OK General Contractor study materials
OK General Contractor study resources

OK General Contractor study plan

OK General Contractor · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Business and Project Management & Oklahoma Code, Licensing, and Lien Law

  • Build a one-page map of the five project delivery methods (design-bid-build, CM at risk, design-build, agency CM, multiple prime) and match each to the contract type and risk allocation it implies.

  • Draft a CPM logic diagram for a 20-activity building shell schedule, then identify the critical path and total float on three non-critical chains.

  • List the Oklahoma Construction Industries Board licensing classes and the threshold rules that decide when a contractor must hold a state license versus work under local permits only.

  • Summarize the Oklahoma prompt-payment statute timeline (invoice, approval, payment, interest) in a dated flow you can reproduce from memory.

Your checkpoint

A two-page reference sheet containing the delivery-method matrix, the completed CPM diagram with critical path marked, and the Oklahoma licensing/prompt-payment timeline.

Week 2

Business and Project Management & Estimating and Plan Reading

  • Produce a full quantity takeoff for a simple one-story office shell: excavation, footings, slab, masonry, framing, and drywall, with units and waste factors shown.

  • Convert the takeoff into a priced estimate with labor, material, equipment, overhead, and profit separated into distinct line groups.

  • Read a 12-sheet plan set and write a takeoff checklist that captures every dimension source (plan, section, detail, schedule) you used.

  • Explain how alternates, allowances, and unit prices are handled differently in a bid summary.

Your checkpoint

A priced estimate workbook for the office shell with a one-page assumptions and exclusions memo.

Week 3

Safety, OSHA, and Environmental Compliance & Sitework and Earthwork

  • Map the OSHA Focus Four hazards to the specific 1926 subparts that govern them and the abatement each subpart requires.

  • Write a site-specific fall-protection and excavation safety plan for a project with a 12-foot cut and a two-story structural frame.

  • Calculate soil volume change using swell and shrinkage factors and apply the results to a cut-and-fill balance for a 100-foot by 200-foot pad.

  • Identify the OSHA excavation requirements for protective systems, spoil pile setback, access and egress, and daily competent-person inspection.

Your checkpoint

A combined safety and earthwork plan that includes the cut-and-fill balance calculation, haul volume, and the citation basis for each control measure.

Week 4

Safety, OSHA, and Environmental Compliance & Oklahoma Code, Licensing, and Lien Law

  • Assemble the Oklahoma lien process end to end: pre-lien notice, filing deadline, affidavit of lien, foreclosure window, and the owner's remedy to discharge a lien.

  • Distinguish lien rights for general contractors, subcontractors, and suppliers, and note where the preliminary notice requirement changes the analysis.

  • Build a jobsite environmental compliance checklist covering stormwater permits, erosion control, spill prevention, and waste disposal documentation.

  • Recite the recordkeeping and posting obligations that trigger OSHA citations most often on small commercial jobs.

Your checkpoint

A one-page Oklahoma lien timeline plus a one-page environmental and recordkeeping compliance checklist, both written to be used on a live job.

Week 5

Concrete and Masonry & Metals and Wood Construction

  • Solve concrete mix design problems: water-cement ratio, yield, and adjusting a trial mix for field moisture in the aggregate.

  • Explain formwork pressure, shoring and reshoring sequence, and the cure-time rules that govern when forms and shores may be removed.

  • Compare structural steel, light-gage steel, and wood framing for a given span and loading condition, naming the failure mode each is designed to resist.

  • Detail masonry wall components: flashing, weep holes, movement joints, anchors, and the reinforcement lap requirements that tie them together.

Your checkpoint

A worked problem set of ten concrete, masonry, and steel/wood calculations with a short written justification for each answer.

Week 6

Thermal, Moisture, and Openings & Mechanical, Electrical, and Plumbing Coordination

  • Draw a wall section from footing to roof that correctly layers weather barrier, flashing, insulation, air barrier, and drainage plane, and label the water-shedding intent of each layer.

  • Specify window and door performance requirements (U-factor, SHGC, DP rating, fire rating) for three different occupancies and justify each choice.

  • Coordinate a mechanical, electrical, and plumbing clash set: identify sleeve locations, ceiling plenum conflicts, and clearance requirements for equipment service access.

  • Explain how BIM coordination and the submittal process sequence with structural and architectural work to prevent rework.

Your checkpoint

A hand-drawn wall section with labeled control layers plus a clash list of at least eight MEP conflicts with the resolution you would direct.

Week 7

Estimating and Plan Reading & Business and Project Management

  • Complete a timed 40-question mixed-domain practice set and log every wrong answer by domain and root cause (misread, knowledge gap, calculation error).

  • Re-derive the three formulas you missed most often until you can write them from memory without notes.

  • Draft a change-order package for a scope change: pricing, time impact, schedule revision, and the contract clause that authorizes it.

  • Review the plan-reading conventions you got wrong on the practice set and rebuild the affected takeoff items.

Your checkpoint

An error log with root-cause categories, a corrected formula sheet, and a complete change-order document.

Week 8

Safety, OSHA, and Environmental Compliance & Oklahoma Code, Licensing, and Lien Law & Business and Project Management

  • Retake a full-length timed practice exam under exam conditions and score it against your target passing margin.

  • Review only the error log and formula sheet, not new material, in the final three days.

  • Recite the Oklahoma licensing thresholds, lien deadlines, and OSHA Focus Four controls aloud without reference.

  • Finalize exam-day logistics: identification, scheduling confirmation, calculator policy, and a break plan.

Your checkpoint

A scored full-length practice exam with a written final-week review plan showing which domains still need attention.

Milestones

Week 2: You can complete a takeoff and priced estimate for a small shell building in under three hours with assumptions documented.

Week 4: You can state the Oklahoma lien filing and foreclosure deadlines and the OSHA Focus Four controls from memory with no notes.

Week 6: You score at least 70 percent on a mixed 40-question set spanning concrete, masonry, metals, wood, envelope, and MEP.

Week 8: You score at or above your target passing margin on a full-length timed practice exam and your error log shows no repeated root cause.