This page supports independent preparation for the Armenian engineer attestation used in urban development and construction. The credential is intended for engineers and construction specialists who need to demonstrate that they can apply Armenian construction legislation, technical norms, seismic-safety principles, structural design methods, construction technology, building services, normative pricing, and supervision and safety duties in practice. It is not a substitute for any licence or registration requirement, and this platform is not affiliated with the Armenian authority that administers the attestation. The exam is broad rather than narrowly specialised. The Armenia Engineer Attestation case studies are 5 cases and about 2,316 words.

1

Expired permit, added floor and pre-sold flats in Yerevan

A developer in Yerevan holds a construction permit for a six-storey residential building with one underground parking level on a 0.18 ha lot. The permit was issued in March 2021 for three years.

490 words, about 2 min
2

Soft-storey risk after shop conversion in a Gyumri panel building

A 1983 nine-storey precast concrete panel apartment building in Gyumri contains 108 flats. The ground floor originally held storage rooms and a small lobby.

443 words, about 2 min
3

Mat settlement on expansive clay after a water leak in Vanadzor

A five-storey reinforced-concrete frame building in Vanadzor sits on a 1.2 m thick mat foundation at 2.5 m depth. The soil is a clay with plasticity index 35 and seasonal moisture variation.

420 words, about 2 min
4

Flue blockage and CO incident in a 16-storey gas-supplied apartment

A 16-storey apartment building in Yerevan receives natural gas at a measured pressure of 18 mbar at the riser, while the appliance rating plate requires 20 mbar. Several flats use instantaneous gas water heaters connected to individual flues.

431 words, about 2 min
5

Cover shortfall and price escalation on a school seismic retrofit

A school seismic retrofit in Sevan is under a unit-price contract of 480 million AMD with an 8% contingency. The contractor is nine weeks behind schedule.

532 words, about 3 min