- Critical path
- The longest sequence of dependent activities through a project network; its length sets the minimum project duration, and any delay on it delays the project unless float is recovered.
- Earned value CPI
- Cost Performance Index equals earned value divided by actual cost. A value below 1.0 indicates the project is spending more than the work performed is worth.
- Retainage
- A percentage withheld from each progress payment until final completion. Oklahoma public contracts commonly cap it at 5 percent; private contracts often use 5 to 10 percent.
- Scale conversion
- On a drawing scaled one-quarter inch equals one foot, one inch on paper represents four feet in reality. Multiply measured paper length by the scale denominator.
- Board foot
- A lumber volume unit equal to a board one inch thick, twelve inches wide, and twelve inches long. Formula: thickness times width times length divided by twelve.
- Rebar weight No. 5
- A number 5 deformed bar weighs about 1.043 pounds per linear foot. Bar weight per foot approximates the bar number squared divided by 2.67.
- Soil swell
- The percentage volume increase when bank soil is excavated and loosened. Bank volume multiplied by one plus swell gives loose volume for hauling calculations.
- Proctor compaction
- A laboratory test establishing maximum dry density and optimum moisture content for a soil. Field compaction is specified as a percentage of that maximum dry density.
- Trench protective systems
- OSHA requires a protective system for excavations five feet or deeper unless in stable rock. Sloping, shoring, shielding, or benching are acceptable methods.
- Water-cement ratio
- The ratio of water to cementitious material by weight. Lower ratios increase strength and reduce permeability; typical structural concrete uses 0.40 to 0.50.
- Concrete curing
- Maintaining moisture and temperature so cement hydrates. Moist curing for about seven days is typical; cold weather requires protection near or below 40 degrees Fahrenheit.
- Masonry mortar types
- Type M is highest strength, Type S is moderate-high, Type N is general purpose above grade, and Type O is low strength for interior non-load-bearing use.
- High-strength bolts
- A325 and A490 bolts used in structural steel connections. Slip-critical joints require specified tension achieved by turn-of-nut or calibrated wrench methods.
- Nominal versus dressed lumber
- Nominal size is the name, such as 2x4. Dressed actual size is smaller, about 1-1/2 by 3-1/2 inches, and actual dimensions govern design calculations.
- Joist hanger fasteners
- Connectors must use the manufacturer's specified fasteners. Substituting different nails or screws voids the published load capacity and may fail inspection.
- R-value and U-factor
- R-value measures thermal resistance; U-factor is its reciprocal. Lower U-factor means better insulating performance for windows and assemblies.
- Flashing sequence
- At openings, install the sill pan first, then jamb flashing, then head flashing. Upper layers must lap over lower layers so water sheds outward.
- SHGC
- Solar Heat Gain Coefficient measures the fraction of solar radiation admitted through a window. Lower values reduce cooling loads in hot climates such as Oklahoma.
- Sanitary drain slope
- Drain lines typically slope one-quarter inch per foot for two-inch and smaller pipe and one-eighth inch per foot for three-inch and larger pipe.
- Electrical working clearance
- Clear space in front of electrical equipment, generally 36 inches and greater for higher voltages. The space must remain clear and cannot be used for storage.
- Firestop penetration
- A listed system restoring the fire rating of a wall or floor where pipe, conduit, or duct passes through. Fire dampers are required where ducts penetrate rated assemblies.
- Fall protection threshold
- OSHA requires fall protection at six feet or more in construction. Guardrails, safety nets, or personal fall arrest systems are acceptable controls.
- Fall arrest forces
- Personal fall arrest must limit arresting force to 1,800 pounds and free fall to six feet or less. Anchors must support 5,000 pounds per worker.
- Hazard Communication
- Requires labeled containers, accessible safety data sheets, a written program, and employee training for workers exposed to hazardous chemicals on site.
- Oklahoma CIB
- The Construction Industries Board licenses trade contractors and administers construction codes. Local jurisdictions may adopt and enforce their own amendments.
- Oklahoma lien filing
- A lien statement is filed with the county clerk within the statutory period, generally 90 days after last furnishing labor or materials for most claimants.
- Conditional lien waiver
- A waiver that becomes effective only when payment is received. An unconditional waiver is effective upon signing, so never sign one before funds clear.
- Public works lien remedy
- Mechanics' liens do not attach to public property. Claimants instead pursue payment bonds, following the statutory notice and claim procedures for public contracts.
- Roof slope factor
- A multiplier converting plan area to sloped area. A 4:12 pitch has a factor near 1.054; steeper pitches increase the factor and material quantities.
- Expansive clay soils
- Fine-grained soils with high plasticity index that swell when wet and shrink when dry. Common in Oklahoma; mitigated by over-excavation, moisture control, or deep foundations.
- Air barrier continuity
- A sealed, continuous layer controlling infiltration. Air leakage transports far more moisture and heat than vapor diffusion, so continuity at joints matters most.
- Lockout tagout
- A procedure controlling hazardous energy during servicing. Only authorized employees apply locks and tags, and energy must be verified as isolated before work begins.