TN General Contractor · Keep the key ideas within reach.

Quick reference

Business Organization, Financial Management, and Accounting

  • Accounting equation: assets = liabilities + owner's equity; each transaction affects at least two accounts.

  • Current ratio = current assets ÷ current liabilities; a value below 1.0 means near-term assets cannot cover near-term obligations.

  • Working capital = current assets − current liabilities.

  • Gross profit = revenue − cost of goods sold; gross margin % = (gross profit ÷ revenue) × 100.

  • Selling price = cost ÷ (1 − target margin %); markup % = (price − cost) ÷ cost. A 20% markup is only a 16.7% margin.

  • Straight-line depreciation = (cost − salvage value) ÷ useful life in years.

  • Percentage-of-completion revenue = total contract price × (costs incurred to date ÷ total estimated costs).

  • 'Costs and estimated earnings in excess of billings' is a current asset; 'billings in excess of costs' is a current liability.

  • A sole proprietor reports business income on personal returns and carries unlimited personal liability; corporations and LLCs shield owners' personal assets.

Quick reference

Contract Law and Contract Administration

  • A valid contract requires offer, acceptance, consideration, capacity, and a lawful purpose.

  • Statute of Frauds requires a writing for contracts that cannot be performed within one year and for promises to answer for another's debt.

  • Constructive change: owner-directed or owner-caused work treated as a change even though no written change order was issued.

  • Cardinal change: a deviation so far beyond the contract scope that it is a breach rather than an ordinary change.

  • Pay-if-paid makes owner payment a condition precedent to subcontractor payment; pay-when-paid is only a timing mechanism.

  • Differing site conditions: Type I is a subsurface or latent physical condition materially different from the contract documents; Type II is an unknown physical condition of an unusual nature.

  • Substantial completion starts warranties, permits owner occupancy, and commonly starts the limitations period for claims.

  • Flow-down (incorporation by reference) clauses pass prime-contract duties and remedies to subcontractors and suppliers.

Quick reference

Tennessee Contractor Licensing Law and Board Rules

  • The Tennessee Contractors Licensing Act is codified at TCA Title 62, Chapter 6, and is administered by the Board for Licensing Contractors.

  • A contractor license is required for projects of $25,000 or more in total cost; projects from $3,000 to $24,999 require a home improvement license.

  • A license is issued to an entity only through a qualifying agent (designated qualifier) who passes the required examinations and remains actively involved.

  • Each license carries a monetary limit per single project; contracting or bidding above that limit is a licensing violation.

  • The license number must appear on bids, contracts, permits, and advertising.

  • The license must already be held before bidding on work that requires a license.

  • The Board may issue citations and civil penalties, suspend or revoke a license, and order restitution to consumers.

  • Changes of qualifying agent must be reported to the Board; loss of the qualifier jeopardizes the entity's license.

Quick reference

Liens, Payment Bonds, and Payment Provisions

  • A mechanic's lien is recorded in the Register of Deeds of the county where the improved property is located.

  • The lien instrument must state the amount claimed, owner's name, property description, claimant's name, and the date labor or materials were last furnished.

  • An enforcement suit on a recorded Tennessee mechanic's lien must be filed within the statutory period (generally six months after recording).

  • Liens do not attach to public property; public works are protected instead by payment bonds under Little Miller Acts.

  • The federal Miller Act requires payment and performance bonds on federal construction contracts over $150,000.

  • A Miller Act claimant must give written notice to the surety within 90 days after last furnishing and sue within one year.

  • Four lien waiver forms: conditional progress, unconditional progress, conditional final, unconditional final.

  • A conditional waiver takes effect only upon actual receipt of the funds stated in the waiver.

Quick reference

Employment Law, Labor Relations, and Jobsite Safety

  • OSHA 29 CFR 1926 governs construction; fall protection is required at 6 ft in construction (4 ft in general industry).

  • Excavations 5 ft or deeper require a protective system; excavations 20 ft or deeper require design by a registered professional engineer.

  • A competent person must inspect excavations, scaffolds, and fall-protection systems daily and after rain or any hazard-changing event.

  • Spoil and equipment are kept at least 2 ft back from the excavation edge; a ladder must be within 25 ft of lateral travel for egress.

  • Report to OSHA: a fatality within 8 hours; an in-patient hospitalization, amputation, or loss of an eye within 24 hours.

  • Recordable injuries must be entered on the OSHA 300 log within 7 days of learning of them.

  • Tennessee requires workers' compensation coverage for employers with 5 or more employees, and the state is a right-to-work state.

  • Hazard Communication: a safety data sheet must be available for every hazardous chemical on site, and employees must be trained.

Quick reference

Estimating, Bidding, and Project Scheduling

  • Bid price = direct costs + project indirect costs + company overhead + contingency + profit.

  • Bid bond is typically 5–10% of the bid; performance and payment bonds are typically 100% of the contract amount.

  • Every addendum must be acknowledged in the bid and becomes part of the contract documents.

  • Total float = late start − early start, which equals late finish − early finish.

  • The critical path is the longest-duration path through the network; it has zero total float and sets project duration.

  • Crashing shortens duration by adding resources to critical-path activities; fast-tracking overlaps activities or phases.

  • Quantity takeoff measures net quantities from the drawings, then adds a waste factor by material type (commonly 5–10%).

  • Unit-price estimating = quantity × unit cost of labor, material, and equipment, plus markup.

Quick reference

Site Work, Excavation, and Foundations

  • Structural fill is typically compacted to 95% of maximum dry density per the Standard Proctor test (ASTM D698).

  • Bank volume is converted to loose volume with the soil swell factor; loose to compacted uses the shrinkage factor.

  • Footings must bear on undisturbed soil below the frost line and, where possible, above the water table.

  • OSHA excavation slopes: Type A 3/4:1, Type B 1:1, Type C 1.5:1; steeper cuts require shoring or shields.

  • Dewatering options include sumps and ditches, wellpoints, and deep wells; discharge may require a permit.

  • Silt fence and other erosion controls are installed before grading, with a stabilized construction entrance at the site access.

  • Balancing cut and fill minimizes haul cost; compare net earthwork volumes before finalizing grades.

Quick reference

Concrete, Masonry, and Structural Steel

  • The slump test (ASTM C143) measures consistency; specified slump tolerances are typically ±1 to ±2 in.

  • Concrete reaches design strength at 28 days; 7-day strength is roughly 75% of the 28-day strength.

  • A lower water-cement ratio increases strength and durability but reduces workability; admixtures are used to compensate.

  • Air entrainment of roughly 4–8% provides resistance to freeze-thaw damage.

  • Moist curing for a minimum of 7 days is typical for Type I cement concrete.

  • Mortar types in descending compressive strength are M, S, N, and O; Type S is common for structural and below-grade masonry.

  • Masonry walls require flashing and weep holes at the base of the cavity to drain water to the exterior.

  • High-strength structural bolts are A325 and A490; welding follows AWS D1.1 with qualified procedures and inspection.

Quick reference

Carpentry, Roofing, and Building Envelope

  • Asphalt shingles require a minimum slope of 2:12 with double underlayment; 4:12 and steeper is the standard application.

  • Ice-dam membrane is required at eaves where ice damming occurs, extending at least 24 in. inside the warm wall line.

  • Weather-resistive barriers and flashing are installed shingle-fashion so upper courses overlap lower courses.

  • Roof sheathing panel edges must be supported; 7/16-in. OSB is limited to 24 in. on center for roof decks.

  • The vapor retarder goes on the warm (interior) side of the insulation in cold climates; air sealing precedes insulating.

  • Framing notches and bored holes are limited by code: notches are restricted on the tension side and holes must be centered.

  • Attic ventilation is commonly 1/150 of the vented ceiling area, reduced to 1/300 where a vapor retarder is installed.

Quick reference

Project Management, Quality Control, and Project Closeout

  • Three-phase quality control uses preparatory, initial, and follow-up inspections for each definable feature of work.

  • RFIs document design questions; submittals verify materials and equipment before installation.

  • Substantial completion means the work is usable for its intended purpose, and the punch list is issued at that point.

  • Final payment follows punch-list completion, final lien waivers, and delivery of closeout documents.

  • Closeout package: as-built drawings, O&M manuals, warranties, test reports, spare parts, and attic stock.

  • The schedule of values allocates the contract price to work items and drives the amount of each progress payment.

  • Retainage is released per the contract, with final payment conditioned on a final waiver and contractor's affidavit.