Armenia Engineer Attestation study materials
Armenia Engineer Attestation study resources

Armenia Engineer Attestation cheat sheet

Armenia Engineer Attestation · Keep the key ideas within reach.

Quick reference

Urban development and construction legislation

  • Legal hierarchy: Constitution → RA laws (including the Urban Development Law) → government decrees → ministerial orders → construction norms (SNiP / RA SN); a lower act contradicting a higher one has no force.

  • The Urban Development Law governs territorial planning, zoning, design, permitting, construction and state supervision; separate laws cover land use, environmental impact and licensing.

  • Project participants: investor/developer, designer, contractor, technical supervisor (client's representative), author's supervisor and the state or local self-government control body.

  • Design is produced in stages: pre-design feasibility, preliminary design (նախագիծ) and working documentation; the required depth of each stage depends on object complexity.

  • Construction is lawful only on a cadastral plot whose designated use matches the object; urban planning conditions fix permitted density, height and setbacks.

  • Urban planning documentation hierarchy: territorial plan → general (master) plan of the settlement → zoning plan → detailed plot plan.

  • Objects are classified by function, complexity and risk; the class determines whether state expert review, a building permit and intensified supervision are required.

  • Unauthorised (self-built) objects are legalised through an administrative or court procedure once compliance with planning, fire and seismic requirements is proven.

Quick reference

Permitting and licensing

  • A building permit (շինարարության թույլտվություն) is obtained before any excavation or construction; it is issued by the authorised urban development body or the local self-government.

  • Permit application package: title documents for the plot, urban planning conditions, design documentation with the state expert conclusion, and proof of fee payment.

  • Grounds for refusal: incomplete documents, mismatch with the permitted use or zoning, or a negative state expert conclusion.

  • A permit has a limited validity period; works must start within it, and any material design change (footprint, height, structural scheme) requires re-issue.

  • Operation of a completed object is allowed only after the acceptance commission issues a commissioning certificate confirming conformity with the approved design.

  • Design, engineering survey and construction-installation activity are licensable; the licence is granted by the authorised ministry on evidence of qualified staff, equipment and quality control.

  • Licensed entities appear in a public register; suspension or revocation follows repeated violation of norms or of licence conditions.

  • Permits, licences and commissioning certificates are state services with statutory processing deadlines and published fee tariffs.

Quick reference

Technical regulation

  • The Law on Technical Regulation separates mandatory technical regulations (safety, health, environment) from voluntary standards.

  • A technical regulation is adopted by law or government decree and may reference standards; once a standard is cited, its referenced clauses become binding.

  • National standards carry the designation AST and are administered by SARM, the national body for standards, metrology and conformity assessment.

  • Conformity is demonstrated by declaration (self-assessment with test evidence) or by certification through an accredited body, depending on the risk level.

  • Armenia has been an EAEU member since 2015, so EAEU technical regulations (TR CU / TR EAEU) prevail for products in their scope, with mutual recognition of test reports.

  • Accreditation of laboratories and certification bodies is a function separate from standardisation; only accredited test reports are accepted for mandatory conformity assessment.

  • Measuring instruments used in construction control undergo periodic verification, giving traceability to national measurement standards.

  • Design, test and acceptance documentation submitted to authorities must be in Armenian or accompanied by a certified translation.

Quick reference

Construction norms and standards

  • Design uses the limit-state method: ultimate states (strength, stability, fatigue) and serviceability states (deflection, cracking, vibration) are checked separately.

  • Design load = characteristic load × partial factor γf: dead load 1.05–1.1, imposed floor load 1.2, wind 1.4, snow 1.4 in the fundamental combination.

  • Where several variable actions act together, combination factors ψ reduce the accompanying ones; snow is commonly taken with ψ = 0.5 in lowland zones.

  • Modular coordination uses the basic module M = 100 mm and the enlarged module 3M = 300 mm for planning grids and component sizes.

  • Typical deflection limits: floor slabs span/250, roof elements span/200, cantilevers span/150, evaluated under the characteristic combination.

  • Fire resistance is expressed as REI ratings (15–120 min); the required rating fixes minimum section size, concrete cover and protection thickness.

  • Snow and wind loads are taken from the RA climatic zoning maps; mountain regions carry substantially higher snow loads than the Ararat valley.

  • Norm documents separate mandatory (safety) provisions from recommended (good practice) provisions; only the mandatory parts are enforced by supervision.

Quick reference

Seismic engineering and structural safety

  • Armenia lies in the Alpine–Himalayan seismic belt; design intensity comes from RA seismic zoning maps in MSK-64 scale points (7, 8 or 9), adjusted for soil category.

  • Equivalent static base shear: V = K1·K2·S·W, distributed over the height in proportion to storey weight W_i multiplied by height h_i.

  • Regularity is required: symmetric plan layout, shear walls distributed on the perimeter, no soft or weak storey, torsional eccentricity within code limits.

  • Seismic joints divide the building into regular blocks; width is at least the sum of adjacent computed lateral displacements plus a margin, and no rigid element may bridge the joint.

  • Ductile detailing: confinement spacing in plastic-hinge zones ≤ min(8·db, 100 mm); strong-column/weak-beam capacity check; staggered lap splices.

  • Behaviour factor q reduces the elastic spectrum: about 4–5 for ductile RC frames, 3–4 for wall systems, 2–3 for infilled frames, 1.5–2 for masonry.

  • Masonry buildings in high-seismicity zones require reinforced seismic belts at floor and roof levels, reinforced lintels and storey-height limits.

  • Foundations are tied by continuous strip beams or a raft; piles are checked for kinematic effects and for differential displacement between blocks.

Quick reference

Structural design and analysis (concrete, steel, masonry, foundations)

  • Design strengths: fcd = αcc·fck/γc with γc = 1.5; fyd = fyk/γs with γs = 1.15.

  • Beam longitudinal steel: ρ ≥ max(0.26·fctm/fyk, 0.0013) and ρ ≤ 0.04 at lap zones; shear reinforcement by the truss or strut-and-tie model.

  • Column reinforcement 0.10·NEd/fyd ≤ As ≤ 0.04·Ac, at least four bars, minimum diameter 12 mm, link spacing ≤ min(12·db, least section dimension).

  • Steelwork partial factors: γM0 = 1.0 for cross-section resistance, γM1 = 1.0 for member stability, γM2 = 1.25 for net sections and connections.

  • Footing bearing capacity: qu = c′Nc + q′Nq + 0.5γ′BNγ with Nq = e^(π·tanφ′)·tan²(45° + φ′/2); designed with partial factors or a global factor near 3.

  • Settlement acceptance: total settlement typically limited to 25–50 mm, differential tilt to about 1/500 between adjacent columns.

  • Masonry walls are checked for slenderness λ = h/t (limits around 12–15 for load-bearing walls) and for load eccentricity.

  • Rule-of-thumb slab depth: h ≈ L/25–30 for simply supported one-way slabs, L/30–35 for continuous slabs; flat slabs require punching shear checks at columns.

Quick reference

Construction technology, materials and quality control

  • Concrete class (e.g. C20/25) denotes characteristic cylinder strength 20 MPa and cube strength 25 MPa at 28 days; 150 mm cubes are the standard specimens.

  • Acceptance sampling: one set of at least three cubes per 50–100 m³ placed, plus a set for each element cast from a separate mix.

  • Workability is checked by the slump test; the measured slump must stay within the specified target ± 30 mm, otherwise the batch is rejected.

  • Durability: w/c ≤ 0.50 and cement content ≥ 280 kg/m³ for normally exposed reinforced concrete; cover fixed by exposure class and fire rating.

  • Curing lasts at least 7 days (3 days for rapid-hardening cement) with surfaces kept moist; cold-weather concreting requires protection until 50% design strength.

  • Formwork and props are removed at 70% of design strength for slabs and beams of span ≤ 6 m, and 85–100% for longer spans and cantilevers.

  • Backfill is placed in layers ≤ 300 mm and compacted to a coefficient of at least 0.95 (0.98 under roads and floors), confirmed by field density tests.

  • Reinforcement is tested per batch (up to 60 t) for yield strength, tensile strength and elongation; welded joints need separate tensile and bend tests.

Quick reference

Building engineering systems (water, sewerage, HVAC, electrical, gas supply)

  • Water supply: minimum pressure at the most unfavourable fixture is about 0.05–0.1 MPa; design velocities 0.6–1.5 m/s in service pipes limit noise and head loss.

  • Gravity sewers: minimum slopes about 0.02 for DN100 and 0.008 for DN150, maximum filling ratio 0.6–0.8, self-cleansing velocity not below 0.7 m/s.

  • Every drainage stack serving several fixtures is ventilated above the roof to protect trap seals; a separate vent stack is required where the stack serves many fixtures.

  • Ventilation: dwellings need 20–30 m³/h of outdoor air per person; bathrooms and kitchens have local exhaust (about 25–60 m³/h per fixture) discharging to the roof.

  • Electrical installations use TN-S earthing with main equipotential bonding; 30 mA residual current devices protect socket circuits and wet rooms.

  • Earth resistance at the main earthing terminal is typically required to be ≤ 4 Ω, or ≤ 10 Ω where only protective earthing of the supply is provided.

  • Internal gas pipes are laid in ventilated shafts, never in lift shafts or electrical ducts; rooms with gas appliances need permanent ventilation openings.

  • Gas pipelines are strength-tested at 1.5× working pressure and tightness-tested at working pressure before service, with signed records.

Quick reference

Cost estimation and normative pricing in construction

  • Estimated cost structure: direct costs (materials, labour, machine time) + overhead + estimated profit + value added tax, which in Armenia is 20%.

  • Unit price = Σ(resource quantity × current price) + overhead percentage + profit percentage; resource quantities come from element-level norms per unit of work.

  • Estimating methods: resource method (current prices), resource-index method, base-index method and analogy with a completed object.

  • Contract price types: fixed lump sum, adjustable with indexation, and unit-rate measured contracts; the choice allocates inflation risk between client and contractor.

  • A contingency reserve of 3–10% of base cost is included in the summary estimate and increased for technically complex or seismically demanding objects.

  • Winter and high-altitude coefficients are applied to labour and machine costs where work is executed under those conditions.

  • Estimate documentation set: bill of quantities, unit-price estimates, object estimate, summary estimate and consolidated cost statement.

  • Completed work is certified monthly against quantities measured on site; the certified amount feeds the cost report and earned-value analysis.

Quick reference

Technical supervision, project management and occupational safety

  • Three distinct control roles: state construction supervision (legality and safety), technical supervision by the client (quality, quantity, schedule) and author's supervision by the designer (conformity with design).

  • Concealed work - reinforcement, embedded pipes, waterproofing, subgrade - is inspected and recorded in a hidden works act before covering; otherwise it must be opened up.

  • Executive documentation at completion: as-built drawings, test reports, concrete and weld certificates, general and special works journals, hidden works acts.

  • Work at height begins at 1.8 m; guardrails 1.1 m high with a mid-rail and toe board, or personal fall-arrest systems, are then mandatory.

  • Trenches deeper than 1.5 m in unsupported soil require shoring or safe slopes, with ladders placed so no worker travels more than about 10 m to an exit.

  • Crane work requires a certified operator and signalman, a defined hazardous zone, tested lifting gear, and no passage of loads over people or live areas.

  • Site electrical safety: temporary earthing, residual current devices on distribution boards, and 42 V or 12 V supply for portable lamps in wet or confined spaces.

  • Progress control uses critical-path scheduling and earned value: CPI = EV/AC and SPI = EV/PV; values below 1.0 indicate cost overrun or delay.