First 50 of 200 questions. Each one lists the choices, the correct answer, and an explanation. The checker at the top of this page saves progress in this browser when it is available.
Continue in the practice tool above to load more questions, 50 at a time.
Question 1Resource Management
A firm's project schedule shows that a design task can begin only after a permit is issued. In a network diagram, this dependency is best described as which type of relationship?
- Start-to-finish
- Finish-to-start Correct answer.
- Start-to-start
- Finish-to-finish
Explanation
A finish-to-start relationship means the predecessor activity must finish before the successor can begin, which matches a permit issuance gating design work. The other relationship types link starts or finishes without requiring the predecessor to be fully complete before the successor starts.
Question 2Resource Management
Which document establishes the total authorized budget against which project cost performance is measured?
- The resource calendar
- The work breakdown structure
- The cost baseline Correct answer.
- The chart of accounts
Explanation
The cost baseline is the time-phased, approved project budget used to measure and monitor cost performance. The WBS organizes scope, the chart of accounts codes costs, and the resource calendar shows availability, none of which is the authorized budget baseline.
Question 3Resource Management
A project manager is estimating how many hours a code review will take by comparing it to similar reviews completed on prior projects. Which estimating technique is being used?
- Three-point estimating
- Parametric estimating
- Bottom-up estimating
- Analogous estimating Correct answer.
Explanation
Analogous estimating uses historical data from comparable activities to estimate duration or cost. It is less accurate than detailed methods but useful when limited information is available.
Question 4Resource Management
A project manager wants a single summary measure of schedule efficiency that compares earned value to planned value. Which metric should be used?
- Schedule performance index Correct answer.
- Cost performance index
- To-complete performance index
- Schedule variance in dollars
Explanation
The schedule performance index (SPI) equals earned value divided by planned value and expresses schedule efficiency as a ratio. Schedule variance is an absolute dollar measure, and the cost performance index and TCPI address cost, not schedule efficiency.
Question 5Resource Management
A project has an earned value of $80,000, a planned value of $100,000, and an actual cost of $90,000. What is the cost performance index?
- 0.80
- 0.89 Correct answer.
- 1.25
- 1.13
Explanation
The cost performance index equals earned value divided by actual cost, or $80,000 divided by $90,000, which is approximately 0.89. A CPI below 1.0 indicates the project is spending more than planned for the work earned.
Question 6Resource Management
A project manager is building a team and needs to record each member's skills, availability, and cost rate in one place. Which tool is most appropriate?
- Resource calendar
- Staffing management plan Correct answer.
- Responsibility assignment matrix
- Resource histogram
Explanation
The staffing management plan documents how and when project staff will be acquired, their attributes, and related resource policies, making it the appropriate place for consolidated staffing information. A RAM assigns roles, a histogram shows resource usage over time, and a calendar shows availability windows.
Question 7Resource Management
During execution, a key consultant becomes unavailable and the project manager must obtain a replacement. Which process does this activity fall under?
- Acquire resources Correct answer.
- Manage team
- Develop team
- Control resources
Explanation
Acquire resources is the process of confirming and obtaining the human and physical resources needed to complete project work. Developing and managing the team address capability and performance after resources are on board, and controlling resources monitors physical resource use.
Question 8Resource Management
A project manager needs to formally document that a specific work package is complete so that payment can be released. Which action best supports this?
- Updating the resource histogram
- Verifying the deliverable through control quality Correct answer.
- Rebaselining the cost baseline
- Updating the issue log
Explanation
Formal completion and acceptance of a deliverable is established through quality control verification, which provides documented evidence the work meets requirements. Payment is then tied to that verified acceptance rather than to scheduling or cost updates.
Question 9Resource Management
Which cost estimating approach is most appropriate when detailed scope information is available and a high degree of accuracy is required?
- Reserve analysis
- Bottom-up estimating Correct answer.
- Analogous estimating
- Parametric estimating
Explanation
Bottom-up estimating builds the estimate from detailed work-package or activity-level data, which yields greater accuracy when scope is well defined. Analogous estimating is used with limited detail, parametric uses rate relationships, and reserve analysis sets contingency.
Question 10Resource Management
A project manager wants to reduce the risk of cost overruns by setting aside funds for identified risks with known probabilities and impacts. What is this reserve called?
- Contingency reserve Correct answer.
- Management reserve
- Funding limit reconciliation
- Cost baseline
Explanation
A contingency reserve is allocated for identified risks and is part of the cost baseline. Management reserve covers unknown risks and sits above the baseline, while funding limit reconciliation aligns spending with funding constraints.
Question 11Resource Management
A project manager is analyzing a network diagram and identifies the longest path through it. What does this path determine?
- The minimum project duration Correct answer.
- The cost baseline
- The total float available on each activity
- The resource leveling requirement
Explanation
The critical path is the longest path through the network and therefore determines the shortest possible project duration. Activities on this path have zero or minimal float, and delays there directly extend the project finish.
Question 12Resource Management
An activity has an early start of day 5, a late start of day 9, an early finish of day 12, and a late finish of day 16. What is the total float?
- 4 days Correct answer.
- 7 days
- 3 days
- 11 days
Explanation
Total float equals late start minus early start, or late finish minus early finish, which is 9 minus 5 (or 16 minus 12), equal to 4 days. This is the amount the activity can be delayed without delaying the project finish.
Question 13Resource Management
A project manager is comparing the number of staff needed each month against the number available and wants a visual display of peaks and valleys. Which tool should be used?
- Network diagram
- Responsibility assignment matrix
- Resource histogram Correct answer.
- Cost baseline
Explanation
A resource histogram displays resource usage over time, making peaks and valleys in demand visible. It is commonly used to identify overallocation and to support resource leveling decisions.
Question 14Resource Management
A project manager must compress the schedule by adding resources to critical path activities. What is the primary risk of this approach?
- Elimination of the critical path
- Increased cost and potential quality reduction Correct answer.
- Decreased stakeholder engagement
- Reduced scope
Explanation
Crashing adds resources to shorten duration, which typically increases cost and can introduce quality or coordination risks. It does not change scope or remove the critical path.
Question 15Resource Management
A project manager is reviewing a cost estimate and notices that a 15% factor was applied to account for uncertainty in labor productivity. This factor is best classified as which type of estimate?
- Budget estimate Correct answer.
- Rough order of magnitude estimate
- Definitive estimate
- Parametric estimate
Explanation
A budget estimate is prepared with a moderate level of detail and typically includes contingency factors for uncertainty, often with an accuracy range of about -10% to +25%. Definitive estimates are more precise, and rough order of magnitude estimates are the least accurate.
Question 16Resource Management
A project manager is assigning roles for a deliverable and wants to ensure only one person is accountable for each task. Which tool best supports this?
- Risk register
- Issue log
- RACI chart Correct answer.
- Resource histogram
Explanation
A RACI chart clarifies who is responsible, accountable, consulted, and informed for each task, helping ensure a single accountable owner per deliverable. The other tools track resources, problems, or risks rather than role clarity.
Question 17Resource Management
A project manager notices that a team member consistently delivers late, affecting the schedule. Which action is most appropriate under the Manage Team process?
- Reassign the work without discussion
- Immediately escalate to the sponsor
- Document the issue and provide feedback and coaching Correct answer.
- Add a contingency reserve
Explanation
Managing the team involves tracking performance, providing feedback, and resolving issues through coaching or corrective action. Immediate escalation or reassignment without discussion bypasses the normal performance management steps.
Question 18Resource Management
A project manager is developing a cost management plan and needs to define how cost variances will be measured and reported. Which element of the plan addresses this?
- Reporting formats
- Units of measure
- Level of accuracy
- Control thresholds Correct answer.
Explanation
Control thresholds define the acceptable variance limits that trigger action, establishing how cost variances are monitored and managed. Reporting formats describe presentation, units of measure define currency and units, and level of accuracy sets estimate precision.
Question 19Resource Management
A project manager is estimating activity durations and wants to account for uncertainty by weighting optimistic, most likely, and pessimistic estimates. Which technique should be used?
- Analogous estimating
- Reserve analysis
- Parametric estimating
- Three-point estimating Correct answer.
Explanation
Three-point estimating uses optimistic, most likely, and pessimistic values to compute an expected duration, often using a weighted average. It explicitly incorporates uncertainty, unlike single-point methods.
Question 20Resource Management
A project manager is reviewing a resource-leveled schedule and notices the project finish date has moved later. What is the most likely cause?
- Scope was reduced
- Activities were crashed
- The critical path was eliminated
- Resources were overallocated and sequencing was adjusted Correct answer.
Explanation
Resource leveling resolves overallocation by adjusting activity start and finish dates, which can extend the critical path and delay the project finish. Crashing would shorten duration, and scope reduction would not typically extend the schedule.
Question 21Resource Management
A project manager wants to forecast the cost performance needed to complete the remaining work within the approved budget. Which metric should be calculated?
- Schedule performance index
- Estimate at completion
- To-complete performance index Correct answer.
- Cost variance
Explanation
The to-complete performance index (TCPI) expresses the cost efficiency required for the remaining work to meet a specified budget target. EAC forecasts total cost, CV measures past variance, and SPI measures schedule efficiency.
Question 22Resource Management
A project manager is negotiating for a specialized subcontractor whose services are in high demand. Which consideration most directly affects the acquisition strategy?
- The project's cost baseline
- The risk register
- The communications management plan
- The subcontractor's availability and market conditions Correct answer.
Explanation
Acquisition strategy depends heavily on resource availability, market conditions, and competition for scarce skills. The cost baseline, risk register, and communications plan inform but do not directly determine how scarce resources are acquired.
Question 23Resource Management
A project manager is calculating the estimate at completion using the assumption that future work will continue at the current cost performance index. Which formula applies?
- EAC = AC + (BAC - EV)
- EAC = BAC / CPI Correct answer.
- EAC = AC + ETC
- EAC = BAC - EV
Explanation
When future work is expected to continue at the current cost efficiency, EAC equals the budget at completion divided by the cost performance index. The formula AC + (BAC - EV) assumes remaining work proceeds at the planned rate.
Question 24Resource Management
A project manager must decide between buying a piece of equipment and leasing it. Which analysis best supports this decision?
- Make-or-buy analysis Correct answer.
- Reserve analysis
- Root cause analysis
- Earned value analysis
Explanation
Make-or-buy analysis evaluates whether to produce a resource internally or acquire it externally, weighing costs and capabilities. It directly supports decisions such as purchasing versus leasing equipment.
Question 25Resource Management
A project manager is evaluating whether to level or smooth resources. Which statement best describes resource smoothing?
- It may extend the project finish date
- It reduces the project scope
- It adjusts activities within their float without changing the critical path Correct answer.
- It eliminates all resource overallocation by delaying the project
Explanation
Resource smoothing adjusts activities within their available float so resource demand is more even, without changing the critical path or finish date. Resource leveling, by contrast, may extend the schedule when float is insufficient.
Question 26Resource Management
A project manager is defining how the project team will acquire, develop, and manage resources. Which document provides the most comprehensive guidance for these activities?
- Resource calendar
- Staffing management plan
- Team charter
- Resource management plan Correct answer.
Explanation
The resource management plan is a component of the project management plan that describes how project resources will be acquired, developed, managed, and controlled. It includes roles, responsibilities, reporting relationships, and resource management processes. The team charter focuses on team values and agreements, while the resource calendar shows availability.
Question 27Resource Management
Which technique is used to determine the number of resources needed for a project by comparing the work to be done with the available resources?
- Resource breakdown structure
- Resource leveling
- Resource histogram Correct answer.
- Resource smoothing
Explanation
A resource histogram is a bar chart that shows the amount of time a resource is scheduled to work over a series of time periods. It helps compare resource demand with availability. Resource leveling and smoothing are techniques to adjust the schedule, while a resource breakdown structure organizes resources hierarchically.
Question 28Resource Management
A project manager is creating a document that defines the project team's values, agreements, and expected behaviors. What is this document called?
- Project charter
- Team charter Correct answer.
- Resource management plan
- RACI chart
Explanation
The team charter is a document that establishes the team values, agreements, and operating guidelines for the team. It helps create a collaborative environment and clarifies expectations. The project charter authorizes the project, while a RACI chart defines roles and responsibilities.
Question 29Resource Management
Which tool is used to display the reporting structure of a project team and the relationships among team members?
- Responsibility assignment matrix (RAM)
- Work breakdown structure (WBS)
- Organizational breakdown structure (OBS) Correct answer.
- Resource breakdown structure (RBS)
Explanation
The organizational breakdown structure (OBS) is a hierarchical representation of the project organization, showing reporting relationships and team structure. The RBS organizes resources by category, and the WBS organizes project scope. A RAM maps tasks to responsible individuals.
Question 30Resource Management
What is the primary purpose of a resource calendar?
- To schedule project meetings
- To track team member vacations
- To identify the availability of resources during the project Correct answer.
- To document resource costs
Explanation
A resource calendar identifies the working days, shifts, and availability of resources, including team members and equipment. It helps the project manager schedule activities based on when resources are available. It does not primarily track costs or schedule meetings.
Question 31Resource Management
Which of the following is an example of a project resource that is typically considered a physical resource rather than a team resource?
- Business analyst
- Project manager
- Materials Correct answer.
- Subject matter expert
Explanation
Physical resources include materials, equipment, facilities, and infrastructure, which are distinct from human resources (team members). The project manager, business analyst, and subject matter expert are all human resources. Physical resources are managed through procurement and logistics.
Question 32Resource Management
What is the primary benefit of using a responsibility assignment matrix (RAM) such as a RACI chart?
- It reduces the number of resources needed.
- It clarifies roles and responsibilities for project activities. Correct answer.
- It estimates activity durations.
- It automatically levels resources.
Explanation
A RAM, such as a RACI chart, maps activities or deliverables to team members and defines their roles (Responsible, Accountable, Consulted, Informed). This clarity helps prevent confusion and duplication of effort. It does not reduce resource needs, level resources, or estimate durations.
Question 33Resource Management
Which of the following best describes the acquire resources process?
- Obtaining team members, facilities, equipment, materials, and other resources necessary to complete project work Correct answer.
- Estimating the number of resources needed for each activity
- Tracking team member performance and providing feedback
- Developing individual and team skills to enhance project performance
Explanation
Acquire Resources is the process of obtaining team members, facilities, equipment, materials, and other resources necessary to complete project work. Developing skills is part of Develop Team, tracking performance is Manage Team, and estimating resource needs is part of Estimate Activity Resources.
Question 34Resource Management
A project manager is planning a project with a tight budget and needs to determine the most cost-effective way to staff a temporary data entry task. Which approach is typically most appropriate?
- Outsource the entire project
- Assign permanent employees who are already on the payroll
- Use overtime for existing staff
- Hire temporary workers from an agency Correct answer.
Explanation
For a short-term, low-skill task like data entry, hiring temporary workers from an agency is often the most cost-effective because it avoids long-term commitments and benefits costs. Assigning permanent employees may divert them from higher-value work, outsourcing the entire project is disproportionate, and overtime can lead to fatigue and higher costs.
Question 35Resource Management
During project execution, a project manager notices that a key team member is consistently working beyond scheduled hours to meet deadlines. What is the most appropriate first step?
- Reassign the team member's tasks to others.
- Report the team member for policy violation.
- Ignore the situation as long as deadlines are met.
- Discuss workload and time management with the team member. Correct answer.
Explanation
The project manager should first investigate the cause of overtime, which may indicate unrealistic deadlines, insufficient resources, or personal work habits. A private discussion can identify solutions such as adjusting workload or providing support. Reassigning tasks or ignoring the issue may not address the root cause.
Question 36Resource Management
A project manager is developing the project team and wants to enhance team performance by building trust and collaboration. Which action is most effective?
- Assign all challenging tasks to the most senior team member.
- Avoid conflicts by not addressing team disagreements.
- Conduct regular team-building activities and recognize individual contributions. Correct answer.
- Increase the frequency of status meetings.
Explanation
Team development activities such as team-building and recognition foster trust and collaboration, improving overall performance. Assigning all challenging tasks to one person can cause resentment, avoiding conflict allows issues to fester, and more status meetings do not necessarily build team cohesion.
Question 37Resource Management
A project manager is managing a virtual team spread across multiple time zones. What is the most important consideration for effective team management?
- Establish clear communication protocols and use collaborative tools. Correct answer.
- Schedule all meetings during the project manager's working hours.
- Limit communication to email only.
- Require team members to work the same hours.
Explanation
Virtual teams require clear communication norms and the use of technology to facilitate collaboration across time zones. Scheduling meetings only in the project manager's hours or requiring synchronous work can be impractical. Limiting communication to email may reduce effectiveness.
Question 38Resource Management
A project manager is evaluating the performance of a team member who is not meeting expectations. Which action is most appropriate according to team management principles?
- Provide constructive feedback and create a development plan. Correct answer.
- Publicly criticize the team member to set an example.
- Reduce the team member's responsibilities without discussion.
- Immediately replace the team member.
Explanation
Effective team management involves addressing performance issues through constructive feedback and support, such as a development plan. Immediate replacement or reducing responsibilities without discussion can be demotivating and may not solve the underlying issue. Public criticism is unprofessional and damages trust.
Question 39Resource Management
A project manager is estimating the resources needed for a project activity. Which factor is most likely to increase the required number of resources?
- A reduced scope
- A compressed schedule Correct answer.
- A lower quality standard
- A relaxed schedule
Explanation
A compressed schedule often requires additional resources to complete the same work in less time. A relaxed schedule, reduced scope, or lower quality standard would typically reduce resource needs. Resource estimation must consider schedule constraints.
Question 40Resource Management
A project manager is creating a resource breakdown structure (RBS). What is the primary purpose of this tool?
- To track resource costs
- To categorize project resources by type and function Correct answer.
- To schedule resource assignments
- To define the project team's reporting hierarchy
Explanation
The resource breakdown structure (RBS) is a hierarchical representation of resources by category and type, such as labor, materials, and equipment. It helps in organizing and understanding resource needs. It does not show reporting hierarchy, schedule assignments, or cost tracking directly.
Question 41Resource Management
A project manager is leading a colocated team and wants to improve communication and collaboration. Which action is most effective?
- Create a team workspace with open communication channels. Correct answer.
- Assign individual cubicles to isolate work.
- Encourage team members to work remotely.
- Limit interactions to formal meetings.
Explanation
Colocated teams benefit from a shared workspace that facilitates informal communication and collaboration. Encouraging remote work, limiting interactions, or isolating team members would reduce the advantages of colocation. A team workspace with open channels fosters teamwork.
Question 42Resource Management
Which of the following is a primary output of the acquire resources process?
- Resource management plan
- Resource assignments Correct answer.
- Team performance assessments
- Change requests
Explanation
The Acquire Resources process results in resource assignments, which document the physical and team resources assigned to project activities. Team performance assessments are outputs of Develop Team, change requests may be outputs of various processes, and the resource management plan is an input.
Question 43Resource Management
A project manager is negotiating for the assignment of a functional employee to the project team. Which factor is most important to address during the negotiation?
- The employee's availability and the project's timeline Correct answer.
- The employee's salary
- The employee's personal career goals
- The functional manager's preference
Explanation
When negotiating for resources, the project manager must ensure that the employee is available for the required period to meet project deadlines. While personal goals, functional manager preferences, and salary may be considerations, availability and timeline alignment are critical to project success.
Question 44Resource Management
A project manager is reviewing the resource management plan and notices that it does not include a recognition and rewards system. Why is this a potential issue?
- Recognition and rewards help motivate the team and reinforce desired behaviors. Correct answer.
- It ensures that team members are paid correctly.
- It eliminates the need for performance reviews.
- It is required by law in most industries.
Explanation
A recognition and rewards system is part of team development and helps motivate team members, reinforce positive behaviors, and improve morale. It is not a legal requirement, does not replace payroll systems, and does not eliminate performance reviews.
Question 45Resource Management
A project manager is leading a team through the forming stage of team development. What behavior is most typical during this stage?
- Team members collaborate seamlessly and resolve conflicts independently.
- Team members are confrontational and challenge authority.
- Team members are focused on achieving high performance.
- Team members are polite and dependent on the leader for guidance. Correct answer.
Explanation
In the forming stage, team members are typically polite, tentative, and dependent on the leader for direction as they get to know each other. Confrontation is more typical of the storming stage, collaboration of the norming stage, and high performance of the performing stage.
Question 46Resource Management
A project manager is using a resource histogram and notices that the demand for a specific skill exceeds the available supply during weeks 5-7. What is the most appropriate action?
- Hire additional staff for weeks 5-7.
- Adjust the schedule to level the demand for that skill. Correct answer.
- Ignore the overallocation as it is temporary.
- Reduce the project scope.
Explanation
Resource leveling or smoothing can adjust the schedule to resolve temporary overallocation. Hiring additional staff may be costly and unnecessary if the demand can be leveled. Ignoring the issue can lead to burnout and delays, and reducing scope may not be feasible.
Question 47Resource Management
A project manager is evaluating the cost of acquiring a resource versus the benefit it brings to the project. Which technique is most appropriate for this analysis?
- Team charter
- Resource histogram
- RACI chart
- Cost-benefit analysis Correct answer.
Explanation
Cost-benefit analysis compares the costs of acquiring a resource with the expected benefits to determine if the investment is worthwhile. A resource histogram shows resource usage over time, a RACI chart clarifies roles, and a team charter defines team values.
Question 48Resource Management
A project manager is managing a team where two members have a disagreement about technical approach. The project manager wants to resolve the conflict collaboratively. Which conflict resolution technique is most appropriate?
- Forcing
- Smoothing
- Problem-solving Correct answer.
- Avoiding
Explanation
Problem-solving (or collaborating) involves addressing the conflict directly and finding a solution that satisfies both parties. Forcing imposes one viewpoint, avoiding ignores the conflict, and smoothing emphasizes agreement over resolution. Problem-solving is generally the most effective for important issues.
Question 49Resource Management
A project manager is assessing team performance and notices that the team is highly cohesive but is exhibiting groupthink. What is the most appropriate action?
- Increase pressure to conform to maintain harmony.
- Encourage dissenting opinions and assign a devil's advocate. Correct answer.
- Ignore the groupthink as it indicates strong teamwork.
- Disband the team and form a new one.
Explanation
Groupthink occurs when a cohesive team suppresses dissent and fails to critically evaluate alternatives. Encouraging dissenting opinions and assigning a devil's advocate can stimulate critical thinking. Increasing pressure or ignoring the issue can lead to poor decisions, and disbanding the team is drastic.
Question 50Resource Management
A project manager is planning to use a virtual team and is concerned about team building. Which strategy is most effective for building trust in a virtual team?
- Hold regular video conferences and encourage informal virtual interactions. Correct answer.
- Rely solely on email for all communications.
- Limit team interactions to formal status meetings.
- Require team members to relocate to a central office.
Explanation
Trust in virtual teams is built through regular, rich communication such as video conferences and informal interactions that help team members connect personally. Email alone is less effective for building relationships, relocating may not be feasible, and limiting interactions to formal meetings reduces opportunities for bonding.