ARE 5.0: PjM study materials
ARE 5.0: PjM study resources

ARE 5.0: PjM study plan

ARE 5.0: PjM · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Resource Management & Project Work Planning

  • Map the PjM exam content outline for Resource Management and Work Planning into a one-page topic checklist

  • Define the project manager's authority over budget, schedule, and staffing versus the architect-of-record's contractual role

  • Draft a work breakdown structure for a hypothetical mid-size project, decomposing scope into billable phases and tasks

  • Identify the staffing roles typically required across each phase of a standard design and construction sequence

Your checkpoint

A one-page topic checklist plus a full work breakdown structure for one sample project, with each task tagged to a phase and responsible role

Week 2

Resource Management

  • Calculate a staffing plan from a work breakdown structure by estimating hours per task and applying a utilization factor

  • Build a project budget covering direct labor, reimbursables, consultants, and a contingency line

  • Compare lump-sum, hourly, and percentage-of-construction-cost fee structures and state when each is appropriate

  • Reconcile a planned staffing curve against a fee to detect an unprofitable staffing profile

Your checkpoint

A spreadsheet staffing plan and fee budget for the sample project, with a charted staffing curve and a written note on profitability

Week 3

Project Work Planning

  • Sequence project phases into a milestone schedule with dependencies and reasonable durations

  • Differentiate the owner's program schedule, the design schedule, and the construction schedule and explain how they interlock

  • Identify which tasks sit on the critical path and describe the consequence of a slip in each

  • Select appropriate schedule formats (Gantt, milestone chart, critical path) for different audiences

Your checkpoint

A milestone schedule for the sample project annotated with critical-path tasks and a short justification of chosen durations

Week 4

Resource Management & Project Work Planning

  • Integrate the staffing plan, budget, and schedule into a single coherent project plan

  • Write the scope-of-services and deliverable definitions for owner and consultant agreements

  • Identify the information the project manager must collect before committing to a schedule and fee

  • Diagnose at least three common causes of scope creep and describe a control for each

Your checkpoint

A consolidated project plan document combining scope, schedule, staffing, and budget, plus a one-page scope-creep control checklist

Week 5

Project Team Management

  • Define roles, responsibilities, and decision authority for each team member on the sample project

  • Draft a team communication plan specifying meeting cadence, channels, and documentation standards

  • Describe methods for giving constructive performance feedback and addressing underperformance

  • Explain how to onboard a new team member mid-project without disrupting schedule

Your checkpoint

A responsibility matrix (roles by tasks) plus a written communication plan for the sample project

Week 6

Project Team Management & Project Risk Management

  • Build a risk register for the sample project identifying at least ten risks across cost, schedule, quality, and staffing

  • Score each risk by likelihood and impact and assign a mitigation or transfer strategy

  • Describe how team composition and delegation practices affect project risk exposure

  • Explain conflict-resolution approaches and when escalation to the owner is warranted

Your checkpoint

A risk register with at least ten scored risks, each with an owner and a response strategy

Week 7

Project Risk Management

  • Distinguish risk avoidance, mitigation, transfer, and acceptance and match each to a sample scenario

  • Describe how professional liability insurance, contracts, and indemnification clauses allocate risk

  • Outline a monitoring process for tracking risk triggers and updating the register through construction

  • Explain the project manager's role in quality control and how QA/QC failures translate into risk

Your checkpoint

A risk-response decision guide mapping at least eight scenarios to a strategy, a contract mechanism, and a monitoring trigger

Week 8

Resource Management & Project Work Planning & Project Team Management & Project Risk Management

  • Synthesize all four domains by walking through one integrated project scenario end to end

  • Self-test on each domain and log weak areas with a targeted review action for each

  • Re-derive the staffing and budget math without notes to confirm retention

  • Write a personal exam-day strategy covering time allocation and question triage

Your checkpoint

A completed integrated practice scenario with a scored self-assessment and a written remediation list for any weak domain

Milestones

Week 2: Can produce a staffing plan and fee budget from a work breakdown structure without reference materials, and explain the profitability check

Week 4: Can present a consolidated project plan linking scope, schedule, staffing, and budget, and defend each assumption

Week 6: Can build and score a risk register from scratch and assign a response strategy to every entry

Week 8: Scores at or above a self-set passing threshold on all four domains in the integrated scenario, with no domain below threshold