Quick reference

Business and Project Management

  • Critical path = the longest-duration chain of dependent activities; its length sets the minimum project duration.

  • Total float = LS − ES = LF − EF; free float = ES of the successor − EF of the activity.

  • Earned value: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC ≈ BAC ÷ CPI.

  • Utah requires a contractor license from DOPL for construction projects totaling $3,000 or more in labor and materials.

  • Utah contractor classifications include General Engineering, General Building, Residential/Small Commercial, and Specialty.

  • Crashing reduces duration by adding resources and cost; fast-tracking overlaps activities and adds coordination risk.

  • Labor burden (payroll taxes, workers' comp, insurance, benefits) commonly runs 25–40% of base wage; apply it before markup.

  • Margin on price versus markup on cost: margin = markup ÷ (1 + markup); a 10% markup is only about 9.1% margin.

Quick reference

Contract Administration and Law

  • Contract types: lump sum (fixed price), unit price (paid per measured unit), cost-plus with or without a guaranteed maximum price, and time and materials.

  • Notice provisions are usually enforced strictly - a claim can be waived if written notice is not delivered within the stated period.

  • Utah mechanics lien: record a Notice of Lien within 90 days after last furnishing labor, materials, or equipment.

  • Utah lien enforcement: suit must be filed within 180 days after the Notice of Lien is recorded, or the lien expires.

  • Utah subcontractors and suppliers generally give preliminary notice within 20 days after first furnishing to preserve lien rights.

  • Substantial completion starts the warranty period, allows retainage release, and begins the clock on defect claim periods.

  • Pay-if-paid makes owner payment a condition precedent to the subcontractor being paid; pay-when-paid is only a timing mechanism.

  • Differing site conditions: Type I differs materially from the contract documents; Type II is unusual and unknown despite a reasonable site investigation.

Quick reference

Estimating and Bidding

  • Crew cost = sum of wages × (1 + labor burden) + equipment + small tools + applicable taxes.

  • Unit conversion: CY = (length × width × depth in feet) ÷ 27; SF = length × width; add a 5–10% waste factor for most materials.

  • Bid bond on Utah public work is typically 5% of the bid; performance and payment bonds are typically 100% of the contract price.

  • When a unit price conflicts with the extension, the unit price governs and the extension is corrected.

  • Bidders must acknowledge every addendum; failure to acknowledge can render the bid nonresponsive.

  • Typical ranges: overhead 5–15% of direct cost, profit 5–10%, contingency 5–10% of the base estimate.

  • Unbalanced bidding front-loads early work items to improve cash flow; materially unbalanced bids may be rejected.

  • Only a contractor holding a valid Utah license may bid or contract for public work; status is checked as of bid opening.

  • Estimate review: compare cost per square foot and per unit against historical data before finalizing the bid.

Quick reference

Construction Safety and Site Supervision

  • Fall protection is required at 6 feet in general construction; guardrails run 38–45 inches with midrail and toeboard.

  • Excavations 5 feet or deeper require a protective system (slope, shore, or shield) unless a competent person documents no hazard.

  • Spoil piles and equipment must be kept at least 2 feet back from the edge of an excavation.

  • Trenches 4 feet or deeper need a ladder, stair, or ramp within 25 feet of lateral travel for workers.

  • Crane clearance from power lines: 10 feet minimum up to 50 kV, plus 0.4 inch per kV above 50 kV.

  • Report to OSHA a fatality within 8 hours; an in-patient hospitalization, amputation, or loss of an eye within 24 hours.

  • Record a recordable injury on the OSHA 300 log within 7 calendar days; post the annual summary February 1 through April 30.

  • Hazard Communication requires an SDS for each hazardous chemical, labeled containers, and trained exposed employees.

  • Utah has no state OSHA plan; federal OSHA enforces the construction standards in 29 CFR 1926.