ASHRAE HBDP: Commissioning and Operations

ASHRAE HBDP · Work through your exam, one topic at a time.

All guide sections

Commissioning and Operations

Commissioning process

Understand the commissioning (Cx) process: owner's project requirements (OPR), basis of design (BOD), Cx plan, pre-functional checks, functional performance testing (FPT), issues log, and final Cx report. Recognize retro-commissioning (RCx) for existing buildings and ongoing commissioning (OCx) for continuous monitoring. Know roles: Cx authority (CxA), owner, contractor, design team; independence of the CxA matters.

Operations and measurement

Concepts: energy management information systems (EMIS), fault detection and diagnostics (FDD), trend logging, sequence of operations, and M&V per IPMVP options (A–D). Understand baseline adjustment and persistence of savings. Know that most savings in RCx come from controls and scheduling, not equipment replacement.

Traps

  1. Confusing commissioning (new building) with retro-commissioning (existing).
  2. Assuming the CxA is the designer or contractor - independence is key.
  3. Skipping seasonal testing (heating and cooling modes).
  4. Claiming savings without baseline adjustment for weather/occupancy.
  5. Treating OCx as a one-time event rather than continuous monitoring.

Worked example

A building's fan runs 24/7 despite 10-hour occupancy. If a 20 hp fan draws ~15 kW and runs 8,760 h/yr, annual energy ≈ 131,400 kWh. Cutting to 10 h/day, 5 days/week (~2,600 h) reduces to ~39,000 kWh - a ~70% fan-energy savings from a schedule fix alone. This is the classic RCx finding: controls and schedules yield large, low-cost savings.