Sensible heat equation
Q in Btu/h equals 1.08 times CFM times the dry-bulb temperature difference. The constant assumes standard air density at sea level and is used to size heating or cooling coils.
Total heat equation
Q in Btu/h equals 4.5 times CFM times the enthalpy difference between entering and leaving air. Enthalpy combines sensible and latent heat and requires a psychrometric chart.
Superheat definition
Suction line temperature minus the saturated suction temperature read from the gauge pressure. It confirms the evaporator is fully fed with liquid and the expansion valve is controlling.
Subcooling definition
Saturated condensing temperature minus liquid line temperature. Adequate subcooling proves the condenser is fully charged with liquid and the metering device receives solid refrigerant.
Refrigerant glide
The temperature difference between bubble point and dew point in a zeotropic blend. Superheat uses dew point, subcooling uses bubble point, and charging must follow the manufacturer method.
CFM per ton rule
Nominal cooling airflow is 400 CFM per ton of capacity. Lower airflow increases the temperature split and latent removal but risks coil icing; higher airflow reduces dehumidification.
Combustion air openings
Two permanent openings connecting an appliance space to the rest of the structure are each sized at 1 square inch free area per 1,000 Btu/h of total input for confined installations.
A2L refrigerant classification
ASHRAE 34 class for lower-flammability refrigerants such as R-32 and R-454B. They burn slowly, require charge limits and ignition-source controls, and need updated leak detection.
Water column to psi
One psi equals 2.31 feet of water column. Divide pump head in feet by 2.31 to obtain psi, or multiply psi by 2.31 to obtain feet of head.
Hydronic heat formula
Q in Btu/h equals 500 times GPM times the supply-to-return temperature difference for water. Use lower constants for glycol mixtures because of higher specific heat and density.
Expansion tank precharge
The air-side pressure of a bladder tank set before filling the system. It typically equals the cold fill pressure so the tank accepts expanded water without exceeding relief pressure.
RPZ backflow assembly
A reduced-pressure zone device with two check valves and a relief valve. It is required for high-hazard cross-connections and must be tested annually by a certified tester.
Water fixture unit
A dimensionless load value assigned to a fixture. Total water supply fixture units convert to probable demand in gallons per minute through the Hunter curve for pipe sizing.
Drain slope rule
Horizontal drainage pipe smaller than 3 inches slopes at 1/4 inch per foot. Pipe 4 inches and larger may slope at 1/8 inch per foot while maintaining self-scouring velocity.
T&P relief discharge
The water heater temperature and pressure relief valve must discharge through a full-size pipe to within 6 inches of the floor or outdoors. It cannot be trapped or reduced.
Series loop hydronic system
A piping arrangement where water flows through each terminal unit in sequence. It is simple and inexpensive but delivers decreasing temperature to downstream emitters.
Ohm's law and power
Voltage equals current times resistance. Power in watts equals voltage times current, and for reactive loads multiply by the power factor to get true power.
Three-phase power equation
P in watts equals 1.732 times line voltage times line current times power factor for a balanced three-phase load. The 1.732 factor is the square root of three.
Motor branch circuit sizing
Branch-circuit conductors are sized at 125 percent of the motor full-load current from the NEC tables, not from the nameplate current, before ampacity adjustments.
Motor overload protection
A device that protects the motor winding from sustained overcurrent. It is sized from nameplate service factor and separate from the short-circuit protection that clears faults.
Equipment grounding conductor
The conductor that provides a low-impedance fault path back to the source. Its size comes from NEC Table 250.122 and is based on the overcurrent device rating.
Voltage drop formula
Single-phase voltage drop equals 2 times conductor constant K times current times length divided by circular mils. Three-phase replaces the 2 with 1.732.
GFCI protection locations
Ground-fault circuit interrupter protection is required in bathrooms, garages, outdoors, kitchens, and near sinks. It interrupts the circuit when current leaks to ground.
Motor disconnect location
The disconnecting means must be within sight of the motor and its controller. A horsepower-rated switch or circuit breaker is required unless the breaker is lockable.
ORC Chapter 4740 scope
Ohio law that licenses heating, ventilating, air conditioning, refrigeration, plumbing, hydronics, and electrical contractors. The OCILB administers licenses and enforces standards.
OCILB role
The Ohio Construction Industry Licensing Board issues, renews, and disciplines contractor licenses. It adopts administrative rules covering exams, continuing education, and fees.
Experience requirement
Applicants must document at least 5 years of business experience in the trade, or equivalent education and experience the board accepts, before taking the licensing exam.
Continuing education requirement
Licensees must complete board-approved continuing education hours each renewal cycle. Certificates must be kept and produced on audit or the license may not renew.
Surety bond requirement
Contractors must maintain a bond and liability insurance as a condition of licensure. Failure to keep coverage can result in suspension of the license.
License non-transferability
A contractor license belongs to the named licensee and cannot be sold, assigned, or used by another person or entity. Work must be performed under the licensed contractor.
Unlicensed practice penalties
The board may seek civil penalties and injunctive relief against unlicensed contracting. It may also refuse, suspend, or revoke licenses for violations of the chapter.