OK General Contractor study materials
OK General Contractor study resources

OK General Contractor cheat sheet

OK General Contractor · Keep the key ideas within reach.

Quick reference

Business and Project Management

  • Critical path method: the longest continuous path through the network; total project duration equals the critical path length, and any delay on it delays completion unless float is recovered.

  • Float (slack) = late start minus early start, or late finish minus early finish; float is shared on a path, so consuming it affects every activity on that path.

  • Retainage in Oklahoma private construction is commonly 5-10% of each progress payment; on public contracts retainage is limited by statute to 5% of the contract price.

  • Earned value: CPI = EV/AC (cost efficiency), SPI = EV/PV (schedule efficiency); CPI below 1.0 means over budget, SPI below 1.0 means behind schedule.

  • Estimate at completion (EAC) = BAC/CPI when current cost performance is expected to continue; VAC = BAC minus EAC.

  • Change order pricing should be agreed before work proceeds; absent agreement, use force-account (time and materials) with documented labor rates, equipment, and markup.

  • A pay-when-paid clause shifts payment risk downstream but does not eliminate the prime contractor's ultimate obligation to the owner's satisfaction of conditions precedent.

  • Submittal review turnaround is governed by the contract's specified review period; approval does not relieve the contractor of responsibility for dimensional or coordination errors.

Quick reference

Estimating and Plan Reading

  • Scale conversion: measured length on paper x denominator of the scale (e.g., 1/4 inch = 1 foot means 1 inch on paper equals 4 feet) gives actual length.

  • Plan symbols: solid line = visible edge, dashed = hidden, centerline (long-short dash) = axis of symmetry or structural grid; grid lines are lettered one way and numbered the other.

  • Section cut marks show the drawing sheet and detail number; elevation marks show a datum triangle with the finished floor value relative to a stated benchmark.

  • Quantity takeoff for concrete: volume = length x width x depth in consistent units; divide cubic feet by 27 for cubic yards, then add waste (typically 5-10%).

  • Rebar weight: No. 4 bar = 0.668 lb/ft, No. 5 = 1.043 lb/ft, No. 6 = 1.502 lb/ft; weight per foot = (bar number squared)/2.67 approximately.

  • Masonry count: modular brick (nominally 3-5/8 x 2-1/4 x 7-5/8 in) with 3/8 in joints yields about 6.75 brick per square foot of wall face.

  • Board feet = (thickness in inches x width in inches x length in feet)/12; lumber is priced per thousand board feet (MBF).

  • Contingency is added to the base estimate for undefined scope; escalation adjusts for cost change between estimate date and construction date.

Quick reference

Sitework and Earthwork

  • Swell is the increase in volume when soil is excavated and loosened; shrinkage is the decrease when compacted fill is placed. Bank volume x (1 + swell) = loose volume.

  • Compaction is specified as a percentage of maximum dry density from a standard (Proctor) or modified Proctor test; typical structural fill requires 95% of standard Proctor.

  • Optimum moisture content produces maximum dry density; adding water or drying soil moves density toward that peak.

  • Cut and fill balance: net volume = cut volume minus fill volume divided by (1 - shrinkage) for compacted fill; haul distance determines whether to waste, borrow, or move on site.

  • Slope stability: angle of repose for granular soil approximates the internal friction angle; temporary excavations 5 ft or deeper require a protective system under OSHA 1926 Subpart P.

  • Trench spoil must be kept at least 2 ft back from the excavation edge to reduce surcharge loading on the trench walls.

  • Stormwater: silt fence, sediment basins, and stabilized construction entrances are typical BMPs; a Stormwater Pollution Prevention Plan (SWPPP) is required for covered construction sites.

  • Erosion vs. sediment control: erosion control prevents soil detachment (mulch, matting), sediment control traps moved soil (silt fence, traps).

Quick reference

Concrete and Masonry

  • Water-cement ratio controls strength and durability: lower w/c means higher strength and lower permeability; typical structural mixes run 0.40-0.50.

  • Concrete must be placed within its specified workability window; generally discharge within 90 minutes of batching unless a retarder is approved.

  • Curing maintains moisture and temperature; moist curing for 7 days is typical for Type I cement, and cold-weather protection is required when ambient falls near or below 40 F.

  • Formwork removal: vertical forms may be removed when concrete is strong enough to resist damage; soffit forms under beams and slabs require strength verification or specified curing periods.

  • Reinforcement cover protects steel from corrosion and provides fire resistance; cover requirements vary by exposure and member, commonly 1.5 to 3 inches for cast-in-place against earth.

  • Masonry mortar joints: head and bed joints are typically 3/8 inch; mortar type M is highest strength, Type N is general-purpose above grade, Type S is moderate-high strength.

  • Masonry wall ties, flashing, and weep holes form the drainage plane; flashing must lap and terminate with weep holes at the base of the cavity.

  • Grout in reinforced masonry must fill cells completely; grout lift height and consolidation by puddling or vibration are specified by code and must be inspected.

Quick reference

Metals and Wood Construction

  • Structural steel connections: bolted connections use A325/A490 (or F3125) high-strength bolts; slip-critical joints require specified minimum tension and turn-of-nut or tension-calibrated tightening.

  • Welding symbols: arrow points to the joint, the reference line carries the weld symbol above (other side) or below (arrow side); a tail holds process or reference notes.

  • Steel erection tolerances and plumbness are checked before final bolting; shimming and leveling nuts correct base plate elevation.

  • Wood grading: visually graded lumber is stamped with grade, species, and moisture content; design values differ by grade and species, and Fb (bending) is adjusted for size and duration.

  • Nominal vs. dressed lumber: a 2x4 is actually 1-1/2 x 3-1/2 inches; nominal dimensions are used for naming, actual for design checks.

  • Wood connectors: joist hangers, hold-downs, and straps must be installed with the manufacturer's specified fasteners; substituting nails voids the listed capacity.

  • Moisture content matters: lumber installed at high moisture shrinks as it dries, causing gaps and nail pops; kiln-dried framing is typically 19% or less.

  • Fire-retardant treatment and preservative treatment are distinct; exposed structural wood in rated assemblies must match the listed assembly's treatment and species.

Quick reference

Thermal, Moisture, and Openings

  • R-value is thermal resistance; U-factor is its reciprocal (U = 1/R). Assembly U-factors combine parallel paths by area-weighted average.

  • Vapor retarders belong on the warm side of the assembly in cold climates; in hot-humid climates, vapor drive can reverse and placement must follow climate-specific guidance.

  • Air barriers control infiltration, which can dominate heat loss; a continuous air barrier must be sealed and aligned with the insulation layer.

  • Water management: drain the cavity, flash the openings, and lap materials shingle-style so upper layers shed over lower ones.

  • Window performance: U-factor measures heat flow, SHGC measures solar heat gain; low SHGC reduces cooling loads in cooling-dominated climates like Oklahoma.

  • Flashing sequence at openings: sill pan first, then jambs, then head; head flashing laps over the sides and the weather-resistive barrier laps over the head flange.

  • Doors and windows require shimming at hinge and lock points and anchoring per manufacturer; rough opening dimensions are the framed opening, not the unit size.

  • Thermal bridging through steel studs and slab edges reduces effective R-value; continuous exterior insulation breaks the bridge.

Quick reference

Mechanical, Electrical, and Plumbing Coordination

  • Coordination drawings (composite or BIM clash detection) resolve conflicts between ductwork, piping, conduit, and structure before installation.

  • Slope requirements: sanitary drain lines typically slope 1/4 inch per foot for 2-inch and smaller, 1/8 inch per foot for 3-inch and larger, per plumbing code.

  • Duct sizing: velocity method and equal-friction method are common; friction loss is expressed in inches of water per 100 ft of duct.

  • Electrical: conductors are sized by ampacity and protected by overcurrent devices; voltage drop should be limited, commonly to 3% on branch circuits and 5% total.

  • Clearances: working space in front of electrical equipment (typically 36 inches, greater for higher voltages) must be kept clear and cannot be used for storage.

  • Penetrations through rated assemblies require listed firestop systems; fire dampers are required where ducts penetrate fire-rated walls or floors.

  • Rough-in inspections must occur before concealment; pressure testing of drain, waste, and vent systems and of water piping is required before closure.

  • Equipment access and service clearance: maintain manufacturer-required clearances for coil replacement, filter access, and electrical disconnects.

Quick reference

Safety, OSHA, and Environmental Compliance

  • OSHA 1926 Subpart M: fall protection is required at 6 ft or more in construction; guardrails, safety nets, or personal fall arrest systems are acceptable.

  • Fall arrest systems must limit maximum arresting force to 1,800 lb and keep free fall to 6 ft or less; anchorages must support 5,000 lb per worker or be designed by a qualified person.

  • Excavations 5 ft or deeper require a protective system unless the excavation is entirely in stable rock; trenches 4 ft or deeper require a means of egress within 25 ft of lateral travel.

  • Scaffolding: guardrails required at 10 ft or more; the scaffold must be designed by a qualified person and erected by trained workers, with footing on stable base.

  • Hazard communication: Safety Data Sheets must be accessible, containers labeled, and employees trained on chemical hazards under 29 CFR 1910.1200.

  • Personal protective equipment: hard hats, eye protection, and hearing protection are required where hazards exist; PPE is the last line of defense in the hierarchy of controls.

  • Environmental: asbestos and lead require survey and abatement by certified workers before demolition; disposal of regulated waste follows EPA and state rules.

  • Recordkeeping: OSHA 300 log entries are required for work-related injuries and illnesses; fatalities must be reported within 8 hours, in-patient hospitalizations within 24 hours.

Quick reference

Oklahoma Code, Licensing, and Lien Law

  • Oklahoma Construction Industries Board (CIB) licenses trade contractors and administers the state's construction codes; local jurisdictions may adopt and enforce their own codes.

  • Oklahoma adopted the Oklahoma Uniform Building Code Commission (OUBCC) codes, which are based on the International Codes; verify the edition and local amendments before bidding.

  • Mechanics' and materialmen's liens in Oklahoma: a pre-lien notice is required for certain claimants, and a lien statement must be filed with the county clerk within the statutory period (generally 90 days after last furnishing labor or materials for most claimants).

  • An owner may demand a lien statement; failure to respond within the statutory time can bar the lien. Suit to foreclose a lien must be filed within the statutory period after filing.

  • On public works, mechanics' liens do not attach to public property; the bond claim process (Little Miller Act equivalent under Oklahoma statutes) provides the remedy.

  • Contractor licensing: a state contractor license is required for many trades; unlicensed contracting can bar recovery of compensation and expose the contractor to penalties.

  • Lien waivers: a conditional waiver becomes effective upon payment; an unconditional waiver is effective on signing, so never sign one before funds clear.

  • Prompt payment: Oklahoma statutes set payment timelines for public contracts; for private work, contract terms govern, but pay-when-paid clauses are construed strictly.

Quick reference

Estimating and Plan Reading (supplemental)

  • Roof pitch is rise over run; a 4:12 pitch means 4 inches of rise per 12 inches of horizontal run, giving a slope factor of about 1.054 for area calculations.

  • Area of a triangle = 1/2 x base x height; area of a trapezoid = average of parallel sides x height; break irregular takeoffs into simple shapes.

  • Concrete slab on grade: add for thickened edges and footings separately; vapor retarder and reinforcement are measured by area or weight.

  • Steel takeoff: weight = length x weight per foot from the AISC manual; add for connections, base plates, and miscellaneous items by percentage.

  • Drywall: board count = wall area divided by board area, plus 10% waste; joint compound and tape are estimated per 1,000 sq ft of board.

  • Painting: coverage rates are stated per gallon (typically 350-400 sq ft per coat); number of coats and surface porosity affect quantity.

  • Labor productivity is expressed in units per labor hour or hours per unit; crew size times hours gives labor cost when multiplied by the loaded rate.

  • Plan reading order: cover sheet and index, general notes, life safety plan, floor plans, elevations, sections, details, and schedules; cross-check dimensions between views.

Quick reference

Sitework and Earthwork (supplemental)

  • Soil classification by USCS groups: GW, GP, GM, GC (gravels); SW, SP, SM, SC (sands); ML, CL, OL (silts and clays of low plasticity); MH, CH, OH (high plasticity).

  • Liquid limit and plasticity index describe fine-grained soil behavior; high PI indicates expansive clay, common in Oklahoma and requiring special foundation treatment.

  • Expansive soils: mitigate with over-excavation and replacement, moisture conditioning, or pier foundations extending below the active zone.

  • Bearing capacity is verified by geotechnical investigation; spread footings, drilled piers, and mat foundations are selected based on soil report recommendations.

  • Subgrade preparation includes proof-rolling, scarifying, moisture conditioning, and compaction in lifts typically 6-8 inches loose.

  • Dewatering: sumps and pumps for shallow groundwater; wellpoints for deeper drawdown; discharge must be managed to avoid erosion and comply with permits.

  • Utility locating: call 811 before digging; Oklahoma requires notification before excavation so public utilities can mark their lines.

  • Grade stakes and laser levels establish elevation control; benchmarks must be tied to a known datum and protected during construction.

Quick reference

Concrete and Masonry (supplemental)

  • Concrete mix design: cement, water, fine aggregate, coarse aggregate, and admixtures; air entrainment improves freeze-thaw resistance in exterior concrete.

  • Slump test (ASTM C143) measures workability; cylinders (ASTM C39) are tested at 7 and 28 days, with 28-day strength typically the design criterion.

  • Hot weather concreting: reduce slump loss by cooling ingredients, using retarders, and placing promptly; avoid adding water at the job site.

  • Cold weather concreting: maintain concrete temperature above 50 F during protection period; use accelerators and insulating blankets as needed.

  • Masonry reinforcement: horizontal joint reinforcement and bond beams with rebar provide crack control and lateral strength.

  • Mortar and grout are different materials; grout has higher water content and is placed in reinforced cells, while mortar bonds units.

  • Efflorescence is a cosmetic salt deposit from moisture migration; it indicates water entry and should be addressed at the source, not just cleaned.

  • Control joints in concrete and masonry are planned crack locations; spacing depends on panel aspect ratio and thickness, typically 2-3 times thickness in feet for slabs.

Quick reference

Metals and Wood Construction (supplemental)

  • Steel beam designations: W-shapes are wide-flange, S-shapes are standard I-beams, and C-shapes are channels; the depth and weight per foot identify the section (e.g., W12x26).

  • Composite construction uses shear studs to transfer force between steel beam and concrete slab, increasing effective strength.

  • Light-gauge steel framing: studs are designated by web depth, flange width, and gauge; screws and welds are typical connections.

  • Wood trusses are engineered components; field modifications, notching, or cutting chords voids the design and requires an engineer's approval.

  • Notching and boring limits for joists: notches in the top or bottom edge are limited in depth and location; holes must be centered and sized per code.

  • Decay and termites: pressure-treated wood is required where wood contacts masonry or concrete, and in areas of high termite hazard.

  • Fireblocking and draftstopping limit concealed air movement in wood-frame assemblies; required at floor levels and in concealed chases.

  • Metal studs require careful layout for opening framing and backing; blocking must be installed for cabinets, grab bars, and heavy fixtures.

Quick reference

Thermal, Moisture, and Openings (supplemental)

  • Insulation types: batt, blown-in, spray foam, rigid board; spray foam provides air sealing in addition to insulation.

  • Attic ventilation: intake at soffits and exhaust at ridge or gable; balanced ventilation extends roof life and reduces moisture problems.

  • Roof underlayment is a secondary moisture barrier; ice and water shield is required at eaves in cold climates and at valleys.

  • Roofing slope: low-slope roofs (less than 3:12) use membrane or built-up systems; steep-slope roofs use shingles, tile, or metal.

  • Window and door installation: use the manufacturer's flashing details; sealant alone is not a substitute for proper flashing.

  • Moisture in buildings: control bulk water first, then capillary, then air-transported moisture, then vapor diffusion; air leakage moves far more moisture than diffusion.

  • Thermal envelope continuity: insulate and air-seal at rim joists, penetrations, and transitions to prevent condensation and energy loss.

  • Door hardware and egress: egress doors must swing in the direction of travel where required by occupancy and must have panic hardware in assembly occupancies.

Quick reference

Mechanical, Electrical, and Plumbing Coordination (supplemental)

  • HVAC load calculation uses Manual J or equivalent; equipment sizing must match the calculated load, not rules of thumb.

  • Duct leakage testing is required in many codes; sealing ducts in conditioned space improves efficiency and comfort.

  • Refrigerant piping: line sizes and lengths are specified by the manufacturer; excessive length or vertical rise reduces capacity.

  • Plumbing vents protect trap seals; each fixture requires a vent unless it is a listed fixture with an approved air admittance valve.

  • Water heater seismic and thermal expansion: expansion tanks and temperature-pressure relief valves are required; discharge piping must terminate safely.

  • Electrical grounding and bonding: grounding electrode system, equipment grounding conductors, and bonding of metallic piping are required for safety.

  • Panel schedules and circuit directories must be accurate and updated; spare capacity should be planned for future loads.

  • Coordination of hangers and supports: duct, pipe, and conduit supports must not conflict with structure; seismic bracing may be required.

Quick reference

Safety, OSHA, and Environmental Compliance (supplemental)

  • Hazard Communication Standard (HazCom) requires a written program, labeling, SDS access, and training for employees exposed to hazardous chemicals.

  • Lockout/tagout (1910.147) controls hazardous energy during servicing; only authorized employees may perform lockout.

  • Confined spaces: permit-required confined spaces require atmospheric testing, ventilation, attendant, and rescue plan before entry.

  • Cranes and rigging: qualified rigger and signal person requirements; load charts must be followed, and swing radius must be barricaded.

  • Electrical safety: GFCI protection is required for temporary receptacles on construction sites; extension cords must be inspected and rated for hard usage.

  • Housekeeping and walking-working surfaces: keep walkways clear, cover or guard floor openings, and maintain safe access.

  • Environmental permits: NPDES construction general permit for stormwater; air permits for demolition and dust-generating activities may apply.

  • Spill prevention and response: store fuels and chemicals with secondary containment; have spill kits and trained responders on site.

Quick reference

Oklahoma Code, Licensing, and Lien Law (supplemental)

  • Oklahoma requires contractors to be licensed by the Construction Industries Board for many trades; license classifications determine the scope and value of work allowed.

  • Bonding: contractors may be required to post a surety bond as a condition of licensure; public works contracts require performance and payment bonds above statutory thresholds.

  • Lien deadlines in Oklahoma are strict; missing the filing or suit deadline generally extinguishes the lien right regardless of the merits of the claim.

  • A notice of lien should be served on the owner and, where required, on the prime contractor; proof of service is important evidence.

  • Contractors should obtain a preliminary notice or pre-lien notice where required to preserve lien rights; requirements differ for subcontractors and suppliers.

  • Oklahoma's consumer protection laws and the CIB complaint process allow homeowners to file complaints against licensed contractors for violations.

  • Contract terms: written contracts should state scope, price, payment schedule, change order procedure, and dispute resolution; oral contracts are enforceable but harder to prove.

  • Warranty and call-back obligations: express warranties in the contract govern; implied warranties of workmanlike quality may apply even without an express term.