Working capital formula
Current assets minus current liabilities. It measures short-term liquidity available to fund payroll, materials, and retainage gaps on active construction jobs.
Break-even revenue calculation
Total fixed overhead divided by gross margin percentage. A firm with $300,000 overhead and 20% margin needs $1,500,000 in annual volume before earning any profit.
Labor burden
Payroll taxes, insurance, benefits, and other costs added on top of base wage. Burden typically runs 25โ€“40% of base wage for field construction labor.
Percentage-of-completion method
Revenue and cost recognition in proportion to work completed, usually measured by costs incurred to date divided by total estimated costs. It smooths reported results across periods.
Retainage receivable
Money withheld from progress payments until contract conditions are met. It is an asset on the balance sheet, not cash, and must be tracked by project and age.
New Mexico CID
The Construction Industries Division of the Regulation and Licensing Department administers contractor licensing, permits, and trade regulation for construction work in New Mexico.
Qualifying party requirement
The individual who passes the trade and business/law exams and holds the license through the contracting entity. Loss of that person generally requires prompt replacement.
Unlicensed contracting consequences
Working without a required New Mexico license can make a contract unenforceable for collecting compensation and exposes the contractor to citations, penalties, and discipline.
License number on documents
New Mexico rules require the contractor license number to appear on advertisements, bids, and contracts. Misrepresenting license status is a violation subject to discipline.
Workers' compensation proof
Contractors must carry workers' compensation coverage for employees and provide proof. Failure to maintain required coverage can result in license suspension.
Pay-when-paid clause
A subcontract provision tying subcontractor payment to the owner's payment to the prime contractor. It affects timing of payment rather than eliminating the obligation in many jurisdictions.
Substantial completion
The stage when work is sufficiently complete for its intended use. It triggers warranty start, retainage release eligibility, and often reduces liquidated damages exposure.
Liquidated damages test
The amount must be a reasonable forecast of probable loss at contract formation. Clauses disproportionate to anticipated harm are treated as unenforceable penalties.
Notice as condition precedent
Contract clauses requiring written notice within a set period for delay, change, or differing site conditions. Missing the deadline can waive entitlement regardless of merit.
Differing site condition claim
A claim that physical site conditions differ materially from those shown in contract documents. It generally requires prompt written notice, documentation, and proof of the difference.
Closeout package contents
As-built drawings, O&M manuals, warranties, lien waivers, final lien releases, and consent of surety where bonds apply, submitted to confirm project completion.
Quantity takeoff method
Measure net quantities from drawings and specifications, then apply waste and overlap factors separately. Keeping factors separate preserves an auditable takeoff.
Labor cost formula
Labor hours equal quantity divided by crew productivity rate. Labor cost equals hours times crew average wage times one plus burden percentage.
Bond premium in bid
Performance and payment bond premium is typically a percentage of contract value, tiered by contract size, and must be included in the bid price.
Contingency versus profit
Contingency covers identifiable risk such as unknowns, escalation, or weather. It is tracked separately from markup for overhead and profit and drawn down as risks occur.
Unbalanced bid risk
Front-loading or overpricing early or changed-work items can create cash-flow advantage but may be rejected and increases dispute and audit risk.
Total float formula
Total float equals late start minus early start, or late finish minus early finish. It is the delay an activity can absorb without delaying project completion.
Free float
The amount of time an activity can be delayed without delaying the early start of any successor activity. It is always less than or equal to total float.
Crash cost slope
Crash cost minus normal cost, divided by normal duration minus crash duration. Crash the lowest-slope critical-path activity first to shorten the project economically.
Cost performance index
CPI equals earned value divided by actual cost. A CPI below 1.0 indicates the work performed is costing more than budgeted.
Estimate at completion
EAC equals budget at completion divided by CPI when current cost performance continues. Alternatively, EAC equals actual cost plus remaining budget when future work is at budget.
OSHA fall protection threshold
General construction fall protection is required at 6 feet or more above a lower level. Guardrails, safety nets, or personal fall arrest systems are acceptable systems.
Excavation protective system
Excavations 5 feet or deeper require sloping, shoring, or shielding unless entirely in stable rock. A competent person must inspect daily and after rain.
SWPPP purpose
A stormwater pollution prevention plan identifies erosion and sediment controls, material storage practices, and inspection schedules required for construction site stormwater compliance.
Water-cement ratio effect
Lower water-cement ratio increases concrete strength and reduces permeability. Higher ratio improves workability but reduces strength and durability of the hardened concrete.
Slip-critical bolted connection
A structural steel connection that resists shear through friction between faying surfaces. It requires specified surface preparation and bolt tensioning to develop the friction resistance.
Soil compaction specification
Compaction is specified as a percentage of maximum dry density from a standard proctor test. Moisture content near optimum allows efficient compaction to the required density.