CDFOM key terms
CDFOM · Get comfortable with the vocabulary.
- Service Level Agreement (SLA)
- Related: Key Performance Indicator (KPI), Operational Level Agreement (OLA)
A written contract between the data centre provider and its customer that states the services delivered, the measurable performance targets, and the remedies if those targets are missed.
- Key Performance Indicator (KPI)
- Related: Service Level Agreement (SLA), Mean Time to Repair (MTTR)
A quantifiable measure chosen to show whether an operational process is meeting its target, such as percentage of change requests completed on schedule or average time to resolve incidents.
- Operational Level Agreement (OLA)
- Related: Service Level Agreement (SLA), Incident Management
An internal agreement between teams inside the same organisation that fixes the responsibilities and response times each team owes the others so that external service commitments can be met.
- Incident Management
- Related: Problem Management, Mean Time to Repair (MTTR)
The process for detecting, logging, escalating, and restoring service after an unplanned disruption, with priority set by business impact rather than by the technical size of the fault.
- Problem Management
- Related: Incident Management, Root Cause Analysis (RCA)
The discipline of finding and eliminating the underlying causes of repeated incidents, usually through root cause analysis, so that the same failure does not recur.
- Change Management
- Related: Configuration Management Database (CMDB), Method of Procedure (MOP)
A controlled process in which planned alterations to facilities, systems, or configurations are assessed for risk, approved by authorised staff, scheduled, implemented, and then verified.
- Method of Procedure (MOP)
- Related: Standard Operating Procedure (SOP), Change Management
A step-by-step written instruction for carrying out a specific task safely, including prerequisites, sequence of actions, verification points, and the rollback plan if the task fails.
- Standard Operating Procedure (SOP)
- Related: Method of Procedure (MOP), Competence Matrix
A documented routine instruction describing how a recurring operational activity is performed consistently, used for training staff and for demonstrating that work follows an approved method.
- Planned Preventive Maintenance (PPM)
- Related: Condition-Based Maintenance (CBM), Corrective Maintenance
Scheduled servicing carried out at fixed intervals or according to equipment run hours to reduce the likelihood of failure and to keep manufacturer warranties valid.
- Corrective Maintenance
- Related: Planned Preventive Maintenance (PPM), Mean Time to Repair (MTTR)
Work performed to restore a failed or degraded asset to acceptable operating condition, ranging from minor repair to full component replacement after a breakdown.
- Condition-Based Maintenance (CBM)
- Related: Planned Preventive Maintenance (PPM), Predictive Maintenance
Maintenance triggered by measured evidence of deteriorating condition, such as vibration analysis, thermography, or oil sampling, rather than by a fixed calendar interval.
- Mean Time Between Failures (MTBF)
- Related: Mean Time to Repair (MTTR), Availability
The average operating time between one failure and the next for a repairable asset, used to compare equipment reliability and to forecast spare-parts demand.
- Mean Time to Repair (MTTR)
- Related: Mean Time Between Failures (MTBF), Availability
The average elapsed time needed to restore an asset to service after failure, including diagnosis, access, repair, and testing, and a key driver of achieved availability.
- Critical Spares
- Related: Mean Time to Repair (MTTR), Concurrent Maintainability
Spare parts and components held on site because their absence would extend an outage beyond the tolerated limit, selected by failure impact and supplier lead time.
- Concurrent Maintainability
- Related: Redundancy (N+1), Critical Spares
The property of a design that allows any item of plant to be serviced or replaced while the IT load continues to be supported, typically by redundant capacity and isolation points.
- Redundancy (N+1)
- Related: 2N Configuration, Concurrent Maintainability
Provision of one more capacity unit than the load requires, so that a single failure or maintenance shutdown does not interrupt service to the supported IT equipment.
- 2N Configuration
- Related: Redundancy (N+1), Availability
A topology in which two complete, independent capacity paths are installed, each able to carry the full load alone, giving protection against a single failure at any point.
- Availability
- Related: Mean Time Between Failures (MTBF), Mean Time to Repair (MTTR)
The proportion of time a system is capable of performing its intended function, usually expressed as a percentage over a period and derived from failure frequency and repair duration.
- Uninterruptible Power Supply (UPS)
- Related: Standby Generator, Power Usage Effectiveness (PUE)
A battery-backed system that supplies conditioned power to IT loads for a short bridging period until generators start or the mains supply recovers.
- Standby Generator
- Related: Uninterruptible Power Supply (UPS), Business Continuity Plan (BCP)
An engine-driven alternator kept ready to supply the facility when the utility feed fails, requiring periodic load testing and fuel quality management to remain dependable.
- Power Usage Effectiveness (PUE)
- Related: Uninterruptible Power Supply (UPS), Thermal Management
Total facility energy divided by the energy delivered to IT equipment; a ratio where 1.0 is theoretical perfection and higher values indicate more overhead energy use.
- Thermal Management
- Related: Hot/Cold Aisle Containment, Power Usage Effectiveness (PUE)
Control of temperature and humidity in white space through cooling equipment, airflow containment, and setpoints so that equipment stays within manufacturer operating envelopes.
- Hot/Cold Aisle Containment
- Related: Thermal Management, Power Usage Effectiveness (PUE)
A physical arrangement that separates equipment intake air from exhaust air using barriers and aisle layout, preventing recirculation and improving cooling efficiency.
- Business Continuity Plan (BCP)
- Related: Disaster Recovery Plan (DRP), Recovery Point Objective (RPO)
A documented set of arrangements that keeps essential services running during and after a disruption, covering people, processes, and technology dependencies across the organisation.
- Disaster Recovery Plan (DRP)
- Related: Business Continuity Plan (BCP), Recovery Time Objective (RTO)
The technical component of continuity planning that describes how IT systems and data are restored at an alternate location after a major loss of the primary facility.
- Recovery Time Objective (RTO)
- Related: Recovery Point Objective (RPO), Disaster Recovery Plan (DRP)
The maximum acceptable elapsed time between a disruption and the restoration of a service, used to size standby capacity and staffing for recovery.
- Recovery Point Objective (RPO)
- Related: Recovery Time Objective (RTO), Business Continuity Plan (BCP)
The maximum acceptable amount of data loss measured in time before a disruption, which determines how frequently backups or replication must occur.
- Capacity Planning
- Related: Rack Power Density, Availability
Forecasting future demand for power, cooling, space, and network ports, then scheduling investment so that headroom is available before limits are reached.
- Rack Power Density
- Related: Capacity Planning, Thermal Management
The electrical load a single rack is designed or permitted to draw, expressed in kilowatts, which drives cooling design, cabling choices, and floor loading assumptions.
- Physical Access Control
- Related: Visitor Management, Security Zone
Layered measures such as badge readers, mantraps, biometrics, and visitor escort rules that ensure only authorised people reach defined security zones.
- Security Zone
- Related: Physical Access Control, Visitor Management
A defined area of the facility with its own access rules and threat level, so that controls tighten progressively from the perimeter through offices to the white space.
- Visitor Management
- Related: Physical Access Control, Security Zone
The process of pre-registering, identifying, badging, escorting, and logging external people on site, and confirming their departure, to prevent unauthorised presence.
- Permit to Work (PTW)
- Related: Lockout/Tagout (LOTO), Method of Procedure (MOP)
A formal authorisation issued before high-risk activity such as hot work or electrical isolation, recording hazards, controls, isolations, and the person accountable for the task.
- Lockout/Tagout (LOTO)
- Related: Permit to Work (PTW), Method of Procedure (MOP)
A safety procedure that isolates energy sources and attaches personal locks and tags so equipment cannot be re-energised while someone is working on it.
- Competence Matrix
- Related: Standard Operating Procedure (SOP), Shift Handover
A grid mapping each staff member against the skills and authorisations their role requires, used to plan training and to confirm shift coverage by qualified people.
- Shift Handover
- Related: Competence Matrix, Incident Management
A structured briefing at change of shift that transfers open incidents, pending changes, equipment status, and site risks to the incoming team in a recorded format.
- Root Cause Analysis (RCA)
- Related: Problem Management, Incident Management
A structured investigation method that traces an incident back to its underlying causes rather than the immediate trigger, producing actions that prevent recurrence.
- Configuration Management Database (CMDB)
- Related: Change Management, Root Cause Analysis (RCA)
A repository recording the facility and IT assets, their attributes, and the dependencies between them, used to assess change impact and support fault diagnosis.
- Audit Trail
- Related: Configuration Management Database (CMDB), Physical Access Control
A chronological, tamper-evident record of who did what and when across access, change, and maintenance systems, relied on during investigations and compliance reviews.