand Signals

  • The operator follows signals from one designated signal person; anyone may give an emergency stop signal, and the operator must obey it immediately.

  • Hoist: arm extended horizontally, forearm vertical, forefinger pointing up, move hand in a small horizontal circle.

  • Lower: arm extended downward, forefinger pointing down, move hand in a small horizontal circle.

  • Bridge travel: arm extended forward, hand open and slightly raised, push hand in the direction of travel.

  • Trolley travel: palm up, fingers closed, thumb pointing in the direction of travel, jerk hand horizontally.

  • Stop: arm extended, palm down, move arm back and forth horizontally.

  • Emergency stop: both arms extended, palms down, move arms back and forth horizontally.

  • Dog everything: clasp hands in front of the body to signal securing or locking the crane motions.

Quick reference

Shutdown, Securing, and Out-of-Service Procedures

  • Normal shutdown: land the load, raise the hook to a safe height, set brakes, neutralize controls, turn off power, and lock out the disconnect when required.

  • Park the crane at the designated location so it does not block walkways, exits, or other equipment travel paths.

  • For outdoor cranes, set rail clamps or brakes, install storm anchors or tie-downs, and follow the manufacturer's wind-securing procedure.

  • Out-of-service condition: attach a lock and tag at the disconnect, remove the key, and record the defect.

  • A crane tagged out of service remains unavailable until a qualified person repairs it and returns it to service.

  • After shutdown, inspect slings and rigging, remove them from the crane, and store them in a clean, dry area.

  • Report all defects and abnormal conditions to supervision; do not conceal or defer safety-related damage.

  • Emergency shutdown: activate the emergency stop, then disconnect power and secure the crane per the site emergency plan.

Quick reference

Site, Work Area, and Environmental Hazards

  • Treat every power line as energized; OSHA crane minimum approach distance is 10 ft at 50 kV or less and increases 0.4 in per kV above 50 kV.

  • Outdoor lifting stops when wind exceeds the manufacturer's limit or when the load cannot be controlled with tag lines; capacity charts assume still air unless stated otherwise.

  • Lightning response: land the load, lower the hook, and secure or move the crane per the site plan; do not resume until the storm has passed.

  • Verify the floor, runway, or support surface can carry the crane plus load; check for trenches, voids, soft fill, and uncompacted areas.

  • Adequate illumination must reach the load, rigging, hook, and signal person; if these cannot be seen clearly, the lift does not proceed.

  • Ice, snow, mud, and grease reduce traction and brake friction; remove accumulations from walkways, rails, and crane surfaces before operation.

  • Barricade the swing radius and keep pedestrians out from under or near the load; a load must not pass over personnel.

  • Check clearance to roof trusses, piping, doors, and other cranes through the full travel path before moving.

Quick reference

Pre-Operational Inspection and Crane Setup

  • Before first use each shift, inspect hook, wire rope, chains, brakes, limit switches, controls, warning devices, rails, bumpers, and record defects.

  • Remove a hook from service if throat opening increased more than 15 percent, twist exceeds 10 degrees, cracks are present, or the latch is missing or inoperative.

  • Inspect wire rope for broken wires, kinks, birdcaging, corrosion, crushed areas, and diameter loss; reject rope exceeding ASME B30.2 criteria.

  • Test the hoist brake by lifting a load slightly, stopping, and confirming the brake holds without drift.

  • Test upper and lower hoist limits and bridge and trolley travel limits without a load at safe speed.

  • Check runway rail alignment, end stops, rail sweeps, and clearance; remove obstructions from the travel path.

  • Verify control function and labeling, and test the emergency stop before placing the crane into service.

  • Do not operate a crane with a safety defect; document the defect and keep the crane out of service until repaired.

Quick reference

Rigging, Load Attachment, and Load Weight Determination

  • Gross load equals the load weight plus all rigging, slings, shackles, spreader beams, and attachments; capacity ratings apply to this total.

  • Determine weight from shipping papers, drawings, manufacturer markings, or a scale; do not rely only on appearance or volume.

  • For a known material, weight equals volume multiplied by material density, with consistent units.

  • Position the hook over the load's center of gravity; off-center lifts require multiple pick points or a plan to prevent tilt and load shift.

  • For a symmetric two-leg lift, tension per leg equals load divided by two times the sine of the sling angle from horizontal: T = W/(2 sin theta).

  • As sling legs approach horizontal, tension increases; at 30 degrees from horizontal each leg carries the load divided by two times 0.5.

  • Never exceed a sling's working load limit; the WLL changes with hitch type, angle, wear, and configuration.

  • Attach to designated lifting points, protect slings from sharp edges, and inspect shackles and slings before use.

Quick reference

Crane Operation and Load Handling

  • Hoist vertically over the load's center of gravity; side pulls, dragging, and swinging loads create forces the crane was not designed to resist.

  • Raise the load a few inches, stop, and check load stability, rigging security, brake holding, and crane response before continuing.

  • Never leave a suspended load unattended and never allow personnel under or on a load; land the load before leaving the controls.

  • Use smooth acceleration and deceleration; shock loading from rapid starts or stops can exceed structural and rigging limits.

  • Travel with the load as low as practical and controlled; use tag lines to prevent rotation and drift.

  • Multiple-crane lifts require a written plan and a qualified person to determine load distribution and coordinate signals.

  • If the load becomes uncontrollable, stop motion, lower the load if possible, and keep personnel clear.

  • On power failure, set brakes, keep the area clear, and lower the load using the crane's controlled lowering procedure; do not allow free fall.

Quick reference

Load Charts, Capacity, and Structural/Limit Considerations

  • Rated capacity is the maximum gross load allowed for a specific crane configuration and includes load, rigging, and attachments.

  • Match the load chart to the crane model, serial number, reeving, trolley position, hook height, and site-specific restrictions.

  • On cranes with variable ratings, capacity can change with trolley position, hoist reeving, hook height, and bridge or runway configuration.

  • Two-blocking occurs when the hook block contacts the hoist drum or upper block; the upper limit switch and operator control prevent rope damage.

  • Limit switches are safety devices; they are tested without a load and are not used as normal stopping controls.

  • Structural warning signs include cracks, deformation, unusual noise, vibration, and loose fasteners; stop operation and report them.

  • Do not use the crane as an anchor, tow point, or drag line; such forces are outside the load chart rating.

  • If load weight is unknown, the chart is missing or illegible, or gross load exceeds rated capacity, do not lift until verified.

Quick reference

Communication and Standard Hand Signals

  • The operator follows signals from one designated signal person; anyone may give an emergency stop signal, and the operator must obey it immediately.

  • Hoist: arm extended horizontally, forearm vertical, forefinger pointing up, move hand in a small horizontal circle.

  • Lower: arm extended downward, forefinger pointing down, move hand in a small horizontal circle.

  • Bridge travel: arm extended forward, hand open and slightly raised, push hand in the direction of travel.

  • Trolley travel: palm up, fingers closed, thumb pointing in the direction of travel, jerk hand horizontally.

  • Stop: arm extended, palm down, move arm back and forth horizontally.

  • Emergency stop: both arms extended, palms down, move arms back and forth horizontally.

  • Dog everything: clasp hands in front of the body to signal securing or locking the crane motions.

Quick reference

Shutdown, Securing, and Out-of-Service Procedures

  • Normal shutdown: land the load, raise the hook to a safe height, set brakes, neutralize controls, turn off power, and lock out the disconnect when required.

  • Park the crane at the designated location so it does not block walkways, exits, or other equipment travel paths.

  • For outdoor cranes, set rail clamps or brakes, install storm anchors or tie-downs, and follow the manufacturer's wind-securing procedure.

  • Out-of-service condition: attach a lock and tag at the disconnect, remove the key, and record the defect.

  • A crane tagged out of service remains unavailable until a qualified person repairs it and returns it to service.

  • After shutdown, inspect slings and rigging, remove them from the crane, and store them in a clean, dry area.

  • Report all defects and abnormal conditions to supervision; do not conceal or defer safety-related damage.