NZ Certifying Drainlayer key terms
NZ Certifying Drainlayer · Get comfortable with the vocabulary.
- Building Act 2004
- Related: Building consent, Building consent authority, New Zealand Building Code
The main New Zealand statute governing building work. It sets out when building consent is needed, who may carry out and certify restricted building work, and the duties of owners, builders and building consent authorities.
- New Zealand Building Code
- Related: Building Act 2004, AS/NZS 3500.2, Code compliance certificate
The performance requirements in Schedule 1 of the Building Regulations 1992. Drainage work must satisfy clauses G13 (foul water), G14 (industrial liquid waste) and E1 (surface water), among others.
- Building consent
- Related: Building consent authority, Code compliance certificate, Certifying drainlayer
Formal approval from a building consent authority to carry out the building work shown in the approved plans and specifications. Drainage must be installed as consented and inspected before being covered in.
- Certifying drainlayer
- Related: Registered drainlayer, Producer statement, Building consent
A registered drainlayer holding a current certifying endorsement from the Board, allowing them to certify that drainage work they design or carry out complies with the Building Code and the consented plans.
- Registered drainlayer
- Related: Plumbers, Gasfitters and Drainlayers Board, Certifying drainlayer
A person registered with the Plumbers, Gasfitters and Drainlayers Board to carry out drainlaying. Registration is a legal requirement before doing drainlaying work for other people.
- Plumbers, Gasfitters and Drainlayers Board
- Related: Registered drainlayer, Certifying drainlayer
The statutory body that registers and licenses plumbers, gasfitters and drainlayers, sets competency requirements, investigates complaints and disciplines practitioners. It also publishes licensing classes and certifying endorsements.
- Building consent authority
- Related: Building consent, Code compliance certificate, Producer statement
A territorial authority or private organisation accredited to issue building consents, carry out inspections and issue code compliance certificates for building work, including drainage work.
- Code compliance certificate
- Related: Building consent, Producer statement, As-built record
A certificate issued by a building consent authority at completion confirming that the building work, including drainage, complies with the building consent and the Building Code.
- AS/NZS 3500.2
- Related: New Zealand Building Code, Gradient (fall), Water test
The joint Australian and New Zealand standard for sanitary plumbing and drainage. It gives design, installation and testing requirements that drainage work is normally expected to follow alongside the Building Code.
- Producer statement
- Related: Certifying drainlayer, Building consent authority, As-built record
A written statement, usually from a designer or installer, that certain work has been done to a stated standard. Consent authorities use it as evidence when deciding whether to inspect or issue certificates.
- As-built record
- Related: Invert level, CCTV inspection, Code compliance certificate
A drawing or record showing the drainage as it was actually installed, including positions, levels, pipe sizes and materials rather than the original design. It is given to the owner and council at completion.
- Foul water drainage
- Related: Surface water drainage, Gully trap, Water trap seal
The system of pipes and fittings that carries sewage and other liquid waste from buildings to a public sewer or on-site treatment system. It must be graded and vented to keep gases out of buildings.
- Surface water drainage
- Related: Foul water drainage, Boundary connection
Pipes, channels and grated inlets that collect stormwater from roofs, paved areas and ground and carry it to a stormwater system or watercourse. It is kept separate from foul water.
- Gradient (fall)
- Related: Self-cleansing velocity, Invert level, Depth of cover
The slope of a drain, written as a ratio such as 1:60 or as a percentage. The correct fall lets liquid and solids travel at a self-cleansing speed without the pipe scouring too fast.
- Self-cleansing velocity
- Related: Gradient (fall), Invert level
The minimum flow speed needed to keep solids moving and stop sediment building up in a drain. It is typically about 0.6 to 0.7 metres per second, depending on the pipe size and standard used.
- Invert level
- Related: Gradient (fall), Depth of cover, As-built record
The height of the inside bottom of a pipe at a given point, usually measured relative to a chosen datum. Invert levels set the fall of a drain and are recorded on plans and as-builts.
- Depth of cover
- Related: Pipe stiffness (SN rating), Bedding, Invert level
The distance from the finished ground surface down to the top of the pipe. It must be sufficient to protect the pipe from traffic loads and damage and to meet the minimums in the standard.
- Boundary connection
- Related: Foul water drainage, Inspection point, Building consent authority
The point where a private drain joins the public sewer or stormwater main, usually near the property boundary. It needs the network operator's approval and its position and level must be recorded.
- Gully trap
- Related: Water trap seal, Foul water drainage, Inspection point
A trapped, grated fitting that receives waste water from fixtures such as sinks, basins and laundry tubs. It holds a water seal that stops sewer gases escaping into the building.
- Water trap seal
- Related: Gully trap, Vent pipe, Inspection point
The body of water held in a trap that seals out sewer gases. Design and venting must keep the seal intact and within the depth limits set in AS/NZS 3500.2.
- Inspection point
- Related: CCTV inspection, Boundary connection, Gully trap
An access fitting such as a rodding eye or inspection opening that allows drains to be cleaned and examined. It must stay accessible and be positioned where the standard requires.
- Vent pipe
- Related: Water trap seal, Air test
A pipe that admits air into the drainage system so trap seals are not siphoned away. It also releases foul gases above roof level, clear of windows and other openings.
- Reflux valve
- Related: Foul water drainage, Surface water drainage
A one-way valve that lets flow leave the site but stops sewage or stormwater flowing back in, protecting the building when the public system surcharges or floods.
- Bedding
- Related: Depth of cover, Pipe stiffness (SN rating), Backfill
The material placed under and immediately around a pipe to support it evenly along its length. Correct bedding spreads loads, protects the pipe and lets it hold the designed gradient.
- Pipe stiffness (SN rating)
- Related: Bedding, Deflection test, Depth of cover
A number describing how well a buried pipe resists deflection under load, written as SN followed by a value. The stiffness needed depends on burial depth, soil type and traffic loading.
- Ring seal joint
- Related: Bedding, Water test
A push-fit joint in which a rubber ring held in a groove forms a watertight but slightly flexible seal between two pipes. It allows small movement and is common on uPVC drains.
- Trench shoring
- Related: Confined space, Site safety plan, Dewatering
Support such as timber, hydraulic props or trench shields placed against the walls of an excavation to stop it collapsing onto workers, used where the sides are not battered back safely.
- Backfill
- Related: Bedding, Deflection test, Trench shoring
The material placed back into the trench after the pipe is laid, bedded and tested. It must be put in and compacted in layers so the pipe is not damaged or pushed out of shape.
- Dewatering
- Related: Trench shoring, Underground service location
Removing groundwater or surface water from an excavation so the trench stays dry and stable. Methods include sumps, pumps and wellpoints, with the water discharged to an approved place.
- Underground service location
- Related: Trench shoring, Site safety plan
Finding existing pipes, cables and ducts before digging, using plans, locating equipment and trial holes. In New Zealand plans are usually requested through beforeUdig and services marked on site.
- Water test
- Related: Air test, Ring seal joint, Inspection point
A test in which a completed section of drain is filled with water and checked for leakage or loss of head. It proves joints and pipes are sound before the trench is backfilled.
- Air test
- Related: Water test, Vent pipe
A test in which a drain or stack is pressurised with air and the pressure drop measured to show it is airtight. It is quicker than a water test but needs careful safety controls.
- CCTV inspection
- Related: Deflection test, As-built record, Inspection point
Recording the inside of a drain with a camera on a push rod or crawler to find defects such as cracks, roots, offsets and sagging. It may be required before handover or before repair work.
- Deflection test
- Related: Backfill, Pipe stiffness (SN rating), CCTV inspection
A check that a flexible buried pipe has not been squashed out of shape, done by pulling a mandrel or laser through it after backfilling. Too much deflection means the pipe or bedding must be redone.
- Trade waste
- Related: Grease trap, On-site wastewater system
Liquid waste from commercial or industrial processes that is not ordinary domestic sewage. It usually needs pre-treatment and a written consent from the network operator before entering the sewer.
- Grease trap
- Related: Trade waste, Inspection point
A chamber that slows kitchen or food-processing waste water so fats, oils and grease float and are held back while clearer water flows on. It must be correctly sized and emptied regularly.
- On-site wastewater system
- Related: Trade waste, Surface water drainage
A system that treats and disposes of wastewater from a property not connected to a public sewer, typically a septic tank or aerated treatment unit followed by a disposal field.
- Confined space
- Related: Trench shoring, Site safety plan
An enclosed or partly enclosed space not designed for people, with restricted entry, that may contain a hazardous atmosphere. Entry requires a permit, gas testing and a standby person.
- Site safety plan
- Related: Confined space, Underground service location, Trench shoring
A document for a job that identifies hazards, sets out the controls to manage them and records who is responsible. It is updated as the work changes and used to brief workers and visitors.