Legislation, regulations and standards for drainlaying
Draw the hierarchy of drainage legislation, regulations and cited standards from memory onto a single page
List the legal duties, notification obligations and offence/penalty provisions that apply to a certifying drainlayer
Match each core drainage standard to the scope of work it governs and note the clauses you must apply on site
Write and sit 20 closed-book recall questions covering licensing, inspections and sign-off responsibilities
Your checkpoint
A two-page legislation-and-standards quick-reference sheet (hierarchy diagram plus standard-to-scope table), validated by scoring at least 90% on your own 20-question closed-book quiz.
Drainage system design, hydraulics and falls
Calculate invert levels and grades for a multi-dwelling run from given surface levels and minimum cover
Convert between percentage, ratio and mm-per-metre gradients and check each result against self-cleansing velocity limits
Size a foul drain and a stormwater line from given fixture and catchment loads using the sizing tables
Diagnose three faulty fall scenarios (flat sections, reverse fall, excessive grade) and specify the corrective design
Your checkpoint
A worked calculation portfolio of 10 gradient, invert-level and pipe-sizing problems, self-marked to at least 90% correct with every error corrected in writing.
Pipe materials, components, jointing and bedding
Classify the main pipe materials by application, stiffness class and joint type
Select the jointing method and bedding class for six given ground-condition and loading scenarios
Specify bedding, surround and backfill requirements for flexible versus rigid pipe, including trench width rules
Compile a components list (fittings, gullies, inspection points, junctions) for a typical residential layout
Your checkpoint
A bedding-and-jointing decision matrix covering six scenarios, each with a written justification that cites the relevant standard clause.
Installation of below-ground and above-ground drainage
Sequence a below-ground installation from set-out through laying, jointing, testing and backfill
Detail correct above-ground stack, branch, trap and vent arrangements for a two-storey dwelling
Identify ten common installation defects from written descriptions and state the compliant fix for each
Plan penetration, support, expansion and protection provisions where the drain passes under or through structures
Your checkpoint
A written installation method statement for a two-storey residential drainage job, plus a 60-question mixed mock on Domains 1, 2, 4 and 5.
Site assessment, ground conditions and earthworks & Testing, commissioning and inspection of drainage systems
Classify given soils and interpret a site investigation (soil class, water table, bearing capacity) to choose trench support and excavation method
Calculate trench dimensions, shoring requirements and compaction-test acceptance for two worked sites
Write the test procedures for water test, air test and CCTV inspection, including pressures, durations and pass criteria
Build a commissioning checklist that links each test result to the inspection and sign-off stage it satisfies
Your checkpoint
A site-assessment memo plus a complete testing and inspection schedule for a 12-dwelling subdivision, cross-checked against the week-1 standards sheet.
Plan interpretation, documentation and certification & Supervision, health and safety, and contracting practice
Extract levels, pipe sizes and fixture counts from a written drainage plan description and list the as-built information required
Assemble the documentation set needed for inspection, certification and code-compliance sign-off
Write a site-specific health and safety plan for a trenching job covering excavation, confined space, PPE and public protection
Describe supervision, verification and record-keeping duties, and how variations and site instructions are documented
Your checkpoint
A combined certification and as-built checklist plus a one-page trenching job safety analysis, reviewed line by line against the legislation sheet from week 1.
Trade waste, on-site wastewater and special drainage systems & Drainage system design, hydraulics and falls & Pipe materials, components, jointing and bedding
Categorise trade waste streams and select pre-treatment (grease interceptor, settling, neutralising) for three given trade premises
Size a grease interceptor and select an on-site wastewater system for given site constraints (soil, area, water table, setback)
Compare pumped, pressure and vacuum special drainage solutions against a stated site problem
Re-drill the weakest 25 questions from your error log until each is answered correctly twice
Your checkpoint
A trade-waste and on-site wastewater selection report for three case sites, plus a closed error log showing every previously missed item re-answered correctly.
Legislation, regulations and standards for drainlaying & Drainage system design, hydraulics and falls & Site assessment, ground conditions and earthworks & Pipe materials, components, jointing and bedding & Installation of below-ground and above-ground drainage & Testing, commissioning and inspection of drainage systems & Trade waste, on-site wastewater and special drainage systems & Plan interpretation, documentation and certification & Supervision, health and safety, and contracting practice
Sit two full-length timed mock exams under exam conditions
Analyse every incorrect answer back to its source standard or regulation and rewrite the rule in your own words
Re-test all flagged weak topics until each reaches consistent accuracy
Rehearse the numeric skills (falls, invert levels, sizing, test pressures) in a single rapid-fire drill
Your checkpoint
Two completed timed mocks scored at least 80%, with a fully resolved error log and a one-page final-revision sheet.
Milestones
Week 2: Complete the 10-problem gradient and invert-level set without notes and score at least 90%.
Week 4: Score at least 70% on the 60-question mock covering Domains 1, 2, 4 and 5, and have the method statement pass a self-review against a 15-point installation checklist.
Week 6: Produce the full documentation and H&S pack with no gaps when checked against the week-1 legislation sheet.
Week 8: Score at least 80% on both full-length timed mocks, with every wrong answer logged, sourced and re-tested to correctness.