CDFOM · Keep the key ideas within reach.

Quick reference

Data Centre Operations Management

  • MTTR = total repair time ÷ number of repairs; MTBF = total operating time ÷ number of failures. Availability from these = MTBF ÷ (MTBF + MTTR).

  • SLA tiers are typically expressed as monthly uptime: 99.9% allows ~43.2 min downtime/month, 99.99% ~4.32 min, 99.999% ~26 s; annual equivalents are 8.76 h, 52.6 min and 5.26 min.

  • Incident vs problem: an incident is an unplanned interruption or degradation restored by a workaround; a problem is the underlying cause, closed only by a permanent fix or accepted risk.

  • Change categories: standard (pre-approved, low risk), normal (CAB review), emergency (expedited approval, retrospective review within an agreed window).

  • Escalation has two axes: functional (to deeper expertise) and hierarchical (to higher authority); both need defined trigger times in the operations manual.

  • KPI set commonly includes PUE, SLA attainment %, incident count by severity, MTTR, change success rate, first-time-fix rate and capacity headroom %.

  • PUE = total facility energy ÷ IT equipment energy; it is a ratio with no unit and is measured over a defined period, not instantaneously.

  • Shift handover record must state open incidents, pending changes, active permits, alarms suppressed or inhibited, and outstanding vendor visits.

Quick reference

Facilities Management and Maintenance

  • Planned maintenance splits into preventive (time- or usage-based) and predictive (condition-based, triggered by trend data such as vibration or thermal rise).

  • Reactive maintenance is corrective after failure; deferred corrective work must be risk-ranked, not simply queued by date.

  • Maintenance contract types: comprehensive (parts, labour, consumables included), non-comprehensive (labour only), and OEM service level agreements tied to warranty terms.

  • Key contract terms to verify: response time vs fix time, escalation path, spares held on site, reporting obligations, KPI credits, and exclusions.

  • Battery strings: IEEE 1188-style practice uses periodic impedance/conductance checks; a rising impedance trend against baseline flags a weak jar before capacity test failure.

  • UPS and generator testing cadence commonly: UPS battery test monthly, full load bank annually; generator exercise monthly with annual load-bank test at rated capacity.

  • Infrared thermography of electrical distribution should be done under load; a loaded scan is required for meaningful results, and findings are ranked by temperature delta.

  • CMMS records must link asset, work order, procedure, technician, spares consumed and outcome, so that maintenance history supports reliability analysis.

Quick reference

Safety, Security and Environmental Management

  • Electrical arc flash boundary and incident energy depend on available fault current, clearing time and working distance; work inside the boundary requires rated PPE and an energised work permit.

  • Lockout/tagout sequence: notify, shut down, isolate, lock and tag, release stored energy, verify absence of voltage, then work; removal reverses with verification.

  • NFPA 75/76-style guidance: detection should be cross-zoned (two independent detectors) before agent release or power isolation, to limit false discharges.

  • Gaseous suppression agents (clean agents) require room integrity testing; a door fan test verifies the enclosure holds agent concentration for the designed hold time.

  • Environmental envelope is commonly 18-27 °C and 40-60% relative humidity for ASHRAE A1-class equipment; excursions must be logged and correlated with hardware faults.

  • Physical security layers: perimeter, building envelope, data hall, cabinet, and logical access; each layer needs its own access control, logging and alarm response.

  • Visitor management: pre-registration, identity verification, escorted access, badge issue and return, and retention of access logs for the audit period.

  • High-availability fire detection must not be disabled for hot work without a documented impairment permit and compensatory measures such as fire watch.

Quick reference

Staffing, Training and Competence Management

  • Shift coverage formula: required FTEs = (24 h × 7 d × positions staffed) ÷ (average weekly hours per FTE × availability factor), then add relief for leave and sickness.

  • A common relief factor is 1.15-1.25 for planned absence and training; critical sites often staff to N+1 per shift so one absence does not reduce below minimum.

  • Competence is evidenced by three elements: training completed, assessment passed, and supervised practice signed off by an authorised assessor.

  • Authorisation to perform switching or work on critical systems should be a named, time-limited, revocable permit held by the individual, not a team attribute.

  • Shift pattern design must respect local working-time rules on maximum consecutive hours, minimum rest between shifts, and night-work limits.

  • Skills matrix maps each role against required competencies; gaps are shown as a dated training plan with an owner, not as a narrative.

  • Vendor and contractor staff require site induction, escort or authorisation level, and competence evidence before unescorted access to critical areas.

Quick reference

Governance, Compliance and Risk Management

  • Risk score = likelihood × impact; each risk register entry needs an owner, a treatment (avoid, reduce, transfer, accept), a target date and a residual score.

  • ISO/IEC 27001 covers information security management; ISO 22301 covers business continuity; ISO 50001 covers energy management; ISO 41001 covers facility management.

  • An audit finding is classified by severity (major, minor, observation); major findings require root-cause analysis and a corrective action plan with a verified closure date.

  • Document control requires version number, effective date, author, approver, and a defined review cycle; superseded documents must be withdrawn from use.

  • Separation of duties: the person who approves a change should not be the sole person who implements and verifies it on critical systems.

  • A risk register differs from an issue log: risks are uncertain future events, issues are realised events requiring action now.

  • Evidence retention for compliance is typically aligned to the longest applicable requirement among contract, certification body and regulator.

Quick reference

Capacity, Availability and Continuity Management

  • Concurrent maintainability is the property that any single component can be maintained while the system remains available; it requires N+1 or better at every dependency, including power and cooling paths.

  • Tier-style topology: N = no redundancy, N+1 = one redundant component, 2N = fully duplicated paths, 2N+1 = duplicated plus one extra; verify the actual path, not the nameplate.

  • Capacity headroom is tracked as % of design capacity used; thresholds commonly trigger action at 70% (plan), 80% (order), 90% (expedite).

  • Power capacity check: rack kW × quantity plus cooling and losses, compared against UPS and PDU ratings with derating applied for continuous load.

  • RTO is the maximum acceptable time to restore a service; RPO is the maximum acceptable data loss measured in time. They drive backup and replication design.

  • Single points of failure are found by tracing each utility path end to end, including control systems, and confirming no shared component exists.

  • Continuity exercises should include a no-notice element and a documented debrief; untested plans are treated as unproven in audit.

  • Cooling capacity depends on delta-T and airflow as well as nominal kW; hot spots can occur well below nominal capacity due to bypass airflow.