TN General Contractor case studies
TN General Contractor · Put your knowledge to work in context.
The Tennessee General Contractor examination is the licensing test administered for contractors who intend to take on commercial or residential projects above the dollar threshold that Tennessee law sets for licensure. It is aimed at working contractors, construction managers, and owners who already know how to build but now need to demonstrate that they can run a business legally, price and schedule work competently, and answer to the state Board for Licensing Contractors. The TN General Contractor case studies are 5 cases and about 4,422 words.
1Retainage Squeeze on a Growing Backlog
Ridgeline Construction LLC holds a Tennessee BC license with a 1.5M monetary limit and carries a 2M aggregate / 1M single-project bonding line. Backlog is 2.4M across four jobs that cover overhead but throw off no surplus cash.
813 words, about 4 min2The Qualifier Walked Out
Delta Ridge Contracting, LLC holds a Tennessee contractor's license with a 900,000 monetary limit. Its designated qualifier, the only person in the company who ever passed the trade exam, resigned six weeks ago and now works for a competitor.
818 words, about 4 min3The Remote Claimant and the Pay-If-Paid Clause
Summit Erectors, a steel erection subcontractor, has a 212,000 contract with Tri-State Fabricators, who is the steel subcontractor to the prime on a private Nashville office project. There is no payment bond.
967 words, about 5 min4Eighteen Days Late and One Late Letter
A 3.6M school renovation contract gives 150 calendar days to substantial completion, liquidated damages of 1,200 per day capped at 10% of the contract sum, and a clause requiring written notice of any delay within 7 days of the event. The accepted schedule carried 6 weather days for the entire calendar.
916 words, about 5 min5Two Feet of Silt and a Disclaimer
On a 100 ft × 60 ft retail pad, footing excavation for a one-story masonry building exposes 3 to 6 ft of organic silt below the bearing elevation shown on the drawings. The geotechnical report, incorporated by reference, was based on two borings at opposite corners and described “stiff to very stiff clay.” The contract states that the contractor is responsible for verifying subsurface conditions and that all excavation is included in the lump sum.
908 words, about 5 min