UT General Contractor study materials
UT General Contractor study resources

UT General Contractor key terms

UT General Contractor · Get comfortable with the vocabulary.

Critical Path Method (CPM)

A scheduling technique that identifies the longest sequence of dependent tasks in a project, showing which activities cannot be delayed without extending the overall completion date.

Related: Earned Value Management, Substantial Completion
Schedule of Values

A project accounting document that breaks the contract price into work items with assigned values, used to review and approve progress payments based on completed work.

Related: Retainage, Substantial Completion
Substantial Completion

The stage when the work is sufficiently complete for the owner to use it for its intended purpose, with only minor items or corrections remaining.

Related: Punch List, Retainage
Punch List

A written list of minor defects, incomplete items, or corrections identified during a final walkthrough that the contractor must fix before final acceptance.

Related: Substantial Completion
Retainage

A percentage of each progress payment withheld by the owner until the project reaches substantial or final completion, providing security for unfinished or defective work.

Related: Schedule of Values, Lien Waiver
Contingency

A reserved amount of money or time set aside in a budget or schedule to cover unforeseen costs, risks, or delays during construction.

Related: Change Order, Allowance
Cash Flow Projection

A forecast of when money will come into and leave the business over a period, helping a contractor plan for payroll, materials, and other expenses.

Related: Retainage, Schedule of Values
Earned Value Management

A method that compares the value of work actually completed against the planned cost and schedule to measure project performance and forecast future results.

Related: Critical Path Method (CPM), Schedule of Values
Request for Information (RFI)

A formal written question from the contractor to the design team asking for clarification of drawings, specifications, or other contract documents.

Related: Change Order, Constructive Change
Scope Creep

Uncontrolled expansion of project work beyond the original contract scope, often without corresponding adjustments to price, schedule, or formal approval.

Related: Change Order, Constructive Change
Mechanic's Lien

A legal claim filed against a property by a contractor, subcontractor, or supplier who has not been paid for labor, materials, or services provided to improve it.

Related: Lien Waiver, Retainage
Lien Waiver

A written document in which a person gives up the right to file a mechanic's lien, often exchanged for a progress or final payment.

Related: Mechanic's Lien, Retainage
Change Order

A written modification to the contract, signed by authorized parties, that changes the scope, price, or schedule of the work.

Related: Constructive Change, Scope Creep
Performance Bond

A surety bond guaranteeing that the contractor will complete the contract work according to its terms; the surety may step in if the contractor defaults.

Related: Payment Bond, Bid Security
Payment Bond

A surety bond that protects subcontractors and suppliers by guaranteeing they will be paid for labor and materials furnished on the bonded project.

Related: Performance Bond, Mechanic's Lien
Indemnity Clause

A contract provision where one party agrees to hold the other harmless from certain claims, losses, or damages, often arising from the indemnifying party's actions.

Related: Flow-Down Clause
Notice to Proceed

A written directive from the owner authorizing the contractor to begin work on a specified date, starting the contract time.

Statute of Repose

A law that sets an absolute deadline for filing lawsuits over construction defects, regardless of when the defect is discovered.

Related: Mechanic's Lien
Constructive Change

An unintended change to the work caused by the owner's or designer's actions or instructions, which may entitle the contractor to an equitable adjustment.

Related: Change Order, Request for Information (RFI)
Flow-Down Clause

A contract provision that passes certain rights and obligations from the prime contract down to subcontractors, so they are bound by similar terms.

Related: Indemnity Clause
Quantity Takeoff

The process of measuring and listing the materials, labor, and equipment needed for each part of the project from the drawings and specifications.

Related: Unit Price, Allowance
Unit Price

A set cost per unit of measurement, such as per cubic yard or per square foot, used to price work that is difficult to quantify exactly in advance.

Related: Quantity Takeoff, Allowance
Addendum

A written change to the bid documents issued before bids are due, such as a correction, clarification, or additional information that becomes part of the contract.

Related: Alternates, Bid Security
Alternates

Specific items in a bid package that offer optional prices for substituting materials, methods, or scope, allowing the owner to choose among them.

Related: Addendum, Allowance
Bid Security

A deposit, bond, or cashier's check submitted with a bid to guarantee the bidder will enter the contract if selected and will provide required bonds.

Related: Performance Bond, Payment Bond
Bid Shopping

The practice of a contractor revealing one bidder's price to others to obtain a lower price after bids have been submitted, generally considered unethical.

Related: Bid Security
Allowance

A specified amount included in the contract for a particular item whose exact cost is unknown at bid time, later adjusted to the actual cost.

Related: Unit Price, Contingency
Lump-Sum Contract

An agreement where the contractor agrees to perform a defined scope of work for a fixed total price, bearing the risk of cost overruns.

Related: Change Order, Contingency
Competent Person

An individual who is capable of identifying existing and predictable hazards and has authority to take prompt corrective measures to eliminate them.

Related: Fall Protection, Excavation Protective System
Fall Protection

A system of guards, nets, harnesses, or other equipment used to prevent workers from falling from heights or to stop a fall safely.

Related: Competent Person
Excavation Protective System

A method such as sloping, shoring, or shielding used to protect workers from cave-ins and other hazards in trenches and excavations.

Related: Competent Person, Confined Space
Hazard Communication

An OSHA program requiring employers to identify chemical hazards, label containers, provide safety data sheets, and train workers about safe handling.

Related: Toolbox Talk
Confined Space

A space with limited entry and exit that is not designed for continuous occupancy and may contain hazardous atmospheres or other serious safety hazards.

Related: Lockout/Tagout, Excavation Protective System
Lockout/Tagout

A safety procedure that isolates energy sources and locks or tags them out to prevent accidental startup or release of energy during maintenance or repair.

Related: Confined Space
Toolbox Talk

A short, informal safety meeting held at the job site before work begins to discuss a specific hazard, procedure, or lesson learned.

Related: Competent Person, Hazard Communication
Experience Modification Rate (EMR)

A number used by workers' compensation insurers to compare a contractor's injury history to industry averages, affecting insurance premiums and prequalification.

Related: Toolbox Talk