TN General Contractor study materials
TN General Contractor study resources

TN General Contractor flashcards

TN General Contractor · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Current ratio
Current assets divided by current liabilities. It measures whether short-term assets can cover short-term obligations, and a value below 1.0 signals possible liquidity problems.
Working capital
Current assets minus current liabilities. Positive working capital indicates the firm can fund day-to-day operations; negative working capital means it relies on credit to operate.
Markup versus margin
Markup is a percentage added to cost, while margin is a percentage of the selling price. Selling price equals cost divided by one minus the target margin.
Percentage of completion method
An accounting method that recognizes revenue and gross profit in proportion to costs incurred to date divided by total estimated costs, used for long-term construction contracts.
Constructive change
Work the owner directs orally or implies through conduct that falls outside contract scope but is never formalized in a change order; it may still be compensable.
Pay-if-paid clause
Contract language making the owner's payment to the prime contractor a condition precedent to paying the subcontractor, shifting the risk of owner nonpayment to the subcontractor.
Substantial completion
The stage at which work is sufficiently complete for its intended use, triggering warranty start, occupancy rights, retainage release rights, and claim limitation periods.
Differing site conditions
Subsurface or latent physical conditions materially different from the contract documents, or unknown physical conditions of an unusual nature, entitling the contractor to an adjustment.
Qualifying agent
The individual who passes the licensing examinations and is designated to qualify a contracting entity before the Tennessee Board; the license depends on maintaining that qualifier.
Tennessee licensing threshold
A Tennessee contractor license is required for projects of $25,000 or more in total cost, while projects from $3,000 to $24,999 require a home improvement license.
Monetary limit
The maximum single-project dollar value a licensed contractor is authorized to perform; bidding or contracting above that limit violates Board rules and can bring penalties.
Mechanic's lien
A statutory claim recorded against real property by a party that furnished labor or materials, giving that party a security interest in the improved property until it is paid.
Miller Act payment bond
Federal law requiring payment and performance bonds on federal construction contracts over $150,000, protecting subcontractors and suppliers who cannot lien government property.
Conditional versus unconditional waiver
A conditional lien waiver becomes effective only when the stated payment actually clears; an unconditional waiver is effective on signing regardless of whether payment is received.
Notice to surety
Under the Miller Act a claimant must give written notice to the surety within 90 days after last furnishing labor or materials, then file suit within one year.
Competent person
An OSHA-defined individual who can identify existing and predictable hazards and is authorized to take prompt corrective action; required for excavation, scaffold, and fall-protection inspections.
Fall protection trigger height
OSHA construction standards require fall protection at 6 feet or more above a lower level, and for employees working in excavations 6 feet deep or more.
Excavation protective system
Trenches 5 feet deep or more require sloping, shoring, shielding, or benching; excavations 20 feet or deeper require a protective system designed by a registered professional engineer.
Total float
The time an activity can be delayed without delaying project completion; calculated as late start minus early start, or late finish minus early finish.
Critical path
The longest-duration chain of dependent activities through a schedule network. It has zero total float and determines the shortest possible project duration.
Bid bond
A bond submitted with a bid, typically 5 to 10 percent of the bid amount, guaranteeing the bidder will sign the contract and furnish required bonds if awarded the work.
Addendum
A written modification to bidding documents issued before bid opening. Bidders must acknowledge each addendum in their bid, and it becomes part of the contract.
Standard Proctor test
A laboratory test finding the maximum dry density and optimum moisture content of soil; field compaction is normally specified as a percentage of that maximum density.
Soil swell factor
The percentage volume increase when soil is excavated and loosened; used to convert bank cubic yards into loose cubic yards for hauling and truck counts.
Frost line footing depth
The depth to which groundwater freezes in winter. Footings must bear below this depth to prevent frost heave, and local codes set the required depth.
Slump test
ASTM C143 field test measuring concrete consistency by the settlement of a standard cone sample; a higher slump indicates a wetter, more workable mix.
Water-cement ratio
The weight of water divided by the weight of cementitious material in a mix. Lower ratios raise strength and durability but reduce workability.
Type S mortar
A cement-lime mortar with high bond strength and moderate compressive strength, commonly specified for masonry below grade and for structural unreinforced walls.
Ice dam membrane
A self-adhering waterproof underlayment installed at eaves and valleys under roofing to stop water backup from ice dams; required by code where ice damming occurs.
Minimum shingle slope
Asphalt shingles generally require a roof slope of at least 2:12 with double underlayment; slopes below that require a different roofing system.
Vapor retarder location
In cold climates the vapor retarder is placed on the warm interior side of the insulation; installing it on the cold side can trap moisture within the assembly.
Punch list
A list of incomplete or defective items compiled near the end of a project; the items must be corrected before final payment and release of retainage.